系统工程实验课指导书(2)

2019-06-11 08:14

A1234567891011121314BCDEFGH0.6High sales+$300Introduce product-$300+$100+$6000.4Low sales+$100-$200+$300=1-H1-$2001+$100Model Output CellDon't introduce$0$0$0IJKLModel Input Cell NO+$1000.000.100.200.300.400.500.600.700.800.901.00P=A10M1234567891011121314

M1234567891011121314NOP(High Sales)Exp. Value0.000.100.200.300.400.500.600.700.800.901.000000050100150200250300P 6

To solve the problem, operate as the following procedure step by step.

1. Construct a decision tree model or financial planning model. 2. Identify the model input cell (H1) and model output cell (A10).

3. Modify the model so that probabilities will always sum to one. (That is, enter the

formula =1-H1 in cell H6.) 4. Enter a list of input values in a column (N3:N13).

5. Enter a formula for determining output values at the top of an empty column on the right

of the input values (=A10 in cell O2). 6. Select the data table range (N2:O13).

7. From the Data menu choose the Table command.

8. In the Data Table dialog box, select the Column Input Cell edit box. Type the model

input cell (H1), or point to the model input cell (in which case the edit box displays $H$1). Click OK. 9. The Data Table command substitutes each input value into the model input cell,

recalculates the worksheet, and displays the corresponding model output value in the table. 10. Optional: Change the formula in cell O2 to =CHOOSE(B9,”Introduce”,”Don’t”).

4. Finish the experimentation report.

7

Systems Engineering Experiment Ⅱ

1. Experiment Objectives

From OR Courseware Recall the following contents: (1) The interpretation of the Decision Trees

(2) The procedure of building decision trees by Treeplan

2. Experiment Tasks

Problem :

The GOFERBROKE COMPANY owns a tract of land that may contain oil. A consulting

geologist has reported to management that she believes there is 1 chance in 4 of oil. Because of this prospect, another oil company has offered to purchase the land for $90,000. However, Goferbroke is considering holding the land in order to drill for oil itself. The cost of drilling is $100,000. If oil is found, the resulting expected revenue will be $800,000, so the company's expected profit (after deducting the cost of drilling) will be $700,000. A loss of $100,000 (the drilling cost) will be incurred if the land is dry (no oil).

How to approach the decision of whether to drill or sell based just on these data. However, before deciding whether to drill or sell, another option is to conduct a detailed seismic survey of the land to obtain a better estimate of the probability of finding oil.

Status of Land Alternative Oil $700,000 $90,000 1 in 4 Payoff Dry -$100,000 $90,000 3 in 4 Drill for Oil Sell the Land Chance of Status Questions:

(a) Formulate the decision tree model for this problem. (b) Build the model on an Excel spreadsheet. (c) Use the Excel Treeplan to solve the model.

3. Finish the experimentation report.

8

Systems Engineering Experiment Ⅲ

1. Experiment Objectives:

Learn how to manage project using Project 2000

2. Experiment Tasks:

Formulate and solve the following project management problems using Project 2000. Problem:

The RELIABLE CONSTRUCTION COMPANY has just made the winning bid of $5.4 million to

construct a new plant for a major manufacturer. The manufacturer needs the plant to go into operation within a year. Therefore, the contract includes the following provisions:

? A penalty of $300,000 if Reliable has not completed construction by the deadline 47 weeks

from now. ? To provide additional incentive for speedy construction, a bonus of $150,000 will be paid to

Reliable if the plant is completed within 40 weeks. The following table shows the list of the various activities. The third column provides important additional information for coordinating the scheduling of the crews.

Activity A B C D E F G H I J K L M N

When a given activity has more than one immediate predecessor, all must be finished before

Activity Description Excavate Lay the foundation Put up the rough wall Put up the roof Install the exterior plumbing Install the interior plumbing Put up the exterior siding Do the exterior painting Do the electrical work Put up the wallboard Install the flooring Do the interior painting Install the exterior fixtures Install the interior fixtures Immediate Predecessors → A B C C E D E,G C F,I J J H K,L Estimated Duration 2 weeks 4 weeks 10 weeks 6 weeks 4 weeks 5 weeks 7 weeks 9 weeks 7 weeks 8 weeks 4 weeks 5 weeks 2 weeks 6 weeks 9

the activity can begin. Adding up these times gives a grand total of 79 weeks, which is far beyond the deadline for the project. Fortunately, some of the activities can be done in parallel, which substantially reduces the project completion time.

Given all the information in the above table, develop answers to the following questions using project 2000.

1. What is the total time required to complete the project if no delays occur?

2. When do the individual activities need to start and finish (at the latest) to meet this project

completion time? 3. When can the individual activities start and finish (at the earliest) if no delays occur? 4. Which are the critical bottleneck activities where any delays must be avoided to prevent

delaying project completion? 5. For the other activities, how much delay can be tolerated without delaying project

completion? 6. What is the Critical Path?

3. Finish the experimentation report.

10

Systems Engineering Experiment Ⅳ

1. Experiment Objectives:

Recall project management operation and have a quiz in class

2. Experiment Tasks:

Task 1: Solve the following problem:

Construct the project network for a project with the following activities list. Please calculate

the engineering time, and find the critical path.

Series Numbers 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Activity A B C D E F G H I J K L M N Immediate Predecessors - A B B B C D, E F G, H I I J K L Estimated Duration 1 Month 2 Months 4 Months 3 Months 2 Months 3 Months 5 Months 1 Month 4 Months 2 Months 3 Months 3 Months 5 Months 4 Months

Task 2: A quiz

Open file of ORtest2.htm and give the answer to each problem, submit the answer and get the score.

11


系统工程实验课指导书(2).doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:化妆品半成品分装企业生产条件审查办法说明

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: