基坑支护设计与地下室结构施工一体化技术应用
摘要:城市中心的建筑工程越来越多,而通常此类工程,场地狭窄,受周围环境、周围建筑影响较大,特别是在地下室施工阶段,工程的施工工作往往受制于场地的限制,施工作业面不足,导致施工难度加大,对工程工期、成本造成不利影响。所以如何又快又好地解决此类密集区域内的深基坑地下室结构施工成为了当前亟待解决的问题。
关键词:建筑工程 深基坑 地下室 结构施工
Abstract: In the center of the city building is become more and more, but usually this kind of engineering, narrow space, by the surrounding environment, the surrounding buildings greatly, especially in the basement construction phase. Construction project is often restricted by the site, construction operation, leading to the construction difficulty. So how to rapidly and efficiently solve such dense deep foundation pit basement structure construction area has become an urgent problem to be solved.
Keywords: building engineering; deep foundation pit; basement structure construction;
基坑支护设计与地下室结构施工一体化技术
作为地下室结构施工的前一阶段,基坑支护设计及施工阶段在整个工程的施工过程中显得尤为重要,如何结合地下室结构施工阶段的施工特点进行策划,预见下阶段施工过程中将遭遇的问题,并且最大限度地将地下室结构施工难度降低。基坑支护设计与地下室结构施工一体化技术正是基于此原则,通过以下四个方面:(1)保证关键线路工期;(2)利于下一阶段的总平面布置;(3)提高出土效率;(4)提高拆撑效率从而提高地下室施工速度,实现地下室结构施工高速、高效地开展。
保证关键线路工期
在进行基坑支护设计前,首先理清整个工程施工的关键线路,从整个项目全周期出发,减少或者避免基坑支护工程对项目总工期的限制,在具体设计中主要表现为减少支护结构对工程结构的影响,以常规的高层建筑为例,支护的内撑结构应尽量避开主塔楼区域,确保主塔楼区域能够在不受基坑支护结构施工及拆除的影响,此外,塔楼区域应为首先施工区域,避免由于基坑支护造成的关键线路工期加长。