低压动照单系统及接口调试方案

目 录

1总则 ................................................................................................. 4

1.1调试依据 ........................................................................................................... 4 1.2项目概况 ........................................................................................................... 4 1.3系统组成 ........................................................................................................... 5 1.4调试目的 ........................................................................................................... 5 1.5调试流程 ........................................................................................................... 6 1.6项目进度及人员安排 ....................................................................................... 7

1.6.1项目进度 ................................................................................................ 7 1.6.2人员安排 .............................................................................................. 24

2单机、单系统调试方案 .................................................................. 27

2.1 EPS应急照明电源装置单机、单系统调试方案 ......................................... 27

2.1.1系统组成及功能介绍 .......................................................................... 27 2.1.2测试目的 .............................................................................................. 29 2.1.3前置条件 .............................................................................................. 29 2.1.4准备工作 .............................................................................................. 29 2.1.5测试步骤 .............................................................................................. 31 2.1.6测试报告 .............................................................................................. 35 2.2低压配电箱单机、单系统调试方案 ............................................................. 38

2.2.1系统组成及功能介绍 .......................................................................... 38 2.2.2测试目的 .............................................................................................. 39 2.2.3前置条件 .............................................................................................. 40 2.2.4准备工作 .............................................................................................. 40 2.2.5测试步骤 .............................................................................................. 41 2.2.6测试报告 .............................................................................................. 43 2.3环控柜单机、单系统调试方案 ..................................................................... 46

2.3.1系统组成及功能介绍 .......................................................................... 46 2.3.2测试目的 .............................................................................................. 46 2.3.3前置条件 .............................................................................................. 46 2.3.4准备工作 .............................................................................................. 47 2.3.5测试步骤 .............................................................................................. 48 2.3.6测试报告 .............................................................................................. 51 2.4 400V智能低压开关柜单机、单系统调试方案 ........................................ 52

2.4.1功能介绍 .............................................................................................. 52

低压动照单系统及接口调试方案

2.4.2测试目的 .............................................................................................. 53 2.4.3前置条件 .............................................................................................. 53 2.4.4准备工作 .............................................................................................. 54 2.4.5测试步骤 .............................................................................................. 54 2.4.6测试报告 .............................................................................................. 59 2.5 防淹门系统 .................................................................................................... 60

2.5.1系统概述 .............................................................................................. 60 2.5.2调试组织机构及职责 .......................................................................... 60 2.5.3前置条件 .............................................................................................. 61 2.5.4调试仪器仪表 ...................................................................................... 61 2.5.5调试方案 .............................................................................................. 61 2.6.6调试报告 .............................................................................................. 67

3接口调试方案 ................................................................................ 68

3.1 EPS应急照明电源装置接口调试方案 ......................................................... 68 3.2低压配电箱接口调试方案 ............................................................................. 68 3.3环控柜接口调试方案 ..................................................................................... 68 3.4 400V智能低压开关柜接口调试方案 ........................................................... 69

4安全管理及应急预案 ..................................................................... 69

4.1安全管理 ......................................................................................................... 69 4.2应急预案 ......................................................................................................... 69

4.2.1应急组织机构 ...................................................................................... 69 4.2.2工作要求 .............................................................................................. 72 4.2.3应急预案的实施 .................................................................................. 72 5.2.4现场抢险 .............................................................................................. 74 4.2.5现场抢险安全事故应急救援流程 ...................................................... 74 4.2.6事故报告 .............................................................................................. 74

5测试记录表 .................................................................................... 76

5.1EPS应急照明电源装置测试记录表 .............................................................. 76 5.2低压配电箱测试记录表 ................................................................................. 80

5.2.1低压配电箱常规测试记录表 .............................................................. 80 5.2.2低压配电箱照明灯箱手动及BAS控制测试记录表 ......................... 81 5.2.3低压配电箱智能照明手动及BAS控制测试记录表 ......................... 82 5.2.4低压配电箱电动蝶阀控制箱控制测试记录表 .................................. 83 5.2.5低压配电箱消防风机控制箱控制测试记录表 .................................. 84 5.2.6低压配电箱应急照明及消防切非控制箱FAS控制测试记录表 ..... 85

低压动照单系统及接口调试方案

5.2.7低压配电箱普通排风、排烟风机控制箱BAS控制测试记录表 ..... 86 5.2.8低压配电箱消防电源监控系统ISCS测试记录表 ............................ 87 5.3环控柜测试记录表 ......................................................................................... 88

5.3.1环控柜单机测试记录表 ...................................................................... 88 5.3.2环控柜单系统测试记录表 .................................................................. 94 5.4 400V智能低压开关柜测试记录表 ............................................................. 121

低压动照单系统及接口调试方案

1总则 1.1调试依据

动力与照明专业施工图纸; 厂家提供的相关技术资料;

《消防应急照明和疏散指示系统》GBl7945—2010; 《地铁设计规范》GB 50157-2013;

《低压成套开关设备和控制设备》GB 977251.1—2013; 《电气装置安装工程蓄电池施工及验收规范》GB 50172—1992; 《低压配电设计规范》GB 50054—1995;

《建筑电气施工质量验收规范》GB50303-2015等相关国家规范。

1.2项目概况

成都地铁5 号线一、二期工程,线路全长49km,其中地下线42.25km,高架线6.45km,过渡段0.3km;共设车站41 座,其中地下站36 座,高架站5 座;换乘站14 座(高架1 座,地下13 座);最大站间距2110m,为鹤高路~蒋家店区间;最小站间距670m,为石羊立交~繁雄大道区间;平均站间距1207m。全线共设综合维修基地1 座、停车场2 座、主变电站4 座,控制中心与在建的7 号线合设于7 号线崔家店停车场内。

低压配电与动力照明系统是由降压变电所0.4kV低压开关柜馈出至用电末端设备的配电系统,包括:智能低压配电、动力照明设备的配电,动力照明设备的控制,配电设备的选型及安装,低压电缆、管线的选型及敷设,防雷、接地及安全,及与其他相关专业的接口等。

低压动照单系统及接口调试方案

1.3系统组成

低压配电与动力照明系统主要由400V智能低压开关柜、低压配电箱系统、应急照明电源装置配电系统和环控系统组成。

400V智能低压开关柜:采用西门子PLC采集所有断路器的状态及所有表计的电参量与PSCADA后台通讯,PLC运行备自投逻辑,保证线路供电可靠,包括电气火灾监控系统。

低压配电箱系统包括:智能照明控制系统,消防电源监控系统、广告照明系统,导向照明系统,区间疏散指示系统,电动蝶阀控制系统,消防专用风机控制系统,应急照明控制系统,普通排风、排烟风机控制系统。

应急照明电源装置配电系统包括:交流配电单元、充电单元、逆变单元、馈电单元、智能监控单元、蓄电池单元等。

环控系统包括:大系统配电控制系统、小系统配电控制系统、隧道通风配电控制系统。

1.4调试目的

成都地铁5号线工程单机、单系统调试是各系统完成设备安装后由施工单位组织进行的、以系统就地功能调试及测试为主的、使相关设备及系统可以进行正常运转的调试工作。单机单系统调试工作的主要目的如下:

(1)使相关设备系统能达到正常运行状态。

(2)检查个机电设备系统功能、性能是否达到设计要求。 (3)发现设备系统安装期间的缺陷,并加以修正。 (4)检验各系统带负荷运行情况。


地铁低压动照调试方案 - 图文.doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:高中生物学考知识点总结(完整版)

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: