八方小区二期C区建安工程(六标段) 水电安装施工组织设计
目 录
1、工程概况 --------------------------------------------------------------- 1 1.1工程简介 ---------------------------------------------------------------------------------------------- 1 1.2水电工程概况 ---------------------------------------------------------------------------------------- 1
1.2.1生活给水系统--------------------------------------------------------------------------------------------------- 1 1.2.2排水 --------------------------------------------------------------------------------------------------------------- 2 1.2.3配电房。 --------------------------------------------------------------------------------------------------------- 3 1.2.4照明、动力系统 ----------------------------------------------------------------------------------------------- 3 1.2.5照明灯具 --------------------------------------------------------------------------------------------------------- 3 1.2.6防雷 --------------------------------------------------------------------------------------------------------------- 3
1.3主要工程量。 ---------------------------------------------------------------------------------------- 4 1.4工程特点. ---------------------------------------------------------------------------------------------- 6 a、施工技术、质量要求高,比较复杂 ------------------------------------------------------------- 6
2、编制的依据 ------------------------------------------------------------- 6 3、施工准备 --------------------------------------------------------------- 6 4、电气工程主要施工方法 --------------------------------------------------- 9 4 .1配电箱、柜的安装 --------------------------------------------------------------------------------- 9 4.2电缆桥架及金属线槽的安装 -------------------------------------------------------------------- 12 4.3、管路敷设 ------------------------------------------------------------------------------------------ 13 4.4管内及金属线槽内配线工程 -------------------------------------------------------------------- 13 4.5电缆敷设的施工方法 ----------------------------------------------------------------------------- 14 4.6灯具安装 -------------------------------------------------------------------------------------------- 14
4.6.1、作业条件: ------------------------------------------------------------------------- 错误!未定义书签。 4.6.2、施工工艺流程: ------------------------------------------------------------------- 错误!未定义书签。 4.6.3操作工艺要求------------------------------------------------------------------------- 错误!未定义书签。
4.7开关、插座安装 ----------------------------------------------------------------------------------- 14
4.7.1工艺流程。 ---------------------------------------------------------------------------------------------------- 14
八方小区二期C区建安工程(六标段) 水电安装施工组织设计
开关、插座的施工工艺流程为: ------------------------------------------------------------------------------- 14 4.7.2、操作工艺。 ------------------------------------------------------------------------------------------------- 15 4.7.3通电试运行。------------------------------------------------------------------------------------------------- 16
4.8防雷工程 -------------------------------------------------------------------------------------------- 16
4.8.1接地体安装。------------------------------------------------------------------------------------------------- 16 4.8.2、接地干线安装。 ------------------------------------------------------------------------------------------- 17 4.8.3、支架安装。 ------------------------------------------------------------------------------------------------- 17 4.8.4、防雷引下线的敷设。 ------------------------------------------------------------------------------------- 18 4.8.5、避雷网的安装。 ------------------------------------------------------------------------------------------- 18 4.8.6、避雷针的安装。 ------------------------------------------------------------------------------------------- 18 4.8.7注意事项。 ---------------------------------------------------------------------------------------------------- 18
