c. 平行实施更多的关键路径任务。
d. 与管理层一起审核原始的项目计划并讨论可以缩短项目时间的范围变更。
47. The scope of work is completed on a project. However, the customer is not happy because they want additional work to be completed. In light of this, what should be done?
A. Begin closure on the contract and sign a new one for the additional work. B. Change to a cost reimbursable contract.
C. Tell the customer it is too late to make a change.
D. Add to scope of work and proceed with additional work after obtaining management’s agreement.
一个项目的工作范围已经完成, 然而, 客户并不满意, 因为他们要求完成额外的工作。据此,应该怎样做?
a. 根据合同开始收尾,并对额外的工作签订新的合同。 b. 变更为成本可回收合同。
c. 告诉客户,太晚了,不能做变更了。
d. 得到管理层同意后,把额外的工作加入工作范围并开始实施。
48. All of the following are part of the project initiation phase EXCEPT?
A. Understand the criteria that will be used to evaluate the project manager. B. Create the project charter.
C. Develop project-related product description. D. Identify the full project team.
下列各项中哪一项不属于项目启动阶段的工作?
a. 了解将用于评估项目经理的标准 b. 建立项目规章
c. 建立项目相关产品的描述 d. 确定完整的项目团队
49. To control the schedule, a project manager is re-analyzing the project to predict project duration. She does this by analyzing the sequence of activities with the least amount of scheduling flexibility. What technique is she using? A. Critical path. B. Flow chart.
C. Precedence diagramming. D. Work breakdown structure.
为了管理进度,一个项目经理正在对项目进行重新分析以便预测项目历时。她是通过使用进度灵活性的最小量来分析活动的顺序从而预测项目历时的。她使用的是什么技术?
a. 关键路径 b. 流程图 c. 优先图表 d. 工作分解结构
50. A PM is working as part of a bid team on a bid the company believes they must win. The delivery costs calculated by the PM appear to high to win and the PM is asked to drop his estimate of the cost in order to help win the bid. However it means that the company is likely to not make a profit if he drops his cost estimates. What should the PM do?
A. he should drop the price and win the business and then make up the loss on change orders.
B. submit the bid with current cost calculations and hope for the best. C. let someone else make the decision of what to do.
D. propose that the costs remain and they look at ways to reduce the price. 一名项目经理是公司一个志在必得项目的竞标小组成员。由这个项目经理估算的交付成本过高而不能在投标中获胜,为了中标,该项目经理被要求降低他的成本估算,然而这样就意味着公司最终没有利润。这时,项目经理该怎么做?
a. 他应该降低报价,获得这笔生意,然后从变更订单中弥补差额 b. 提交目前估算成本的标书,期望最好结果 c. 让其他人做出行动决策
d. 提议维持这个成本,寻找其他方法降低价格
51. Documents that serve as historical records for future projects are archived: A. Throughout the project. B. Before the end of planning. C. Before the end of execution. D. During closure.
作为供将来项目使用的历史记录的文件存档工作应在-------进行。
a. 项目的全过程 b. 计划编制结束之前 c. 执行阶段结束之前 d. 项目收尾过程中
52. Your management has decided that all orders will be treated as a “project” and that project managers will be used to update orders daily, resolving issues and ensuring that the customer formally accepts the product within 30 days of completion. The revenue from the individual orders can vary from US $100 to US $150,000. The project manager will not be required to perform planning or provide documentation other than daily status. How would you define this situation?
A. Because each individual order is a “temporary endeavor”, each order is a project. This is truly project management.
B. This is program management since there are multiple projects involved. C. This is a recurring process.
D. Orders incurring revenue over US $100,000 would be considered projects and would involve project management.
你的管理层决定把所有的订单都作为项目对待, 项目经理用于订单的日常
更新, 解决问题并确保客户在产品完成后30天内正式收到产品。订单的收入从100美元到150,000美元不等。只要求项目经理做日常状态报告,不需要做计划或提供文件。你如何定义这种情况?
a. 由于每份订单都是一项临时性任务, 每份订单都是一个项目。因此,这是真实的项目管理。
b. 由于涉及多个项目,因此,这是超大型项目管理。 c. 这是一种重复过程。
d. 所发生的收入超过100,000美元的订单应看作是项目,并涉及到项目管理。
53. All of the following are found on a control chart EXCEPT? A. Rule of two.
B. Assignable cause. C. Control limit. D. Sample.
下列哪项不在控制图中?
a. 两点原则 b. 可指定的原因 c. 控制范围 d. 例子
54. You are working on a large construction project that is progressing within the baseline. Resource usage has remained steady, and your boss has just awarded you a prize for your performance. One of your team members returns from a meeting with the customer and tells you the customer said they are not happy with the project progress. What is the FIRST thing you should do? A. Tell your manager.
B. Complete a team building exercise and invite the customer’s representatives. C. Change the schedule baseline.
D. Meet with the customer to uncover details.
你正在从事于一个大型建筑项目,这个项目的进展在基线之内。资源使用保持的很稳定,并且你的上司刚刚对你的绩效给予了奖励。你的一个团队成员从与用户的会议上回来后告诉你,用户说他们对项目的进展情况不满意。你首先应该做什么?
a. 告诉你的经理
b. 制定一个团队建设实施计划,并邀请用户代表 c. 更改进度计划基线 d. 会见用户,了解详情
55. The project manager has a project that is three months behind but, surprisingly, markedly under budget. She has decided to try to make up time, but wants to avoid rework. What should she do? A. Crash.
B. Fast track.
C. Redefine the scope. D. Resource level.
一个项目经理的项目已经延误了3个月,令人吃惊的是这个项目还远远没有超支,仍在预算之内。这个经理决定要努力赶上进度,但还要避免返工。她应当怎样做?
a. 赶工。
b. 快速跟进。 c. 重新定义范围。 d. 平衡资源。
56. Customer influence in the project planning process is: A. Meddlesome and will slow down progress.
B. Essential in accurately documenting the goals and objectives of the project. C. A minor consideration because the customer has difficulty in stating what he wants .
D. Best handled by the sales department. 客户在项目计划编制过程中的影响是: A. 好干涉,使进程放慢
B. 在精确地形成项目目标文件过程中很重要 C. 是不用过多考虑的,因为难于说明他想要的 D. 由销售部门处理是最佳的
57. During the course of your project, you notice that most of the changes occurring on the project come from the research department. What should the project manager do?
A. Assign a team member to work solely with the research department.
B. Change your communication plan, so only you are assigned to interact with the research department.
C. Ask the research department to assign one person to be your liaison.
D. Talk to the research department to understand the reasons for the changes. 在你的项目进程中,你注意到,项目上发生的多数变更都来自研究部门。项目经理应该怎样做?
a. 分配一个团队成员单独与研究部门打交道。
b. 改变你的沟通计划,以便只有你负责与研究部门沟通。 c. 请研究部门派一个人作为你的联络人。 d. 与研究部门商谈,以便理解变更的原因。
58. Your boss, the vice president of research at your electronic system development firm, defines success on the project as providing “state-of-the-art” development. The vice president of marketing defines it as “world-class practices.” The vice president of engineering, who is the customer for this project, is primarily concerned with new features. Which of the following BEST describes what you should do?
A. Make sure the requirements are defined in measurable terms B. Concentrate on new features.
C. Identify additional stakeholders that want new features to shift the balance in that direction.
D. Concentrate on making the project state-of-the-art.
你的老板,电子系统开发公司的研究副总裁把项目的成功定义为:提供“艺术级的”开发;市场副总裁则把它定义为:世界级的惯例;而工程设计副总裁是这个项目的用户,他主要关心的是新的特性。下列哪项最能表达你应该做的?
a. 确保对要求使用可测量的条件来定义。 b. 集中精力在新特性上。
c. 识别另外需要新特性的项目干系人,使平衡向新特性方向移动。 d. 集中精力把项目做成“艺术级的”开发。
59. You’ve been assigned to take over managing a project that should be half-complete according to the schedule. You discover that the project is running far behind schedule, and that the project will probably take double the time originally estimated by the previous project manager. However, upper management has been bold that the project is on schedule. What is the BEST course of action?
A. Try to restructure the schedule to meet the project deadline. B. Report your assessment to upper management.
C. Turn the project back to the previous project manager.
D. Move forward with the schedule as planned by the previous project manager and report at the first missed milestone.
你被分配接管一个项目的管理工作,根据进度计划,这个项目应该已经完成了一半。你发现这个项目远远落后与进度计划,如果用原来的项目经理,完成这个项目的时间将可能是原始估算时间的两倍。但是,上级管理层已经被告知,这个项目是按进度计划进行的。最佳的行动方针是什么?
a. 争取调整进度计划,以便满足项目的最终期限。 b. 向上级管理层提交你的评估报告。 c. 把项目交回前一个项目经理。
d. 根据前一个项目经理计划的进度向下进行,并在第一个里程碑失败时向上报告。
60. If EV is US $300,000, AC is US $350,000, and PV is US $375,000, what does the schedule performance index indicate?
A. You are only progressing at 86% of the rate originally planned. B. You are progressing at 125% of the rate originally planned. C. You are progressing at 116% of the rate originally planned. D. You are only progressing at 80% of the rate originally planned.
如果EV是300,000美元,AC是350,000美元,PV是375,000美元,则进度绩效指数说明了什么?
a. 你的进展速度仅仅是原始计划速度的86%。 b. 你的进展速度是原始计划速度的125%。