浅析EPC模式下设计阶段施工安全风险管理体系

2018-11-11 10:43

龙源期刊网 http://www.qikan.com.cn

浅析EPC模式下设计阶段施工安全风险管理体系

作者:乔彦

来源:《价值工程》2014年第21期

摘要: EPC模式,即为工程总承包模式,指把工程所有的任务统一承包下来,包括:工程的设计、设备材料的采购以及工程施工等所有项目。近些年EPC模式在国内快速流行。在EPC模式下,原有的安全风险管理系统早已不能满足要求,因此如何在工程总承包模式下,控制好安全风险,把安全风险降到最低成变得尤为重要,在工程中的安全危险最重要的阶段在于设计施工阶段,因此研究设计阶段施工安全风险管理体系具有重要的现实意义。

Abstract: EPC model, which is short for Engineering Procurement Construction, the project will contract with all tasks, which include: project design, equipment and materials procurement and construction of all projects. In recent years, EPC model is very popular in china. In EPC mode, security risk management system is not the original meet the requirements, so how in the engineering general contracting mode, control the security risk, the security risk to a minimum to become particularly important, safety risk in the project is the most important stage in the construction design stage, so the research on safety risk management system of construction the design phase has the important practical significance. 关键词: EPC模式;设计施工;风险管理

Key words: EPC model;design and construction;risk management

中图分类号:[X947] 文献标识码:A 文章编号:1006-4311(2014)21-0094-02 1 设计阶段安全风险识别与分析

在工程的设计阶段,安全的风险是方方面面的,但是大体上可以分为两大类,其中第一种风险是由于设计的参数要求标准等带来的安全风险,而第二类安全风险却具有很深的隐藏性,一般是由于在设计当中疏忽了某些必要的过程而引起的。

第一类安全风险不同于第二种风险,第一种风险的标准和参数一般都是由国家相关部门指定的,一般我们严格的按照指定的标准来。把设计的标准控制在国家要求的范围之内,第一类风险都可以有效的避开和消除。而第二类风险就复杂的多,它不能只通过遵循国家标准就能消除的,因为这种风险主要是由于在设计施工等阶段,由于忽略了工程中的某些可建造性而引起的。虽然这种风险可以通过在设计施工阶段不断的审查和改进等手段加以控制,但是相较于第


浅析EPC模式下设计阶段施工安全风险管理体系.doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:主体结构验收报告

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: