万科光明城市三期一标段后浇带施工方案
本工程后浇带宽度为800,最厚处的板厚为400, 考虑后浇带下用12mm厚的双面覆膜多层竹胶合板,考虑用50*100的木楞,间距为600 荷载计算: 荷载标准值: 砼自重:
G1=0.6*0.4*25=6KN/M 模板及支架自重: G2=0.5*0.4*0.6=0.12 KN/M 施工活荷载: Q1=2.5*0.6=1.5 KN/M 振捣砼产生的荷载: 2.0*0.6=1.2 KN/M 荷载设计值为
G=(1.2*(6+0.12)+1.4*(1.5+1.2))*0.85=9.455KN/M 竹胶板验算:
弯矩:M=9.455*0.8*0.8/8=0.7564KN.M
M/W=0.7564/(0.4*0. 12*0.12/6)=787.9 KN/m2≤f=18000 KN/m2 挠度:ω=5Ql4/384EI≤[ω]
=5*9.455 *0.84/(384*7.6*106*0.4*0.123/12)=0.000115≤1/400*0.8 挠度符合要求! 木龙骨验算:
弯矩:M=9.455*0.8*0.8/8=0.7564KN.M
M/W=0.7564/(0.05*0.1*0.1/6)=9076.8 KN/m≤f=18000 KN/m 挠度:ω=5Ql4/384EI≤[ω]
=5*9.455*0.84/(384*7.6*106*0.5*0.13/12)=0.000159≤1/400*0.8=0.002 挠度符合要求! 主龙骨验算:
N=9.455*0.8/2=3.782KN
拟采用6米长的Φ48×3.5钢管作为主龙骨,钢管顶托间距为1200, 经过计算:支座反力分别为5.673,最大的弯矩为1.891*0.6=1.1346 KNM 抗弯:M/W=1.1346/(2*5.08)*106=111673KN/m2≤f=205000 KN/m2
- 11 -
2
2
万科光明城市三期一标段后浇带施工方案
挠度:ω=Ql3/48EI≤[ω]
=3.782*0.6*0.6*0.6/(48*2.06*108*12.19*10-8)=0.000677 ≤1/400*0.6=0.0015
满足要求;
立杆稳定性验算:
λ=L/i=4.1/0.0158=259>250 Φ=7320/λ2=7320/259/259=0.109
δ=N/ΦA=5.673/(0.109*4.89*0.0001)=106433 KN/m2≤f=205000 KN/m2 所以后浇带模板符合要求。 2.3.2.2后浇带墙的支模
墙体后浇带两侧用300*1500的钢模拼接,内钢楞采用2根Φ48×3.5钢管,间距为750,外楞采用同一种规格的钢管,ф16对拉螺栓水平间距为600。 荷载计算:
砼侧压力:F1=0.22*25*200/(15+20)*1*1*1.81/2=42.114 KN/m2 F2=25*3.8=95 KN/m2 取两者中的较小值:F1=42.114 KN/m2 设计值:F=42.114*1.2*0.85=42.96 KN/m2 倾倒砼产生的侧压力为:查表得:4 KN/m2
荷载设计值为:4*1.4*0.85=4.76 KN/m
荷载组合:F3=42.96+4.76=47.72 KN/m2
钢模板验算:
2
均布线荷载:Q1=47.72*0.3=14.316 KN/m、 抗弯:
M=14.316*0.375*0.375/2=1.007KN.M
σ=M/W=1.007/(2*5.94)*1000000=84764 KN/m2≤f=205000 KN/m2 Q2=42.114*0.3=12.63 KN/m 挠度:
ω=Qm/(24EI)*(- l3+6m2 l+3m3)≤[ω] =12.63*0.375/(24*2*2.06*108*26.97*10-8)*
(-0.75*0.75*0.75+6*0.375*0.375*0.75+3*0.375*0.375*0.375)=0.000656≤ 1/400*0.75=0.0018
- 12 -
万科光明城市三期一标段后浇带施工方案
挠度符合要求! 钢楞验算:
查表得圆形钢管Φ48×3.5的I=12.19*10-8 m4 ,W=5.08*10-6 m3 划为均布线荷载: Q1=47.72*0.75=35.79 KN/M Q2=42.114*0.75=31.59 KN/M 抗弯:
按三跨连续梁计算:
M=0.10*35.79*0.6*0.6=1.288KN.M
σ=M/W=1.288/(2*5.08)*1000000=126771 KN/m≤f=205000 KN/m 挠度:
ω=0.677*Q2 L4/100EI
=0.677*31.59*0.64/(100*2.06*108*12.19*10-8)
(-0.75*0.75*0.75+6*0.375*0.375*0.75+3*0.375*0.375*0.375)=0.001104≤ 1/400*0.6=0.0015 符合要求! 对拉螺栓验算:
M16的螺栓的净面积为144mm2 对拉螺栓的拉力:
N=47.72*0.4*0.75=14.316 KN
σ=N/A=14.316/144*1000000=99416 KN/m2≤f=170000 KN/m2满足要求! 3、后浇带砼的浇筑
3.1 后浇带处两侧砼断面的清理:两侧砼断面在浇筑砼之前用錾子将成团的钢丝网、裸露松动的石子、浮浆及其它垃圾凿除,并用高压水冲洗干净,同时在浇筑砼之前浇水润湿24h;
3.2 后浇带钢筋的整理:将后浇带处钢筋上的垃圾及浮锈用钢丝刷刷干净,并用水冲洗钢筋;然后将弯曲变形的钢筋调直,最后再将后浇带处的钢筋重新绑扎,并作隐蔽验收。
3.3 后浇带处砼的浇筑:将后浇带处的垃圾及积水清理干净后, 后浇带两侧的断面必须先用净水泥浆接浆,然后再用比原砼强度等级高一个等级的砼进行浇筑,并振捣密实,振动棒必须离开后浇带断面50mm开始浇筑。
- 13 -
2
2
万科光明城市三期一标段后浇带施工方案
3.4 砼浇筑完10~12h后开始覆盖薄膜浇水养护14d. 4、后浇带模板的拆除
根据设计要求,后浇带砼浇筑时间为:主楼封顶,沉降观测结果趋于平缓,即可开始浇筑后浇带砼。待后浇带砼强度达到规范要求的强度后即可拆模。