=(0.5×1.4+0.3×0.4)/(1.4+0.4)
=0.46
②计算沟槽土方工程量
S断1=[(b+2×0.3)+ kh] ×h +(b'+2×0.1)×h'
=[(0.9+2×0.3)+0.46×1.8] ×1.8 +(1.1+2×0.1×0.1
=4.32 m2
J1 : L中=24+(10.8+3+5.4)×2=62.4m V挖1= S断1 × L中=4.32×62.4=269.57 m3 S断2=[(b+2×0.3)+ kh] ×h +(b'+2×0.1)h'
=[(1.1+2×0.3)+0.46×1.8] ×1.8 +(1.3+2×0.1)×0.1 =4.70 m2
J2 : L中=3×6=18m
L净=[5.4-(1.1+1.3)/2]×7+[3-1.1/2-(1.1 +1.3)/4] ×2=33.1m L=18 +33.1 =51.1 m
V挖2= S断×L=4.70×51.1=240.17 m3
沟槽土方工程量合计: V挖= 269.57+240.17=509.74 m3 (4)混凝土基础工程量
J1:[24+10.8×2+3×2+(5.4-1.1/2)×2] ×[(0.37+1.1)×0.35/2+1.1×0.3]
=61.3×0.587 =35.98m3
J2:[24-1.3+(5.4-1.3/2-1.1/2)×7] ×[(0.37+0.9)×0.35/2+0.9×0.3]
= 52.1×0.49 =25.65m3
基础总量=J1+J2=61.63m3 (5)素混凝土垫层工程量
J1:[24+10.8×2+3×2+(5.4-1.1/2)×2] ×1.3×0.1=7.97m3 J2:[24-1.3+(5.4-1.3/2-1.1/2)×7] ×1.1×0.1=5.73m3
垫层总量=J1+J2=13.7m3 (3)余土外运工程量
地面以下墙的体积:(24×2+5.4×13+3×2)×[0.24×(1.8-0.65)]
=124.2×0.276 =34.28m3
余土外运量=509.74-61.63-13.7-34.28=400.13m3