浅谈溶洞处理的一般措施

2019-04-21 15:08

浅谈溶洞处理的一般措施

摘要:溶洞是石灰岩在水中长期溶蚀的结果,工程中溶洞大部分情况下可以考虑为一种不良地质。溶洞十分发育的地段线路要选择绕避,如没有选择绕避,则要根据实际情况对基础下的溶洞做相应处理,本文根据中铁二院洞新高速项目、中交二院乐广项目及本人的一些经验,总结桥梁基础遇到溶洞时的一般处理措施。

关键词:溶洞 桥梁基础

Abstract: water-eroded cave is in the water dissolution of long-term limestone result, in most cases karst cave engineering can be considered as a bad geological. Cave is a very development area should choose the line around the avoid, if not choose from around, according to the actual situation of the karst caves in the corresponding basis do processing, according to TieErYuan hole in the new high-speed project, in the music of the project and some of my wide experience to sum up the bridge foundation of general karst cave meet processing measures.

Keywords: cave Bridges foundation

前言:岩溶地貌是因具有溶蚀力的水对可溶性岩石产生溶蚀等作用而形成的地表和地下形态的总称,又称喀斯特地貌。岩溶问题是岩溶地区工程建设的突出问题。中国岩溶地貌分布广、面积大,我过西南及华南岩溶地貌分布广泛。

溶洞大概可分为4类,即空溶洞、多层溶洞、大型溶洞(H>3m)、有充填物溶洞(全填充、半填充)。类型主要以有填充物溶洞为主,其充填物主要有半充填淤泥质土、砂砾、碎石、卵石、粘土等。最大溶洞高27.2m。,多层溶洞一般高度较小。为了保证岩溶发育地区钻孔灌注桩施工过程中不漏浆,或漏浆但不发生坍孔,保证桩孔顺利成孔、成桩并满足承载力要求。施工时应根据地质钻孔柱状图来判别溶洞地层情况、空洞大小、溶洞填充物情况。根据不同的溶洞采取不同方案,采用常规泥浆护壁方法、向孔内抛填片石、回填素混凝土、压力注浆以及采用钢护筒跟进等不同施工工艺。

1 常规方案

一般情况下,溶洞会有填充物,当溶洞有填充物,是可塑或软塑的亚粘土,且溶洞不漏水,这时不管溶洞有多大也不管溶洞垂直方向数量有多少,都可以不考虑溶洞的存在,而按正常地质情况施工。采用冲击钻成孔,洞内的土质和溶洞外的土质没有什么区别,可以按无溶洞施工。


浅谈溶洞处理的一般措施.doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:第十二课 公民在经济生活中的权利与义务

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: