地下室防水施工方案
目 录
1、编制依据 ----------------------------------------------------------------------------------------- 3 2、工程概况 ----------------------------------------------------------------------------------------- 3 2.1设计防水概况 ----------------------------------------------------------------------------------- 3 2.1.1防水做法概况 ----------------------------------------------------------------------------- 3 2.1.2防水保护层做法 -------------------------------------------------------------------------- 4 3、施工安排 ----------------------------------------------------------------------------------------- 4 3.1工期安排 ----------------------------------------------------------------------------------------- 4 3.2劳动力安排 -------------------------------------------------------------------------------------- 4 3.3施工准备 ----------------------------------------------------------------------------------------- 4 3.3.1材料准备 ----------------------------------------------------------------------------------- 4 3.3.2机具准备 ----------------------------------------------------------------------------------- 7 3.3.3现场准备 ----------------------------------------------------------------------------------- 7 3.3.4技术准备 ----------------------------------------------------------------------------------- 8 3.3.5流水段划分 -------------------------------------------------------------------------------- 8 4、地下室外墙及底板卷材防水施工方法、工艺及注意事项 ---------------------------- 8 4.1地下室外墙及底板卷材防水施工工艺 ---------------------------------------------------- 8 4.1.1地下室底板施工工艺 -------------------------------------------------------------------- 8 4.1.2地下室外墙防水施工顺序 -------------------------------------------------------------- 8 4.2主要施工方法 ----------------------------------------------------------------------------------- 8 4.2.1基层处理剂施工 -------------------------------------------------------------------------- 8
地下室防水施工方案
4.2.2卷材加强层铺贴 -------------------------------------------------------------------------- 9 4.2.3防水卷材铺贴 ----------------------------------------------------------------------------- 9 4.2.4底板与地下室外墙交接处防水做法 ------------------------------------------------- 12 4.2.5外墙施工缝处防水做法: ------------------------------------------------------------ 13 4.2.6后浇带做法 ------------------------------------------------------------------------------ 13 4.2.7穿墙管处防水作法: ------------------------------------------------------------------ 14 4.2.8汽车坡道防水做法 --------------------------------------------------------------------- 15 4.2.9塔吊基础处防水做法: --------------------------------------------------------------- 17 4.2.10抗拔桩桩头防水做法: ------------------------------------------------------------- 18 4.3质量保证措施 --------------------------------------------------------------------------------- 19 5.刚性防水施工 --------------------------------------------------------------------------------- 20 5.1材料准备 ---------------------------------------------------------------------------------------- 20 5.2防水混凝土浇注时注意事项 --------------------------------------------------------------- 21 5.3施工缝处理 ------------------------------------------------------------------------------------- 21 6.安全文明施工 --------------------------------------------------------------------------------- 22 7.成品保护 --------------------------------------------------------------------------------------- 22
地下室防水施工方案
1、编制依据
2、工程概况
**工程用地面积 **平方米,总建筑面积**平方米,分为商业与住宅两栋建筑,地上住宅和商业独立分开,地下室连为一体。商业地上8层,地下4层,檐口高度52m;住宅地上22层,地下4层,檐口高度**m。
本工程±0.000相当于绝对标高62.600m。住宅楼采用CFG桩复合地基,钢筋混凝土筏板基础。商业地下室采用天然地基,钢筋混凝土筏板基础。底板除局部降板外,大面积标高为-17.1m,底板厚度为1000mm局部1600mm。 2.1设计防水概况
2.1.1防水做法概况
本工程地下室外墙防水等级一级(两道柔性防水一道刚性防水);具体分为底板防水(空铺法)、地下室外墙防水(满粘法)、底板后浇带防水(BW遇水膨胀橡胶止水条)、地下室外墙后浇带防水(止水钢板)、厨房、卫生间、消防水池及机房等室内防水(1.5厚聚合物水泥基防水涂料)。
因设计未下发建筑正式施工图纸,本方案只阐述地下室底板防水、地下室外墙防水及地下室顶板防水;对于厨房、卫生间、消防水池及机房等部位室内防水见后续《室内防水施工方案》;具体如下所示,
地下室各部位防水做法见下表:
地下室防水施工方案
2.1.2防水保护层做法
(1)底板防水保护层50mm厚C20细石混凝土拍平压实; (2)侧墙防水保护层为60mm厚聚苯板(密度不小于20kg/m3)。 (3)种植要求的地下室顶板,其防水保护层采用40厚C20细石混凝土 3、施工安排 3.1工期安排
因土方公司仅交于我方商业部分2个段的工作面,初步拟定防水自2011年11月1日至2011年11月8日施工完毕;地下室外墙防水时间决定于土方公司完全交给我方之后确定。 3.2劳动力安排
防水由具备防水专业承包资质的专业施工单位施工。 进场工人须经三级安全教育并经考试合格后方可上岗。 防水施工操作人员须有防水专业上岗证书。 防水工计划为40人。 3.3施工准备