第一章、工程总体概述 ··································································································································································· 第一节 工程概况 ························································································································································ 第二节 本工程施工管理目标承诺 ························································································································· 第三节 施工阶段的划分 ··········································································································································· 第四节 施工措施和施工方案的选择 ····················································································································· 第五节 新技术应用措施方案 ·································································································································· 第二章、施工进度计划和各阶段进度的保证措施及违约承诺 ····················································································· 第一节 施工进度计划编制依据及原则 ················································································································ 第二节 施工工期计划 ··············································································································································· 第三节 工程进度控制管理方法······························································································································ 第四节 工程工期总体控制和缩短工期措施 ········································································································ 第五节 关键阶段工程进度计划保证措施 ············································································································ 第三章、劳动力和材料投入计划及其保证措施 ·················································································································· 第一节 劳动力投入计划及保证措施 ····················································································································· 第二节 材料投入计划及保证措施 ························································································································· 第四章、机械设备投入计划及检测设备 ································································································································· 第一节 主要施工设备配备说明······························································································································ 第二节 施工机械设备表 ··········································································································································· 第三节 施工机械保养、维修措施 ·························································································································
1
第五章、施工平面布置图和临时设施布置 ···························································································································· 第一节 施工平面布置的基本原则 ························································································································· 第二节 临时生产生活设施规划及布置 ················································································································ 第三节 施工总平面布置图 ······································································································································ 第四节 施工临时设施修建计划······························································································································ 第五节 临时用水设计与布置 ·································································································································· 第六节 施工临时用电设计布置······························································································································ 第六章、关键施工技术、工艺及工程项目实施的重点难点和解决方案 ·································································· 第一节 施工测量及沉降监测方案 ························································································································· 第二节 外脚手架及垂直运输工程 ························································································································· 第三节 基础及地下室工程 ······································································································································ 第四节 模板工程 ························································································································································ 第五节 钢筋工程 ························································································································································ 第六节 混凝土工程 ··················································································································································· 第七节 砌体工程 ························································································································································ 第八节 屋面防水工程 ··············································································································································· 第就节 装饰工程 ························································································································································ 第十节 机电工程 ·························································································································································· 第十二节 工程项目的重点、难点分析和解决方案 ·························································································· 第七章、安全文明施工措施 ························································································································································· 第一节 安全管理机构和管理制度的建立 ············································································································ 第二节 文明施工措施 ··············································································································································· 第三节 环境保护措施 ··············································································································································· 第四节 保护现有建筑物、道路、绿化、居民及市政管道的措施 ································································ 第八章、质量保证措施及承诺 ····················································································································································
2
第一节 创优目标 ························································································································································ 第二节 质量保证体系的组成 ·································································································································· 第三节 施工过程质量保证措施······························································································································ 第四节 工程创优体系及保证措施 ························································································································· 第五节 关键工序质量控制措施······························································································································ 第六节 质量通病治理措施 ······································································································································ 第九章、新技术应用措施 ······························································································································································ 第一节 钢筋混凝土框架节点模板工法 ················································································································ 第二节 钢筋直螺纹连接技术 ·································································································································· 第三节 MT砂浆新技术的应用 ································································································································· 第十章、总承包管理及配合措施 ················································································································································ 第一节 总包方的主要协调配合······························································································································ 第二节 总包责任方管理职责 ·································································································································· 第三节 总包责任方对专业施工单位管理总体配合 ·························································································· 第四节 总包责任方对安装工程的照管、配合、协调管理措施 ····································································· 第五节 工程总包责任方与业主、监理及地方政府主管部门、社区等公共关系处理 ····························· 第十一章、项目组织机构及主要人员 ······································································································································ 第一节 项目施工管理组织机构······························································································································ 第二节 项目主要部门、人员的岗位职责 ············································································································
3
第一章、工程总体概述
第一节 工程概况
一、工程名称及地理位置
本工程为科教花园高层,位于衡阳市区,西临城市主干道红湘南路,南临雁城路,北面为石塘路。 二、施工现场条件
1、根据现场勘察,三通一平已完成。 三、参建单位
建设单位 设计单位 勘察单位 监理单位 施工单位
衡阳市福泰房地产开发有限公司 衡阳市经纬建筑设计有限公司 核工业岩土工程勘察设计研究院 衡阳市吉康监理有限公司 衡阳市楚材城乡建筑工程有限公司 四、工程概况
1、工程规模
科教花园高层包括7栋、8栋、15栋、16栋商住楼,总建筑面积为49708.42㎡。7栋、8栋为11层小高层,7栋建筑面积为5470.52㎡,商铺面积为543㎡;8栋建筑面积为8725.46㎡,商铺面积为794.88㎡;15栋、16栋为17层高层商住楼,负一层为地下车库,一、二层为商业用房,三至十五层为住宅;15栋建筑面积为17971.62㎡,其中地下车库为1648.68㎡,商铺面积为3012.24㎡;16栋建筑面积为15662.3㎡,其中地下车库为1662.05㎡,一、二层商场为2820.1㎡,住宅11180.15㎡。建筑高度为49.80m。结构均为框架剪力墙结构。现以16栋商住楼做本施工组织设计。
2、基础工程概况
本工程基础采用人工挖孔桩基础,持力层为中风化岩,桩端承载力特征值为330Kpa,桩径分别为900、1100、1400、1500㎜五种。桩身混凝土强度为C30,
4
均采用导管水下灌注。
3、结构工程概况
?、本工程结构为框架剪力墙结构,建筑结构类别为A级,结构设计的使用年限为50年,本工程为二类高层建筑,耐火等级为二级,结构安全等级为二级。
?、本工程钢筋采用HPB235钢筋、HRB335钢筋或HRB400钢筋、RRB400钢筋,结构混凝土等级为C25~C40。
16栋各部位混凝土材料强度等级表
剪力墙、柱 梁、板 地下层C40 地梁、地下室底板C30 1~2层C40 1~3层C40 3~4层C30 4~5层C30 5~17层C25 屋面水箱C30 6~17层C25 屋面C25 ?、本工程框架柱及剪力墙混凝土等级为C40~C25。
?、本工程地下室工程共一层,混凝土采用C40及C30,地下室底板、顶板、侧墙采用S6抗渗混凝土(防水混凝土的施工配合比尚应通过抗渗性试验确定,试验时抗渗等级应提高到S8),桩顶、地下一层梁板标高为-3.620m,基础垫层为100厚C10素混凝土垫层。
?填充墙土中外墙采用180厚M10页岩砖M7.5混合砂浆砌筑;内隔墙部分采用180厚加气混凝土砌块M5.0混合砂浆砌筑;卫生间采用120厚M10页岩砖M5.0混合砂浆砌筑。
?、本工程首层为4.20m,2层层高为5.10m,2至17层为2.70m ,总建筑高度为51.2m。
4、节能设计
(1)外墙为墙体自保温:饰面层(不计入)+耐碱玻纤网布抗裂砂浆(5㎜)+界面砂浆(不计入)+加气砼砌块(200㎜)+混合砂浆(20㎜)。
(4)屋面类型:细石混凝土(40㎜)+水泥砂浆(20㎜)+挤塑聚苯板(40㎜)+水泥砂浆(20㎜)+改性沥青防水卷材+钢筋混凝土屋面板(120㎜)+混合砂浆(20㎜)。