4--地上脚手架施工方案

2018-12-27 16:04

【沈阳华润中心项目一期工程】 【地上脚手架施工方案】

目 录

1. 编制依据 ················································································································· 1 2. 工程概况 ················································································································· 1

2.1 工程概况 ····················································································································· 1 2.2 建筑设计概况 ·············································································································· 1 2.3 工程脚手架设计概况 ·································································································· 2

3. 施工准备 ················································································································· 2

3.1 材料准备 ····················································································································· 2 3.2 人员准备 ····················································································································· 3

4. 主要施工技术措施 ································································································ 3

4.1 脚手架设计参数及功能······························································································· 3 4.2 脚手架搭设及构造 ······································································································ 3

5. 安全文明施工验收及使用规定 ········································································· 13

5.1 安全组织保证体系 ···································································································· 13 5.2 施工验收及使用规定 ································································································ 14

附录:地上双排脚手架的计算书、悬挑扣件式钢管脚手架的计算书

中建一局集团建设发展有限公司 1 沈阳华润中心项目一期工程项目经理部

【沈阳华润中心项目一期工程】 【地上脚手架施工方案】

1. 编制依据

1) 中国建筑北京设计研究院提供的工程设计图纸

2) 《建筑施工扣件式钢管脚手架安全技术规范》 JGJ130-2001(2002年版) 3) 《建筑安装工程施工技术操作规程脚手架工程》DB21/900.25-2005 4) 《建筑结构荷载规范》GB50009-2001(2006年版) 5) 《建筑施工手册》(第四版)

6) 《建筑工程施工质量验收实施细则》(DB21/1234-2003) 7) 《建设工程监理规范》(GB 50319-2000)

2. 工程概况 2.1 工程概况

工程名称 工程地址 建设单位 设计单位 监理单位 施工单位 工料测量师 建筑功能 沈阳华润中心项目一期工程 沈阳市青年大街原辽宁省体育馆(与辽宁省工业展览馆相邻) 华润(沈阳)地产有限公司 中国建筑北京设计研究院 北京兴电国际工程管理公司 中建一局集团建设发展有限公司 利比有限公司 超高层办公楼、商场 2.2 建筑设计概况

总建筑面积 地上建 筑面积 建筑用途 地上层数 办公楼 商场 约30.83万m2 约5.60万㎡ 约15.83万㎡ 商场、办公 6层/33层 42.800m 地下建筑面积 占地面积 地下层数 建筑总高度 约9.40万㎡ 约3.38万㎡ 3层 万象城约37m 办公塔楼约153m ±0.000标高

中建一局集团建设发展有限公司 1 沈阳华润中心项目一期工程项目经理部

【沈阳华润中心项目一期工程】 【地上脚手架施工方案】

2.3 工程脚手架设计概况

本工程结构外围采用双排落地式脚手架,作为结构施工操作防护架。双排脚手架生根在首层内收楼板上(局部生根于肥槽回填土),由于结构屋面高度为41.6m,女儿墙高度为700mm,根据《建筑施工扣件式钢管脚手架安全技术规范》,脚手架高度应超出女儿墙高度1.0m,故脚手架最高搭设高度约为43.3m。具体布置形式见下表。

序号 1 2 3 4 5 6 7 8 9 使用部位 1-1~1-17,裙楼西侧 1-1~1-17,裙楼西侧 1-17~1-26,裙楼西侧 1-M~1-F,裙楼南侧 1-L~1-G,裙楼南侧 1-A~1-F,裙楼南侧 1-1~1-20,裙楼东侧 1-H~2-M,裙楼北侧 中庭部位 脚手架搭设形式 双排脚手架 双排脚手架 双排脚手架 双排脚手架 单排脚手架 双排脚手架 双排脚手架 双排脚手架 临边防护 双排挑架 生根部位 B1层内收顶板 F5层内收顶板 ±0.00夯实回填土 B1层内收顶板 F5层内收顶板 B1层内收楼板 B1层中庭楼梯处 B1层内收顶板 首层结构楼板 B1顶板 F2~F6顶板 搭设高度 32.5m 10.8m 43.3m 43.3m 10.8m 41.7m 43.3 43.3 7.7m/7.2m 加固措施 注: 详见附图1地上脚手架平面布置图 本工程写字楼部分,1-7层采用双排架,8层以上部分采用整体爬升架,具体见专项方案。

3. 施工准备 3.1 材料准备

3.1.1钢管外径48?0.5mm,壁厚3.5?0.5mm,用于立杆、大横杆的钢管长度为4~6m。用于小横杆的钢管长度为1.5~2.0m,以适应脚手架宽的需要;钢管要求表面平直光滑,不得有裂缝、结疤、分层、错位、硬弯、毛刺、压痕和深的划道。外涂刷防锈层并定 期复涂以保持其完好。

3.1.2应使用与钢管管径相配套扣件。扣件应有出厂合格证明,扣件不得有裂纹、气孔、砂眼、疏松或其他影响使用性能的铸造缺陷。在螺栓拧紧力矩达65N·m 时,不得发生破坏。扣件扭力矩一般应为40~50 N·m。

