高填方专项施工方案

2019-03-03 18:29

G56杭州至瑞丽高速公路宣威至曲靖段G60连接线

(K8+630~K11+294段)

高填方路基 专项施工方案

编制:

复核: 批准:

中交路桥技术有限公司宣曲高速公路项目经理部二分部

二○一五年十月

目 录

一、编制依据···················································1 二、编制原则···················································1 三、工程概况···················································1 四、施工准备、部署·············································2 4.1熟悉图纸和线路调查········································2 4.2测量······················································2 4.3试验······················································2 五、主要施工工艺和方法·········································3 5.1施工工艺流程图············································4 5.2土质路堤··················································4 5.3填石路堤··················································5 5.4土石路堤··················································6 5.5高填方路堤其他要求········································8 5.6土工格栅施工··············································9 5.7高填方路堤检测············································9 5.8路堤边坡修整··············································10 六、施工工期安排···············································10 七、人员、材料、设备进场计划、资源安排·························11 7.1主要管理人员··············································11 7.2主要设备··················································11 7.3材料计划··················································12 八、资金计划···················································12 九、质量、安全、环保保证体系···································12 9.1质量目标及保证措施········································12 9.2安全目标及保证措施········································16 9.3工期目标及保证措施········································19 9.4环境保护、水土保持措施····································22 十、雨季施工保证措施···········································25 10.1组织措施·················································25 10.2雨季施工领导小组工作职责·································25 10.3具体措施·················································26 十一、质量控制及试验检测项目、频率和方法·······················28 十二、应急预案·················································29 12.1组织机构·················································29 12.2紧急情况发生和上报程序···································30

一、编制依据

1、宣曲高速公路第8合同段设计施工图纸 2、公路工程施工安全技术规范(JTGF90-2015) 3、公路工程质量检验评定标准(JTGF80/1-2014) 4、公路路基施工技术规范(JTGF10-2006) 5、《云南省高速公路施工标准化实施要点》

6、云南宣威至曲靖段高速公路土建工程招标文件、合同书、标前会议及补遗书

二、编制原则

以质量为中心,实行“高起点、高要求、高质量、重安全、重环境、重细节”精致化组织施工,做到施工技术全面性。可行性、针对性和先进性,结合工程相关特点,抓好重点工序。以“超前控制、典型示范、带动全面”为实施原则,自始至终坚持对施工现场全过程严密控制、动静结合、科学管理、激励等管理职能,对劳力、设备、材料、资金、技术、方法、环境、能源、信息等进行合理配置和优化组合,实现质量、安全环保、工期、成本造价、合同履行、企业信誉及社会形象的良好预期目标效果。 三、工程概况

本合同段起止桩号:左幅K8+630~K11+293.853;全长2663.853米,右幅K8+630~K11+294.272;全长2664.272米及大龙潭一期工程互通立交A、C、E、F四个匝道。路基挖方约60万立方米;填方约68立方米,高填方路堤共三处,合计378米。具体分布情况见下表:

1

高填方路基一览表

序号 1 2 3 起讫桩号 K8+995~K9+190 K9+460~K9+530 K10+175~K10+288 处理长度(m) 195 70 113 位置 全幅 全幅 全幅 边坡最大高度(m) 25.6 20.1 28.1 四、施工准备、部署 4.1、熟悉图纸和线路调查

路基填筑前,组织技术人员和施工人员认真阅读设计图纸和技术资料,熟悉合同文件和技术规范,组织有关人员对路线走向,取土场的位置,地形地貌,道路交通,桥涵位置,地质水文状况,水准点及控制桩等进行全面的调查、核对,严禁破坏环境。认真听取周边群众的意见,并作汇报,以免以后施工时造成纠纷、打架等不良事件。根据现场实际工期要求情况,工程量大小,编好施工组织设计,确定人员,设备的组合与配置,具体的施工工艺及土石方的调配方案。 4.2、测量

测量队将填方区域及取土区域的导线上的水准点进行加密,恢复路线中、边线,包括路堤的坡角,边沟及桥涵具体的位置,恢复路线的红线,根据有关规定,钉出路基用地界线,开挖50*50cm的土沟与周边群众用地加以区分,以免造成不必要的纠纷;在距路中一定安全距离处设立控制桩,其间隔不宜大于50cm,桩上标明桩号与路中心的填高。 4.3试验

2

试验室有关人员将路基填筑用料进行现场取样,并按《公路土工试验规程》JTGE40-2007进行液限、塑限、塑性指数、天然稠度、颗粒大小分析、含水量、密度、土的击实、相对密度、土的强度、有机含量试验及易溶含量等相关试验。

试验室应尽快将试验的原始资料整理汇总,对于合格的填料来源进行调查,上报项目总工程师,对不合格填料尽量采取废弃处理,重新调查土石方调配,并上报监理工程师。 五、主要施工工艺及方法

经查阅本合同段设计图纸,我部拟建的三处高填方路基施工段前后土石方挖方量较小,路基填料均采用建设单位指定的取土场外运至施工路段进行路基填筑。

按设计要求在路基1/3~1/2高度以下范围内铺设三层土工格栅,间距1米,并每隔2米采用液压式压路机进行冲击碾压补强处理。填至上下路床底部时再分别加铺一层土工格栅,以降低高填方路基的工后沉降。

当采用石料填筑时,坡面采用大块石码砌。边坡码砌应采用强度大于30MPa的不易风化石料,码砌石块最小尺寸不小于300mm,石块应规则。路堤高度大于12米时,宽度应大于2米。

3


高填方专项施工方案.doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:完善财务管理体系的五个方面财会实务精品文档

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: