商业广场项目
1
安全文明施工方案
目录
第一章 工程概况·········································5 1.1工程概况···············································5 1.2编制依据···············································6 第二章 安全生产目标·····································8 2.1安全生产目标···········································8 2.2安全管理基础资料·······································8 第三章 安全生产保证措施································10 3.1现场安全保证体系······································10 3.2安全组织措施和职责····································10 3.3安全管理制度··········································14 3.4安全生产基本措施······································16 第四章 本工程重点安全生产控制措施······················20 4.1现场安全检查措施······································20 4.2基础工程安全施工措施··································20 4.3脚手架工程············································22 4.4模板工程··············································24 4.5临边、洞口及高处作业安全防护技术措施··················25 4.6主体结构安全施工措施··································26 4.7装饰装修工程安全施工措施······························27 4.8现场施工用电安全措施··································28 4.9建筑施工高处作业安全措施······························33
2
4.10防雷击安全措施·······································35 4.11塔吊安全作业措施·····································35 4.12施工机具安全措施·····································36 第五章 文明施工目标及文明施工保证措施··················37 5.1文明施工目标··········································37 5.2文明施工管理控制流程图································37 5.3文明施工保证措施······································38 5.4本工程重点文明施工控制措施····························41 第六章 环境、消防等其他方面保证措施····················43 6.1环境保护的措施········································43 6.2现场消防的措施········································46 6.3夏、雨季施工措施······································47 6.4冬季施工措施··········································50 6.5确保不拖欠民工工资的措施······························51 第七章 施工现场平面图布置说明··························52 7.1工程概况··············································52 7.2施工平面布置原则及说明································52 7.3施工平面布置及说明····································53 第八章 附表附图········································55
3
·第一章 工程概况
·1.1、工程概况 (一)、工程现场情况
**市**新区**广场位于**市**新区西藏路与武汉路交叉口北侧,场内交通较为方便,施工用水、电已经接引至现场,供水管径50mm,从现场东侧约50M外接水口接水,水压较为稳定;现场北侧设置有业主安装的1台400KVA变压器,可以满足施工用电所需。
因施工用电、供水到现场,现场供电、供水和排水情况根据设计单位提供的总平图布置完好,具备开工条件。 (二)、建筑特征及使用功能
**新区**广场工程,该项目为一个综合性建筑,主要功能为商业及办公,本工程总建筑面积为64050㎡。计划工期为270天,主楼25层,裙楼5层,地下2层。主楼建筑高度99.30米,副楼建筑高度23.70米,结构形式为框筒结构。地下室,地下二层,负一层层高5.6米,负二层层高3.6米,为设备用房及车库,总建筑面积13973㎡
使用功能为商业用房。耐火等级为地上一级地下一级;主要结构形式为砼框架结构及框筒结构,抗震设防烈度为7度,设计使用年限50年。建设单位为安徽众友投资管理有限公司,设计单位为**建筑设计研究院有限公司,监理单位:安徽南巽建设项目管理投资有限公司; (三)、结构特征
本工程抗震设防烈度为7度,设计使用年限50年,设计基本地震加速度为 0.10g,设计地震分组为第2组, 场地类别为 II类,场地土特
4
征周期Tg=0.35秒,地下室及主楼抗震等级为一级,其它部分为二级本工程主楼部分采用桩筏基础,其余采用筏板基础。
·1.2、编制依据
①**建筑设计研究有限公司设计的本工程施工图纸 ②《中华人民共和国建筑法》 ③《中华人民共和国安全法》 ④《建设工程安全生产管理条例》 ⑤《实施工程建设强制性标准监督规定》 ⑥《安全技术操作规程》 ⑦中华人民共和国消防条例
⑧国家、省、市颁发的有关建筑工程的法律、法规和规定等 ⑨施工现场实际情况
·1.3采用的规范、规程、标准
①《建筑施工安全检查标准》JGJ59—2011 ②《施工现场临时用电安全技术规程》JGJ46-2005 ③《建筑工程施工现场供电安全规范》GB50104—93 ④《建筑施工扣件式钢管脚手架安全技术规范》JGJ130-2011 ⑤《建筑施工高处作业安全技术规范》JGJ80-91 ⑥《建筑机械使用安全技术规程》JGJ33-2012 ⑦《安全帽》GB2811—2007 ⑧《安全带》GB6095—2009
5