1.适用范围 ......................................................................... 1 适用于津秦客运专线工程五标段内承担的路桥、路涵、路堑与路堤间的过渡段路基工程。 ............................................. 1 2.作业准备 ......................................................................... 1 2.1内业技术准备 ................................................................... 1 2.2外业技术准备 ................................................................... 1 3.技术要求 ......................................................................... 1 4.施工程序与工艺流程 ...................................................... 2 4.1施工程序 ........................................................................... 3 4.2 工艺流程 ........................................................................... 3 5.施工要求 ......................................................................... 4 5.1施工准备 ........................................................................... 4 5.1.3过渡段填筑试验段 ....................................................... 4 5.2施工工艺 ........................................................................... 4 5.2.1过渡段类型 ................................................................... 4 5.2.1.1路堤与桥台过渡段结构型式如下图所示: ........... 4 5.2.1.2路堤与横向结构物过渡段结构型式如下: ........... 5 5.2.2施工工艺 ....................................................................... 6 5.2.2.1基底处理 ................................................................... 6 5.2.2.2结构物基坑回填 ....................................................... 6 5.2.2.3基床表层以下过渡段水泥级配碎石 ....................... 6 5.2.2.5过渡段(填料过渡段)A、B组填料 ...................... 7 5.2.2.6基床表层以下过渡段两侧及锥体填土 ................... 7 5.2.2.7基床表层过渡段水泥级配碎石 ............................... 7
6.劳动组织 ......................................................................... 7 7.材料要求 ......................................................................... 8 8.设备机具配置 ................................................................. 9 8.1主要机械设备配置 ........................................................... 9 9. 质量控制及检验 ............................................................. 9 9.1 质量控制 ........................................................................... 9 9.1.1 层厚控制 ....................................................................... 9 9.1.2 填料平整及均匀性控制 ............................................. 10 9.1.3边坡平顺及压实控制 ................................................. 10 9.2检验标准 ......................................................................... 10 9.2.1过渡段基底处理 ......................................................... 10 9.2.2基坑回填 ..................................................................... 11 9.2.3基床表层以下级配碎石填层 ..................................... 11 9.2.4 基床表层以下过渡段两侧及锥体填土 ..................... 12 9.2.5基床表层以下填料过渡段填层 ................................. 13 10.安全及环保要求 .......................................................... 13 10.1安全要求 ....................................................................... 13 10.2环保要求 ....................................................................... 14
1.适用范围
适用于津秦客运专线工程五标段内承担的路桥、路涵、路堑与路堤间的过渡段路基工程。
2.作业准备 2.1内业技术准备
在开工前,技术主管组织现场技术人员认真学习实施性施工组织设计、作业指导书等相关内容。审核施工图纸,充分理解设计意图和有关技术要求,熟悉规范和技术标准。制定施工安全质量保证措施,有充分的技术准备工作。试验人员完成路基过渡段填料的试验工作,包括路基填料天然含水量,最佳含水量、最大干密度等相关技术参数。技术主管对施工人员进行技术交底,并就施工过程中质量控制、试验检测工作进行针对性的学习和培训,确定现场技术的分工合作,对参加施工人员进行上岗技术培训,考核合格后上岗。
2.2外业技术准备
施工作业层中所涉及的各种外部技术数据收集。 3.技术要求
3.1在路堤与桥台、路堤与横向结构物的连接按设计要求施工过渡段。
3.2桥台和横向结构物基坑的回填工作必须在隐蔽工程验收合格后才能进行。
3.3过渡段范围的原地面处理应符合地基处理的有关规定。
-1-
3.4 过渡段级配碎石应分层填筑压实,每层的压实厚度不应大于30cm,最小压实厚度不宜小于15cm,具体的摊铺厚度及碾压遍数应按工艺试验确定的工艺参数进行控制。每压实层路拱坡面应符合设计要求,无积水现象。
3.5 过渡段级配碎石填层应与相邻的路堤及锥体同时施工,并将过渡段与连接路堤的碾压面按大致相同的水平分层高度同步填筑并均匀压实。在填筑压实过程中,应保证桥台、横向结构物稳定、无损伤。
3.6 过渡段地基采用打入桩加固时,宜先进行打入桩施工,再进行桥涵桩基施工。
3.7过渡段排水要求
3.7.1过渡段施工前,应根据场地情况,采取相应的防排水措施。
3.7.2过渡段台背回填料表面应按设计要求采取措施防止地表水渗入。
3.7.3过渡段台背与回填料之间应按设计要求设置防排水层。
3.7.4过渡段级配碎石填料与相邻路堤填料之间的反滤层应按设计要求进行施工。
3.7.5过渡段坡脚两侧、路堤底部的纵横向排水措施应符合设计要求。
3.8过渡段路堤两侧防护砌体的施工应在地基和路堤变形稳定后进行。宜与相邻路堤的防护砌体施工相互协调。
4.施工程序与工艺流程
-2-
4.1施工程序
施工程序为:施工准备→填筑试验段→确定工艺→结构物基坑混凝土回填→原地面整平压实→测量放样→混合料拌和→运输→填筑→摊铺平整→碾压→检验验收
4.2 工艺流程
结构物基坑混凝土回填 原地面平整压实 检验签证 否 过渡段水泥级配碎倒梯形过渡段A B组填料 路堤A B组填料 同时分层填筑压实 基床表层上层摊铺机摊铺压实 检验签证 是 否 -3-
下道工序