本科阶段课程设计,提供给大家参照。
3.2.2 本桩利用的-----推土机推土
工程量Q1 = 14.46+14.52+359.42+373.86-14.36-14.38=733.52 m3 3.2.3 铲运机---铲运土(k2+800—k3+000)
工程量Q2 = (1247.38+1286.89+1322.22+1355.12+1382.31+1412.14+1453.52+1498.16+
1531.52+1566.73+1601.22)*1.16=18162.37 m3
加权平均运距L=∑QL/Q=(1247.38*200+1286.89*180+1322.22*160+1355.12*140+
1382.31*120+1412.14*100+1453.52*120+1498.16*140+1531.52*160+1566.73*180+1601.22*200)*1.16/15657.21=179.36 m
3.2.4 挖掘机挖装土、自卸汽车运土(k2+000—k2+780)
工程量Q3 =(384.83+390.98+14936+887.6+912.78+940.43+968.41+995.42+1049+
1071.03+1067.47+1096.96+1124.91+1153.29+1182.6+1210.57)*1.16=34071.87 m3
加权平均运距L = ∑QL/Q = (384.83*1000+390.98*980+403.08*960+426.71*940+
414.446*920+19.6834*920+423.05*900+436.71*880+455.47*860+ 475.01*840+493.28*820+510.63*800+527.56*780+542.89*760+ 560.18*740+579.52*720+601.2*700+624.63*680+641.33*660+ 656.13*640+676.93*620+699.84*600+728.17*580+756.21*560+ 781.06*540+807.4*520+833.72*500+861.15*480+887.6*460+ 912.78*440+940.43*420+968.41*400+995.42*380+1049*360+ 1071.03*340+1067.47*320+1096.96*300+1124.91*280+ 1153.29*260+1182.6*240+1210.57*220)*1.16/29372.3 =615.1 m
3.2.5 机械碾压土方
Q = Q1 + Q2 + Q3 =733.52+18162.37+34071.87= 52967.76 m3 定额 1-1-18-8 3.2.6 整修路基
(1)整修边坡:Q=1×1000m=1000 m 定额 1-1-20-3