11 四川科技职业学院毕业设计(论文)
第三章 教学楼商品混凝土总方量单
该教学楼共五层,其中二至四层一样,一层和五层不一样,还有炮楼。
一、框架柱: 第一层:
3 3
KZ-1: 0.6×0.6×5=1.8 mKZ-2: 0.6×0.6×5=1.8 mKZ-3: 0.6×0.6×5=1.8 m3 KZ-4: 0.6×0.6×5=1.8 m3 3 3 KZ-5: 0.6×0.6×5=1.8 mKZ-7: 0.6×0.6×5=1.8 m3 KZ-9: 0.6×0.6×5=1.8 m3 KZ-11: 0.6×0.6×5=1.8 m3 KZ-13: 0.6×0.6×5=1.8 m3 KZ-15: 0.6×0.6×5=1.8 m3 KZ-17: 0.6×0.6×5=1.8 m3 KZ-19: 0.6×0.6×5=1.8 m3 KZ-21: 0.6×0.6×5=1.8 m3 KZ-23: 0.45×0.45×5=1.0125 m3 KZ-24: 0.35×0.5×5=0.875 m3
KZ-25: 0.45×0.45×5=1.0125 m3 第二至四层:
KZ-1: 0.6×0.6×4.1×3=4.428 m3 KZ-3: 0.6×0.6×4.1×3=4.428 m3 KZ-5: 0.6×0.6×4.1×3=4.428 m3 KZ-7: 0.6×0.6×4.1×3=4.428 m3 KZ-9: 0.6×0.6×4.1×3=4.428 m3 KZ-10: 0.6×0.6×4.1×3=4.428 m3
KZ-11: 0.6×0.6×4.1×3=4.428 m3 KZ-12: 0.6×0.6×4.1×3=4.428 m3
KZ-13: 0.6×0.6×4.1×3=4.428 m3 KZ-14: 0.6×0.6×4.1×3=4.428 m3
KZ-15: 0.6×0.6×4.1×3=4.428 m3
KZ-16: 0.6×0.6×4.1×3=4.428 m3
KZ-17: 0.6×0.6×4.1×3=4.428 m3
KZ-18: 0.6×0.6×4.1×3=4.428 m3
KZ-19: 0.6×0.6×4.1×3=4.428 m3 KZ-20: 0.6×0.6×4.1×3=4.428 m3
KZ-21: 0.6×0.6×4.1×3=4.428 m3
KZ-22: 0.6×0.6×4.1×3=4.428 m
3
KZ-23: 0.45×0.45×4.1×3=2.49075 m3
KZ-24: 0.35×0.5×4.1×3=2.1525 m
3
KZ-25: 0.45×0.45×4.1×3=2.49075 m3 第五层:
KZ-1: 0.6× 0.6×4.1= 1.476 m3 KZ-2: 0.6授人以渔
KZ-6: 0.5×0.5×5=1.25 mKZ-8: 0.6×0.6×5=1.8 m3 KZ-10: 0.6×0.6×5=1.8 m3 KZ-12: 0.6×0.6×5=1.8 m3 KZ-14: 0.6×0.6×5=1.8 m3
KZ-16: 0.6×0.6×5=1.8 m3
KZ-18: 0.6×0.6×5=1.8 m3
KZ-20: 0.6×0.6×5=1.8 m3
KZ-22: 0.6×0.6×5=1.8 m3 KZ-2: 0.6×0.6×4.1×3=4.428 m3
KZ-4: 0.6×0.6×4.1×3=4.428 m3
KZ-6: 0.5×0.5×4.1×3=3.075 m3
KZ-8: 0.6×0.6×4.1×3=4.428 m3
× 0.6×4.1= 1.476 m3
能力为本
11
12 四川科技职业学院毕业设计(论文)
KZ-3: 0.6× 0.6×4.1= 1.476 m3 KZ-4: 0.6× 0.6×4.1= 1.476 m3
KZ-5: 0.6× 0.6×4.1= 1.476 m3 KZ-6: 0.5× 0.5×5= 1.25 m
3
KZ-7: 0.6× 0.6×4.1= 1.476 m3 KZ-8: 0.6× 0.6×4.1= 1.476 m3 KZ-9: 0.6× 0.6×4.1= 1.476 m3 KZ-10: 0.6× 0.6×4.1= 1.476 m3 KZ-11: 0.6× 0.6×4.1= 1.476 m3 KZ-12: 0.6× 0.6×4.1= 1.476 m3 KZ-13: 0.6× 0.6×4.1= 1.476 m3 KZ-14: 0.6× 0.6×4.1= 1.476 m3 KZ-15: 0.6× 0.6×4.1= 1.476 m3 KZ-16: 0.6× 0.6×4.1= 1.476 m3 KZ-17: 0.6× 0.6×4.1= 1.476 m3 KZ-18: 0.6× 0.6×4.1= 1.476 m3
KZ-19: 0.6× 0.6×4.1= 1.476 m3 KZ-20: 0.6× 0.6×4.1= 1.476 m3
KZ-21: 0.6× 0.6×4.1= 1.476 m3 KZ-22: 0.6× 0.6×4.1= 1.476 m3
KZ-23: 0.45× 0.45×4.1=0.8303 m3
KZ-24: 0.35× 0.5×4.1= 0.7175 m3 KZ-25: 0.45× 0.45×4.1= 0.8303 m3 炮楼:
KZ-14: 0.6×0.6×3.5=1.26 m3 KZ-15: 0.45×0.45×3.5=0.7088 m3
