实施方案

2019-03-09 13:52

翁井村七组机耕道建设项目

实实施单位:贵州省清镇市建筑工程公司编制单位:贵州省清镇市建筑工程公司编制日期:施 方 案

2014年6月

翁井村七组机耕道建设项目

目 录

1 项目摘要 ···································································································· 3

1.1 项目名称 ····························································································· 3 1.2项目建设地点 ························································································ 3 1.3 项目建设单位 ······················································································ 3 1.4 项目法人代表 ······················································································· 3 1.5项目建设内容及规模 ··············································································· 3 1.6 项目建设期 ·························································································· 3 1.7 项目投资概算 ······················································································· 3 2 基本情况 ···································································································· 4

2.1项目区基本概况及自然条件 ······································································ 4 2.2地理位置及范围 ····················································································· 4 2.3水文气象 ······························································································ 4 2.4地形地质,地貌及土壤 ············································································ 5 2.5 耕地种类、数量及开发潜力 ····································································· 6 2.6 社会经济状况 ······················································································· 6 2.7人口及劳力 ··························································································· 6 2.8 建设需求及群众建设积极性 ····································································· 6 2.9退耕农户现状及需求。 ············································································ 7 3 编制依据 ······································································································ 7

3.1 相关的法律、法规 ················································································· 7 4 基本规则 ···································································································· 7

4.1 坚持优先安排具备建设条件农户的原则 ······················································ 7 4.2 坚持从实际出发,因地制宜的原则 ···························································· 8 4.3 坚持以人为本,体现农户愿意的原则 ························································· 8 4.4 坚持国家支持与农户自我发展相结合的原则 ················································ 8 4.5 坚持以行政村为基本单位,相同类型相对集中的原则 ···································· 8 5 建设目标任务 ······························································································ 8

5.1 建设目标 ····························································································· 8

1

翁井村七组机耕道建设项目

5.2 建设任务 ····························································································· 8 6 建设内容 ······································································································ 9

6.1 水量平衡 ····························································································· 9 7 投资概算及资金来源 ····················································································· 9

7.1 项目概算 ····························································································· 9 7.2 取费单价及取费标准 ·············································································· 9 7.3 投资指标 ····························································································· 9 8 实施计划与施工组织 ···················································································· 10

8.1 年度实施计划 ······················································································ 10 8.2施工组织 ····························································································· 10 8.3 工程招标 ···························································································· 13 9 保障措施 ··································································································· 13

9.1政策保障措施 ······················································································· 13 9.2技术保证措施 ······················································································· 14 9.3资金管理措施 ······················································································· 14 9.4建设和运行管理措施 ·············································································· 15 9.5生态效益分析 ······················································································· 16

2

翁井村七组机耕道建设项目

1 项目摘要

1.1 项目名称

翁井村七组机耕道建设项目 1.2项目建设地点

金华镇翁井村委会 1.3 项目建设单位

翁井村村民委员会 1.4 项目法人代表

金华镇翁井村村民委员会主任:何培林 1.5项目建设内容及规模

一、项目总投资:

本工程总投资12万元。包含路基处理、砂土面层铺设、路肩墙分项工程。 二、建设内容

金华镇翁井村片区建设内容统计表

序号 1 2 3 4 1.6 项目建设期

本工程计划于2014年6月16日开工建设,于2014年8月12日完工,计划工期为58天,2014年14日计划组织验收。 1.7 项目投资概算

本工程总投资12万元,包含路基处理、砂土面层铺设、路肩墙分项工程,全部为上级专项资金。

分项工程名称 路肩墙 回填土 沟渠开挖 机械 单位 m3 m3 M 小时 数量 224.06 739.82 81 36 备注 3

翁井村七组机耕道建设项目

2 基本情况

2.1项目区基本概况及自然条件

金华镇翁井村位于贵阳市西南面,行政区域面积6平方公里,属亚热带温润气候区,具有较为明显的高原性气候特点,年均气温在14.6℃左右,年均日照为1183.2小时,无霜期288天,年降雨量1172.60mm;地势北高南低,西部平缓,以丘陵地貌为主,平均海拔1250米,辖9个村民组,全村农业人员口2019人,耕地面积1020亩,其中田600亩、土420亩,农业人员人口均占有耕地0.7亩。

近几年来、国家相继出台了相关惠农政策和措施,免除了农业税、实行粮食直补、农机具购置补贴等,并不断加大对农村基础设施的补助扶持,增强了农民从事农业生产的积极性,农民认识到土地是他们的生命线,是他们的财富,建设农村机耕道关系到他们的切身利益,随着农业的不断发展,农业基础设施建设的薄弱与农业的快速发展之间的矛盾日渐显现,因此加快农业基础设计建设力度,进一步改善农业生产条件,提高农业生产抗风险能力也犹为必要。 2.2地理位置及范围

金华镇位于贵州省贵阳市观山湖区,地理坐标为东经106°29′至106°31′,北纬26°32′地处“一区两市三湖”之地,东有贵阳市、西有清镇市、红枫湖;北有百花湖、金华湖、贵黄公路、321国道横穿金龙村、金华村、三甫村、蒿芝村、下甫村和金华居委会、蒿芝居委会,有“双龙汇金华”之称,全村九个村民组十个自然村寨,总面积6个平方公里,平均海拔1250米,全村耕地面积1020亩,其中田600亩。 2.3水文气象

观山湖区属北亚热带,东春半干燥夏季润湿气候,四节分明,东暖夏凉。雨量充沛,气温较高。根据原乌当区气象站理念资料统计:多年平均气温14.7℃,最冷月一月均温4.3℃,最热月七月均温为23.5℃,极端最高气温为35.9℃,极端最低气温为-8.3℃。年平均相对湿度81%,最热月月平均相对湿度81%,最冷月月平均相对湿度82%;年平均风速为2.1m/s,最多风向为NE风;年平均日照时数为1168.6h,占可照时数的26%;多年平均无霜期208.7天,多年平均雾日数24.9天。

多年平均年降水量为1172.6mm,集中在夏季半年,占全年降水量的75%~

4