5、给排水工程安装 -------------------------------------------------------- 18 5.1管道安装工艺流程 -------------------------------------------------------------------------------- 19 5.2管道安装工艺要求 -------------------------------------------------------------------------------- 19 5.3卫生洁具安装工程 -------------------------------------------------------------------------------- 21
5.3.1、作业条件 ---------------------------------------------------------------------------------------------------- 21 5.3.2、材质要求 ---------------------------------------------------------------------------------------------------- 21 5.3.3、工艺流程 ---------------------------------------------------------------------------------------------------- 21 5.3.3、操作工艺 ---------------------------------------------------------------------------------------------------- 21
6、质量要求. ------------------------------------------------------------- 24 6.1电气工程质量要求 -------------------------------------------------------------------------------- 24 6.2给水排水工程质量要求 -------------------------------------------------------------------------- 24
7、安全要求. ------------------------------------------------------------- 24 8、产品防护措施 ---------------------------------------------------------- 25
八方小区二期C区建安工程(六标段) 水电安装施工组织设计
1、工程概况
1.1工程简介
八方小区二期C区建安工程(六标段)工程位于长沙市岳麓区含光路与岳华路交汇处由长沙市经发房地产开发有限公司开发建设,湖南长安项目管理有限公司监理,长沙市富湘建筑工程有限公司承建。
本工程总建筑面积191133.88平方米,主体建筑地下二层主要为车库及设备用房,地上三十三层,一层局部架空,其它均为住宅,屋顶设有电梯机房。本工程属于一类高层住宅楼,耐火等级为一级,建筑主体高度104.52米。结构形式为框架剪力墙结构,现浇砼梁、板,基础形式为桩基础。
本项目采用双重10KV电源供电,在地下室设有专变室一座,公变室四座,本建筑公变电源引自地下室3#公变室。消防控制室设在1#栋负一层。
工程内容包括:土建、水暖卫、安装、消防等工程。
本施工方案仅包括生活给水、排水和电气工程。消防工程用水另行编制方案。 1.2水电工程概况
1.2.1生活给水系统
1、水源来自小区室外自来水环网压力为300KPa。
2、设高区一套一体化成套智能泵站供水设备组(带水箱)。水表采用IC卡水表。 3、室内冷水分三个区。
一区:-1层至4层住宅:采用小区市政水直供。 二区:5层至18层,由低区无负压设备供水。 三区:19层至32层,由高区无负压加压设备供水。 4、给水管:DN〈=50采用截止闸;DN〉50采用闸阀或蝶阀。 管材及接口:
——室内给水主立管采用PSP钢塑复合压力管,内外双热熔连接。户内支干管采用PPR管,粘接。
1
八方小区二期C区建安工程(六标段) 水电安装施工组织设计
——室内排水管、雨水管采用U—PVC塑料管,粘接。室外采用双壁波纹管横干管及1米以下排水管,采用柔性球墨铸铁管。
——室外给水管采离心球墨铸铁给水管,给水排水标准图集02ss405—1~4。户内给水支管采用暗装,暗装管道的墙槽应在土建施工时预留。
5、给水横管,宜有0.002-0.005的坡度坡向泄水装置。
6、给水管穿越沉降缝时,应采用橡胶纹管连接,给水管道穿越屋面处应设防水套管。 7、给水立管和装有3个或3个以上配水点支管始端,均应安可拆装的连接外。 8、给水管道貌岸然支,吊架要求:支,吊架的制作与安装详见国标03S402给水(包括热水)立管管卡安装要求:层高〈5米,每层设1个,层高〉5米,每层设2个。
9、屋顶明装给水管道需做保温,保温材料采用橡塑管壳,防结露给水管保温厚度为10 mm;保护层采用玻璃布缠绕,外刷二道调和漆。
10、给水和热水立管穿楼板时,应设套管。安装在楼板内的套管,其顶部应高出装饰地面20mm;安装在卫生间及厨房内的套管,其顶部高出装饰地面50mm,底部应与楼板底面相平;套管与管道之间缝隙应用阴燃密实材料和防水油膏填实,端面光滑。
1.2.2排水
1、排水管道的横管与横管,横管与立管的连接,应采用45o三通或四通和90o斜三通或90o斜四通,立管底部与排出管连接时应采用两个45o弯头连接,或弯曲半径不少于四倍管径的90o弯管。
2、立管上应每二层设置一个检查口,但在最低层和有卫生器具的最高层必须设置,若有乙字管,则在该乙字管的上部设置检查口,检查口高度自地面(楼面)至检查口为1.0m。并应有高于该层卫生器具上边缘 150mm,检查口朝向应便于检修。
3、地漏:采用带水封直型地漏,水封≮50mm,口径除图中注明者外,均为DN50。 4、在不上人屋面的排水通气立管伸出屋面为0.50m,上人屋面其通气立管应高出屋面2.0m,伸出屋面的通气立管均应有气帽。
2
八方小区二期C区建安工程(六标段) 水电安装施工组织设计
5、所有卫生器具自带或配套的存水弯其水封深度不得小于50mm。
6、在连接两个及两个以上大便器或三个及三个以上卫生器具的污水横管应设置清扫口,污水管起点的清扫口与管道相垂直的墙面距离,不得小于200mm若污水管起点设置堵头代替清扫口与墙面距离不得小于400mm。
7、排水管道支架与吊架要求,固定件间距,横管不得大于是2m;立管不得大于3m,层高小于或等于4m时,立管可安一个固定件,且每隔三米(可每层)应设一个伸缩节,排水立管底部的弯管处应设支敦,排水干管应设专用的伸缩节及阻火圈。
1.2.3配电系统
低压配电系统采用~220/380V放射式及树干式相结合供电方式。一级消防电梯负荷采用双电源供电,在末端互投;一级非消防负荷采用双电源供电,在末端互投(或在适当位置互投);三级负荷采用单电源供电。
1.2.4照明、动力系统
光源及灯具:室内外照明选用发光效率高、显色性好、使用寿命长、色温相宜、符合环保要求的光源与高效节能灯具。照明和插座由不同的支路供电,照明、插座为单相三线,应急照明回路出线采用WDZN-BYJ-3*2.5mm2-SC20,普通照明回路出线采用BV-3*2.5mm2-SC20。插座为单相三线,插座回路出线采用BV-3*4mm2-SC20。除挂式空调插座外,所有插座回路均设30mA剩余电流断路器保护。凡是I类灯具的外露可导电部分均可靠连接PE线接地。在楼梯间及其前室、消防电梯前室、疏散走廊等场所设置疏散照明,楼梯间等处地面照度值不低于5Lx,疏散走道的地面照度值不低于0.5Lx。在走廊、安全出口、楼梯间及其前室、电梯间及其前室、主要出入口等场所设置疏散指示照明。应急照明采用专用照明箱供电,选用自带蓄电池的应急型灯具,要求连续供电时间不少于30分钟(消防电梯机房不少于180分钟,由消防电梯双电源切换箱保障)。火灾时消防控制室切断单元应急照明箱总开关,灯具自动点亮。所有应急照明灯具应设玻璃或其他非燃烧材料制作的保护罩。
1.2.5照明灯具
3