KZ-16: 0.6×0.6×3.5=1.26 m3
KZ-17: 0.45×0.45×3.5=0.7088 m
3
KZ-21: 0.45×0.45×3.5=0.7088 m3
KZ-22: 0.45×0.45×3.5=0.7088 m
3
KZ-23: 0.45×0.45×3.5=0.7088 m3 KZ-24: 0.35×0.5×3.5=0.6125 m3
KZ-25: 0.45×0.45×3.5=0.7088 m3 KZ-26: 0.4×0.3×3.5=0.42 m3
KZ-27: 0.4×0.3×3.5=0.42 m3 KZ-28: 0.4×0.3×3.5=0.42 m3 二、楼板: 第一层:
第一块: 28.45×18.05×0.1=51.352 m3
第二块: 38.25×18.05×0.1=69.041m3 第三块: 10.5×6.95×0.1=7.2975m3 第四块: 6.95×0.3×0.1=0.2085 m3 第五块: 4×3.1×0.1=1.24 m3
第六块: 10.65×0.3×0.1=0.3195 m3
增加处一: 7.325×7.25×0.02=1.0621 m3
增加处二: 8.85×7.25×0.03=1.9249 m3
增加处一: 8.85×7.25×0.03=1.9249 m3 第二至四层:
第一块: 28.45×18.05×0.1×3=154.0568 m3 第二块: 38.25×18.05×0.1×3=207.1238 m3 第三块: 10.5×6.95×0.1×3=21.8925 m3 第四块: 6.95×0.3×0.1×3=0.6255 m3 第五块: 4×3.1×0.1×3=3.72 m3
第六块: 10.65×0.3×0.1×3=0.9585 m3
授人以渔
能力为本
12
13 四川科技职业学院毕业设计(论文)
增加处一: 7.325×7.25×0.02×3=3.186375 m3
3
增加处二:8.85×7.25×0.03×3=5.774625 m 增加处三: 8.85×7.25×0.03×3=5.774625 m3 第五层:
第一块: 28.45×18.05×0.1=51.352 m3 第二块: 38.25×18.05×0.1=69.041m3 第三块: 10.5×6.95×0.1=7.2975m3 第四块: 6.95×0.3×0.1=0.2085 m3
3
第五块: 4×3.1×0.1=1.24 m
第六块: 10.65×0.3×0.1=0.3195 m3
3
增加处一: 7.325×7.25×0.03=1.5932 m增加处二: 8.85×7.25×0.04=2.5665 m3 增加处一: 8.85×7.25×0.04=2.5665 m3 炮楼:
第一块: 10.65×7.85×0.1=8.3603 m3 第二块: 10.65×8.95×0.14=13.344 m3 三、梁: 第一层:
KL-1:24.85×0.3×0.6=4.473 m3 KL-2:25.45×0.3×0.6=4.581 m3
3 3
KL-3:24.85×0.3×0.6=4.473 m KL-4:24.85×0.3×0.6=4.473 m KL-5:15.65×0.3×0.6=2.817 m3 KL-6:31.3×0.3×0.6=5.634 m3 KL-7:15.65×0.3×0.6=2.517 m3 KL-8:15.65×0.3×0.6=2.817 m3 KL-9:15.65×0.3×0.6=2.817 m3 KL-10:9.25×0.3×0.6=1.665 m3 KL-11:16.25×0.3×0.6=2.925 m3 KL-12:57.85×0.3×0.6=10.413 m3 KL-13:6.65×0.3×0.6=1.197 m3 KL-14:52.4×0.3×0.6=9.432 m3 KL-15:61.15×0.3×0.6=11.007 m3 KL-16:61.4×0.3×0.6=11.052 m3
3 3
L-1: 7.25×0.25×0.35=0.6344 mL-2:16.85×0.25×0.4=1.685 m L-3: 9.6×0.25×0.4=0.96 m3 L-4:101.1×0.25×0.4=10.11 m3
3 3
L-5: 16.85×0.25×0.35=1.685 mL-6:16.85×0.25×0.4=1.685 m L-7: 14.5×0.25×0.4=1.45 m3 L-8:7×0.25×0.4=0.7 m3 第二至四层:
KL-1:24.85×0.3×0.6×3=13.419 m3 KL-2:25.45×0.3×0.6×3=13.743 m3
KL-3:24.85×0.3×0.6×3=13.743 m3 KL-4:24.85×0.3×0.6×3=13.419 m3
3
KL-5:15.65×0.3×0.6×3=8.451 m
3
KL-6:31.3×0.3×0.6×3=16.902 m
3
KL-7:15.65×0.3×0.6×3=8.451 m KL-8:15.65×0.3×0.6×3=8.451 m3
KL-9:15.65×0.3×0.6×3=8.451 m3 KL-10:9.25×0.3×0.6×3=4.995 m3
KL-11:16.25×0.3×0.6×3=8.775 m3 KL-12:57.85×0.3×0.6×3=31.239 m3
KL-13:6.65×0.3×0.6×3=3.591 m3
授人以渔
能力为本
13
14 四川科技职业学院毕业设计(论文)
KL-14:52.4×0.3×0.6×3=28.296 m3
3
KL-15:61.15×0.3×0.6×3=33.021 m
3
KL-16:61.4×0.3×0.6×3=33.156 m
L-1: 7.25×0.25×0.35×3=1.903125 m3
L-2:16.85×0.25×0.4×3=5.055 m3
L-3: 9.6×0.25×0.4×3=2.88 m3 L-4:101.1×0.25×0.4×3=30.33 m3
L-5: 16.85×0.25×0.35×3=5.055 m3
3
L-6:16.85×0.25×0.4×3=5.055 m
L-7: 14.5×0.25×0.4×3=4.35 m3
3
L-8:7×0.25×0.4×3=2.1 m第五层:
KL-1:24.85×0.3×0.6=4.473 m3 KL-2:25.45×0.3×0.6=4.581 m3 KL-3:24.85×0.3×0.6=4.473 m3 KL-4:24.85×0.3×0.6=4.473 m3 KL-5:15.65×0.3×0.6=2.817 m3 KL-6:31.3×0.3×0.6=5.634 m3 KL-7:15.65×0.3×0.6=2.517 m3 KL-8:15.65×0.3×0.6=2.817 m3
3 3
KL-9:15.65×0.3×0.6=2.817 m KL-10:9.25×0.3×0.6=1.665 m
3 3
KL-11:16.25×0.3×0.6=2.925 m KL-12:57.85×0.3×0.6=10.413 m KL-13:6.65×0.3×0.6=1.197 m3 KL-14:52.4×0.3×0.6=9.432 m3
3 3
KL-15:61.15×0.3×0.6=11.007 m KL-16:61.4×0.3×0.6=11.052 m L-1: 7.25×0.25×0.35=0.6344 m3 L-2:16.85×0.25×0.4=1.685 m3 L-3: 9.6×0.25×0.4=0.96 m3 L-4:101.1×0.25×0.4=10.11 m3 L-5: 16.85×0.25×0.35=1.685 m3 L-6:16.85×0.25×0.4=1.685 m3 L-7: 14.5×0.25×0.4=1.45 m3 L-8:7×0.25×0.4=0.7 m3 四、楼梯一 第一层:
3
平台板: 7.55×3.65×0.13×3=10.74743 mKTL-1 : 13.9×0.25×0.47×3=4.89975 m3
3
KTL-2 : 2.125×0.25×0.27×3=0.551813 mTZ-1 : 0.25×0.4×4.84=0.484 m3 10.2×3.35×0.28=9.5676 m3 第二至四层:
平台板: 7.55×3.65×0.13×3=10.74743 m3 KTL-1 : 13.9×0.25×0.47×3=4.89975 m3 KTL-2 : 2.725×0.25×0.27×3=0.551813 m3
3
TZ-1 : 0.25×0.4×3.94×3=1.182 m 8.72×3.35×0.28×3=24.53808 m3 第五层:
平台板: 7.55×3.65×0.13=3.5825 m3 KTL-1 : 13.9×0.25×0.47=1.6333 m3 KTL-2 : 2.725×0.25×0.27=0.1839m3 TZ-1 : 0.25×0.4×3.94=0.394 m3 8.72×3.35×0.28=8.1794 m3 五、楼梯二
授人以渔
能力为本
14
15 四川科技职业学院毕业设计(论文)
第一层:
TB:4.5×1.7×0.15=1.1475 m
3
平台板: 4.3×3.05×0.13=1.705 m3 KTL-1: 13.9×0.2×0.27=0.7506 m3 KTL-2: 2.275×0.2×0.27=0.1229 m3 TZ-1 : 0.25×0.4×4.84=0.484 m3
10.2×1.7×0.28=4.8552 m3
第二至四层:
TB:3.8×1.7×0.15×1=0.9945 m3
平台板:4.3×3.65×0.13×3=6.12105 m3KTL-1: 13.9×0.2×0.27×3=2.2518 m3
KTL-2: 2.275×0.2×0.27×3=0.44145 m3 TZ-1 : 0.25×0.4×3.94×3=1.82 m3
8.72×1.7×0.28×3=12.45216 m3 第五层:
TB:3.8×1.7×0.15=0.9945 m3
平台板:4.3×3.65×0.13=2.0404 m3
KTL-1: 13.9×0.2×0.27=0.7506 m3
KTL-2: 2.275×0.2×0.27=0.1472 m3
TZ-1 : 0.25×0.4×3.94=0.394 m3
8.72×1.7×0.28=4.1507 m3 第一层总方量:304.0794625 m3
第二层至第四层总方量:878.4625275 m3 第五层总方量:296.839655 m3 炮楼总方量:29.79845 m3 总方量:1509.170095 m3
授人以渔
15
能力为本