3.1.3脚手板采用木脚手板,每块质量不宜大于30kg

3.1.4其他材料必须符合国家规范要求,安全帽、安全带、扣件、防火安全网等重要防护用品必须使用在满足规定要求的条件下,中建一局定点厂家的定点产品。

中建一局集团建设发展有限公司 沈阳华润中心项目一期工程项目经理部 2

【沈阳华润中心项目一期工程】 【地上脚手架施工方案】

3.2 人员准备

3.2.1承担脚手架搭设的操作人员必须有专门的特种作业证(脚手架操作),施工前将对操作工人的持证情况进行检查,施工过程中对参与脚手架搭设、拆除、安装的工人要进行上岗证件检查,由工程部、安全部负责。

3.2.2脚手架施工前,由技术部对工程部、安全部及三家土建分包单位做方案交底;而由工程部对搭设架子的施工人员做技术交底、安全交底。

3.2.3必须保证所有参与架体作业的施工人员安全防护设备配备到位,否则不得参加架体施工。由安全部、工程部负责监督检查。

4. 主要施工技术措施 4.1 脚手架设计参数及功能

部位 结构外围 中庭 脚手架形式 双排落地脚手架 单排外挑架 主要设计参数 水平杆步距 1.5m 1.5m 立杆横距 立杆纵距 1.05m 0.75 1.5m 1.5m 连墙件设置 竖向:3.5m 横向:5.5m 使用功能 施工操作 防护架 防护架 4.2 脚手架搭设及构造

4.2.1架体采用全封闭形式,立杆底部垫250350通长木跳板,架体外立杆内侧满挂绿色密目安全网,从第二层起每层脚手架立杆之间水平方向设置大眼网,安全网的外边沿要明显高于内边沿50~60cm。

4.2.2立杆的对接扣件应交错布置,两个相邻立杆接头不应设在同步同跨内,两相邻立杆接头在高度方向错开的距离不应小于500mm,各接头中心距主节点的距离不应大于步距的1/3;立杆垂直立于垫木正中。开始搭设立杆时,应设置临时抛撑;当搭至有连墙件的构造位置时,搭设完该处的立杆、纵向水平杆、横向水平杆后应立即设置连墙件。 4.2.3纵、横向水平杆搭设

? 纵向水平杆设于横向水平杆之下,立杆的内侧,用直角扣件与立杆扣紧; ? 纵向水平杆一般用对接扣件连接,对接头应交错布置; ? 封闭型脚手架的同步纵向水平杆必须四周交圈;

? 每一主节点处设置一根横向水平杆,并采用直角扣件扣紧在纵向水平杆上; ? 纵向水平杆的长度一般不宜小于三跨,并不大于6m。 ? 横向水平杆伸出架体外侧100mm,并铺设跳板。

中建一局集团建设发展有限公司 沈阳华润中心项目一期工程项目经理部 3

【沈阳华润中心项目一期工程】 【地上脚手架施工方案】

? 第一道纵向水平杆距地面的距离不得大于200mm。 4.2.4明确架子的搭设顺序

放置纵向扫地杆——自转角部起依次向两边竖立杆,底端与纵向扫地杆扣接固定后,搭设横向扫地杆并也与立杆固定(固定立杆底端前,应确保立杆垂直),每边竖起3-4根立杆后装第一步大横杆(与各立杆扣接固定)和第一步小横杆(靠近立杆并与大横杆扣接固定)、校正立杆垂直和横杆水平使其符合要求后,按40-60N.m力矩拧紧扣件螺栓,形成构架的起始段——按上述要求依次向前延伸搭设,直至第一步交圈完成。交圈后,再全面检查一遍构架质量和脚手架基础情况,严格确保设计要求和构架质量——设置连墙件(或加抛撑)——按第一步架的作业程序和要求搭设第二步、第三……——随搭设进程及时装设连墙件和剪刀撑——装设作业层间横杆、铺设脚手板和装设作业层栏杆、挡脚板、安全网。

4.2.5斜撑、剪刀撑的构造要求

? 本工程双排架剪刀撑在外侧立面整个高度和长度上设置剪刀撑,每道剪刀撑跨越立柱的根

数为5根,其宽度≮4跨,且≮6M,剪刀撑与地面的倾斜角在45~60°之间。

? 剪刀撑斜杆的接头必须采用搭接方法进行连接,搭接长度100cm,并且不少于3个扣件。剪

刀撑斜杆应用旋转扣件固定在立杆上,旋转扣件的中心线距主节点的距离不大于150mm。端部扣件盖板边缘主杆端的距离不应小于100mm。 ? 横向斜撑在拐角部位设置,中间每隔6跨设置一道。 4.2.6连墙件的设置

外架连墙采用如下图的三种方式:

? 由于本工程柱间距较大不能满足连墙件设置要求,在跨中搭设120031200钢管框架,放

置钢管框架的位置预埋三级25钢筋头,钢筋头埋至板中,露出板面300mm。架体横杆与之拉结。(见图一)

预埋三级25钢筋头至板中楼板

? 双排架遇柱时必须与之拉接,拉接钢管箍与混凝土柱间应用5cm木方垫开,防止柱表面被

损坏。(见图二)

? 双排架遇墙时,在墙体竖直方向每隔2步,水平方向每隔2跨预留孔,以便以后钢管穿过

拉结架体。(见图三)

中建一局集团建设发展有限公司 沈阳华润中心项目一期工程项目经理部 4


4--地上脚手架施工方案.doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:电子商务专业“三二分段”人才培养标准

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: