Abstract

The design for a boiler room process design in Hohhot Economic Development Zone, construction area of 380,000 square meters, the heating method is taken directly from the 95/70 ℃ hot water heating boiler. In this article , the principles of this heat plant and the design data this has been explained In detail. This paper gives a reasonable basis for equipment selection and the type of major equipment.According to the architectural design energy saving requirements, calculate the maximum thermal load of 17.85 MW. This design choose three set CDZL7.0-1.0/95/70-Ptype boiler. A single boiler is rated at 7.0 MW, working pressure of 1.0 MPa.

The boiler room of raw water hardness and oxygen content do not meet the requirements of the boiler feed water, to soften and the need for oxygen treatment.According to supply water flow, the design uses two LNN-800 / 8 model of the regeneration of fixed bed countercurrent ion exchange of sodium and choose one CJYZS-10 type analytical deaerator. Two sodium ion exchange, in turn used to run.

Based on the hydraulic calculation to determine the size of the pipeline section and water pump and fan model.

Keywords: coal-boiler; heating with hot water; Water treatment ; The wind system


内蒙古-锅炉房毕业设计说明书(3).doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:机载、航电专题21 飞机故障诊断与维护系统的设计

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: