厦门市轨道交通2号线一期工程土建2标 【建业路站、湖滨中路站、体育中心站、育秀东路站】
地铁暗挖车站土方施工作业
指导书
编制:
审核:
审批:
厦门市轨道2号线二标项目部
二O一五年八月
厦门市轨道2号线二标 施工作业指导书
目录
1 编制目的(黑体四号) ··························································································· - 2 - 2 编制依据 ············································································································· - 2 - 3 适用范围 ············································································································· - 2 - 4 施工方法及工艺要求 ······························································································ - 2 -
4.1施工工艺流程 ······························································································· - 3 -
4.2. 施工方法 ·································································································· - 3 - 5 质量保证措施 ······································································································· - 8 - 6 安全、文明施工保证措施 ······················································································· - 11 - 7 环境保护措施 ······································································································ - 11 -
- 1 -
厦门市轨道2号线二标 施工作业指导书
地铁暗挖车站土方施工作业指导书
1 编制目的
为使施工人员充分了解施工图纸及工程特点,明确施工任务、操作方法、质量标准及安全措施,有效科学组织施工,确保暗挖车站土方的施工质量达到设计及施工规范要求,针对本工程施工特点,特制定本作业指导书。
2 编制依据
1、设计文件、设计施工图及变更图
2、《厦门市轨道交通2号线一期工程施工图设计系统对土建的要求》(中铁第四勘察设计院集团有限公司,2014.10)
3、建筑基坑支护工程技术规程(GB120-99)
4、建筑地基基础工程施工质量验收规范(GB50202-2002) 5、建筑地基处理技术规范(JGJ79-2002)
6、建筑工程施工质量验收统一标准(GB50300-2001) 7、地下铁道工程施工及验收规范(GB50299-2003) 8、《建筑结构荷载规范》(GB50009-2012) 9、《建筑基坑工程技术规范》(YB9258-97) 10、《建筑基坑支护技术规程》(JGJ120-2012) 11、《地下铁道工程施工及验收规范》GB50299-1999 12、福建省标准《建筑地基基础技术规范》(DBJ13-07-2006) 13、《厦门市轨道交通2号线一期工程施工图设计》
3 适用范围
适用于2号线二标的建业路站、湖滨中路站、体育中心站以及育秀东路站及其附属工程的土方开挖施工。
4 施工方法及工艺要求
盖挖逆作法是由地面向下开挖至一定深度后,先施工围护结构、中间桩和柱、主体结构顶板,然后在顶板的保护下从上向下开挖土体,并从上至下施作主体结构的侧墙、中板、横梁、纵梁、底板等。施工原则为:分区、分层、分段、分块,对称均衡开挖,
- 2 -
厦门市轨道2号线二标 施工作业指导书
边挖快支,严禁超挖,快速封闭底板,做好防水。
4.1施工工艺流程
盖挖施工工艺流程图
4.2. 施工方法 4.2.1主要施工步骤
施工准备—测量放线—围护结构施工—中间柱施工—施工结构顶板—回填
土、恢复路面—自上而下挖土—自上而下施工主体结构。
4.2.2施工工艺流程
开挖施工工艺流程如下图所示
- 3 -
厦门市轨道2号线二标 施工作业指导书
施工工艺流程
4.2.3施工准备
1) 完成地质补勘专项工作。
2) 基坑范围内地表建筑物已清除,地下管线已进行迁改或釆取了保护措施,作业面已具备施工条件。
3) 相应方案已编制并审批完毕,手续齐全。
- 4 -