中铁四局集团第四工程有限公司遵贵扩容工程第4-B合同段项目经理部
目 录
目 录 ······························································································································· 1 1、编制说明 ······················································································································· 1
1.1 编制依据 ················································································································ 1 1.2 编制原则 ················································································································ 1 1.3 规范、标准 ············································································································· 1 2、工程概况 ······················································································································· 2
2.1 工程简介 ················································································································ 2 2.2设计概况 ················································································································· 2 2.3自然条件 ················································································································· 3
2.3.1地形地貌 ········································································································ 3 2.3.2工程地质条件·································································································· 3 2.3.3水文条件 ········································································································ 4 2.3.4不良地质 ········································································································ 5 2.3.5进出口段围岩评价 ··························································································· 6 2.3.6进出口边仰坡稳定性评价 ·················································································· 8 2.4主要技术标准 ··········································································································· 9 2.5主要工程量 ············································································································· 10 2.6计划工期 ························································································ 错误!未定义书签。 2.7施工条件 ················································································································ 10
2.7.1 施工便道 ······································································································ 10 2.7.2 施工用电 ······································································································ 11 2.7.3 施工用水 ······································································································ 11 2.8建设相关单位 ·········································································································· 11 3、工程重难点分析及施工对策。 ··························································································· 11 4、施工进度计划 ················································································································ 11
4.1总体计划安排 ·········································································································· 11 4.2主要工序作业时间分析 ····························································································· 11 4.3主要工序施工进度计划 ····························································································· 11 5、施工工艺技术 ················································································································ 13
5.1 总体施工方案 ········································································································· 13 5.2施工准备 ················································································································ 13
5.2.1隧道进口场地布置 ·························································································· 13
1
中铁四局集团第四工程有限公司遵贵扩容工程第4-B合同段项目经理部
5.2.2隧道进口场地布置 ·························································································· 13 5.2.3技术准备 ······································································································· 14 5.2.4物资准备 ······································································································· 14 5.2.5施工测量 ······································································································· 14 5.2.6工程试验准备································································································· 14 5.2.7二衬台车拼装场地填筑 ···················································································· 14 5.3 主要施工方法及工艺 ································································································ 15
5.3.1 洞口测量放样 ································································································ 15 5.3.2 洞顶截水沟 ··································································································· 15 5.3.3 边仰坡开挖、支护 ·························································································· 16 5.3.4套拱施工 ······································································································· 18 5.3.5 大管棚施工 ··································································································· 19 5.3.6 暗洞施工 ······································································································ 23
6、劳动力、机械配置计划 ···································································································· 41 7、施工安全保证措施 ·········································································································· 42 8、其它技术保证措施 ·········································································································· 44 9、附图、附表 ··················································································································· 46
2
中铁四局集团第四工程有限公司遵贵扩容工程第4-B合同段项目经理部
1、编制说明 1.1 编制依据
(1) 与业主签订的工程承包合同、协议、会议纪要。
(2) 遵贵扩容工程第4-B合同段上甘坪隧道施工设计图纸及相关设计文件。 (3)投标书承诺的工期节点、合同要求的工期、质量及环境保护要求。 (4)国家、行业、地方有关职业健康安全的要求。 (5)对本项目现场和施工条件调查掌握的有关资料。 (6)国家现行施工和设计规范、验收标准及业主的有关规定。
(7)工程项目部的组成、机械设备、各类技术人员配备及施工队伍作业能力的基本情况。 1.2 编制原则
(1) 贯彻国家的相关方针、政策及及有关工程施工规范、规定,当地政府的相关制度。
(2) 整个工程统筹组织,合理安排各专业施工顺序和工序的衔接,突出重点项目和关键工序,统筹兼顾,均衡生产,确保工期兑现。
(3) 从组织机构、施工方案、机械设备配备、工程材料供应等方面确保工程质量、施工进度和施工安全。
(4) 质量创优、安全无事故,执行GB/T19001标准,确保质量第一,保证施工人员人身健康安全。
(5) 临时工程本着节约用地、满足施工、精打细算的原则安排。 (6) 充分考虑并做好环境保护工作。 1.3 规范、标准
(1)公路工程技术标准 (JTG BO1-2014) (2)公路隧道施工技术规范 (JTG F60-2009) (3)公路工程质量检验评定标准 (JTG F80/1-2004) (4)公路工程施工安全技术规范 (JTGF9—2015) (5)爆破安全规程 (GB6722-2014) (6)《锚杆喷射混凝土支护技术规范》 (GB50086-2001)
1
中铁四局集团第四工程有限公司遵贵扩容工程第4-B合同段项目经理部
2、工程概况 2.1 工程简介
上甘坪隧道为一座上、下行分离的六车道高速公路中隧道,位于楠木渡镇黄木村至楠木渡镇临江村区间,隧道起讫桩号左线ZK40+995~ZK42+060,长1065m;右线YK40+980~YK42+085,长1105m,洞身最大埋深90m,最小埋深4m。 2.2设计概况
本隧道均采用端墙式洞门,洞口段设计均采用长管棚进行支护。隧道洞口围岩支护参数详见表2.1-1。
平面线形:隧道遵义端位于直线段上,平面线位线间距为24.4m,洞身处于右偏圆曲线及缓和曲线段上,贵阳端位于直线段上,平面线位线间距为26.1m,隧道最大平面线位间距位于洞身,为34m。
纵断面线形:本隧道左、右线遵义端洞口位于直线段上,贵阳端洞口纵断面分别位于R=30000m、R=25000m凹型竖曲线上;左、右线洞身直坡段纵坡分别为3.000% +2.333%,3.000% +1.935%。
路面横坡:本隧道洞口段左、右线均为2%单向横坡。洞身左线存在3%超高及其缓和段。
上甘坪隧道按照规范及安全要求,设置了1处车行横洞,2处人行横洞。
表2.1-1 隧道洞口围岩支护参数表 里程、段落 位长度围岩级别 30cmC20ZK41ZK41喷射砼,60cmC23 V1 S-Va 20*20双层钢筋网 30cmC20ZK41ZK42喷射砼,60cmC35 V2 S-Va 20*20双层钢筋网 右YK41YK4130cmC2035 V1 S-Va 喷射砼,20*20双60cmC30钢30钢筋砼 30钢筋砼 4m长φ25mm中空锚杆,间距0.5m*1.2m 4m长φ25mm中空锚杆,间距0.5m*1.2m 4m长φ25mm中空衬砌类型 喷射砼 仰拱 系统锚杆 钢支撑 辅助措施 初支 二衬 置 起始终点(m里程 里程 ) I22b@0.5m φ108mm超前长管棚,φ50mm超前小导管 φ108mm超前长管棚,φ50mm超前小导管 φ108mm超前长管棚,φ50mm超前二衬为60cmC30钢筋砼 二衬为60cmC30钢筋砼 二衬为60cmC30钢筋+015 +038 左线 I22b@0.5m +990 +025 I22b@0.5m 线 +000 +035 筋砼 锚杆,间距 2
中铁四局集团第四工程有限公司遵贵扩容工程第4-B合同段项目经理部 里程、段落 位长度围岩级别 层钢筋网 衬砌类型 喷射砼 仰拱 初支 系统锚杆 0.5m*1.2m 钢支撑 二衬 辅助措施 小导管 砼 置 起始终点(m里程 里程 ) 30cmC20YK42YK42喷射砼,60cmC35 V2 S-Va 20*20双层钢筋网 30钢筋砼 4m长φ25mm中空锚杆,间距0.5m*1.2m I22b@0.5m φ108mm超前长管棚,φ50mm超前小导管 二衬为60cmC30钢筋砼 +015 +050 2.3自然条件 2.3.1地形地貌
隧道区地形较简单,为单座山丘。山体总体呈北西走向。隧道穿越部位最高海拔934m,最低海拔817m,相对高差117m,属低山地貌。 2.3.2工程地质条件
(1).地层特征:测区基岩地层岩性主要为二迭系下统茅口组(P1m)灰岩和二迭系中统龙潭组(P2l)灰岩、泥质粉砂岩、泥岩、煤层夹灰岩及煤层等互层,分布于整个隧道测区。
测区中风化基岩局部出露,溶蚀、溶隙较发育,大部分地区被第四系地层所覆盖。地层主要为第四系(Q4)碎石土,二迭系下统茅口组(P1m)灰岩和二迭系中统龙潭组(P2l)灰岩、泥质粉砂岩、泥岩、煤层夹灰岩及煤层等互层。分述如下:
①、红粘土:棕红色,硬可塑,含泥质粉砂岩、灰岩碎块,含量约30%。 ②、碎石土:黄褐色,稍湿,粒径一般为2-6cm,最大粒径约10cm,碎石主要成分为灰岩、泥质粉砂岩,含量约60%,充填物为红粘土,结构松散,残积成因。
③、中风化灰岩(P2l):深灰色,隐晶质结构,中厚层状构造,裂隙较发育-发育,方解石石充填,岩芯较破碎,主呈柱状,节长5-25cm,最长35cm,采芯率85%-90%,岩石质量指标RQD=25-50。
④、中风化泥质粉砂岩:灰色,砂质结构,薄~中厚层状构造,裂隙发育-很发育,岩芯极破碎-破碎,在钻具的机械作用下,岩芯主呈碎块状,采芯率70%-85%,岩石质量指标RQD=0。
⑤、中风化炭质灰岩:黑色,隐晶质结构,中厚层状构造,岩质较软,裂隙较发
3