XX高速公路 XX段改扩建工程
创优规划实施方案
编制: 审核:
XX集团有限公司
XX高速公路XX段改扩建工程TJ-3标项目经理部
二〇一一年三月
目 录
绪论 ························································································································ 3 一、工程概况................................................................................................................. 4 工程简介 ························································································································ 4
XXXX灵(豫陕界)段改扩建工程TJ-03标 创优规划实施方案
自然条件 ························································································································ 4 二、创优规划指导思想 ................................................................................................ 5 三、创优规划管理目标 ................................................................................................ 6 (一) 创优质量目标: ·································································································· 6 (二) 创优进度目标: ·································································································· 6 (三) 创优文明施工目标:·························································································· 6 (四) 创优廉政目标: ·································································································· 6 四、创优标准................................................................................................................. 7 五、工程创优质量保证体系 ........................................................................................ 8 (一) 工程质量创优计划······························································································ 8 (二) 质量创优保证体系的建立与运行······································································ 8 六、工程创优质量保证措施 .......................................................................................11 (一) 创优质量管理措施·····························································································11 (二) 工程创优技术保证措施···················································································· 14 七、创优工期保证措施 .............................................................................................. 21 (一) 施工计划保证工期···························································································· 21 (二) 施工资源上保证工期························································································ 21 (三) 技术上保证工期 ································································································ 21 (四) 环境上保证工期 ································································································ 22 (五) 安全生产上保证工期························································································ 23 八、创优安全保通措施 .............................................................................................. 26 (一) 项目主要管理人员的安全职责:···································································· 26 (二) 安全保障检查程序与保障措施········································································ 28 九、文明施工创优保证措施 ...................................................................................... 31 (一) 组织机构 ············································································································ 31 (二) 制订健全的管理制度························································································ 31 (三) 管理措施 ············································································································ 32 (四) 现场管理 ············································································································ 32 (五) 健全管理资料 ···································································································· 33 (六) 开展文明施工竞赛···························································································· 34 (七) 加强教育培训工作···························································································· 34 十、廉政工作创优保证措施 ...................................................................................... 35 (一) 相关各方的配合及协调 ··············································································· 35 (二) 廉政工作保证措施 ······················································································· 35 (三) 项目建设资金管理 ······················································································· 37
2
XXXX灵(豫陕界)段改扩建工程TJ-03标 创优规划实施方案
绪论
为认真深入贯彻省厅“创优座谈会”精神,落实“全省高速公路建设项目创国家优质工程动员会”的工作部署,明确理念是灵魂、设计是基础、管理是关键、施工是保证,深刻理解构建优质高速公路的内涵,准确把握高速公路建设管理创优的重要性,对此我们结合自身的实际情况,特制定本方案。
3
XXXX灵(豫陕界)段改扩建工程TJ-03标 创优规划实施方案
一.工程概况
工程简介
我单位承建的XX高速公路洛阳至三门峡(豫陕界)改扩建工程土建№3合同段,地处新安县境内,合同段起点为RK25+500,位于后峪村南新石公路东侧,延续北侧整体式加宽方式,向西跨越牌楼沟,设大桥通过,路线继续向西经过新安县城北,跨越省道S246,设新安互通式立交,作为新安县的出入口,再向西,跨越王庄水库,设大桥通过,经西庄、槐林北到达本合同段终点RK31+700。本合同段路线长6.2公里。
本合同段共设大桥1343.4米/4座,互通式立交1处,分离式立交1座,天桥6座,通道5道、涵洞9道。填土方217.314千立方米,挖土方361.226千立方米,挖石方34.578千立方米。占用土地249.3991亩。 自然条件
项目所在地区洛阳、三门峡位北暖温带半干旱、半潮湿大陆性季风气候,冷暖适中,四季分明,雨热同期、干冷同季。
项目区域为大陆性季风气候特征,四季分明,多年平均气温为13.9°C,春夏秋冬平均气温分别为12.3°C~15.2°C、22.9°C~26.6°C、12.3~14.9°C、0.5°C~2.0°C。四季时节分部,夏多冬少,春秋居中。区内一个月盛行偏北风,七月盛行偏南风。平均风速冬季1.1~3.1米/秒,春季2.4米/秒,夏季1.8米/秒,秋季1.7米/秒。全年以冬春风速较大,多大于2米/秒,夏秋风速较小,多小于2米/秒。
4
XXXX灵(豫陕界)段改扩建工程TJ-03标 创优规划实施方案
二.创优规划指导思想
通过五个标准化管理,即:驻地建设标准化管理、试验室建设标准化管理、拌和站和预制场建设标准化管理、便道等施工现场保通、安全和文明施工标准化管理、项目创优施工工法标准化管理;实现总体工程优良、结构工程精品、附属工程协调、景观工程优美,确保省级优质工
程一等奖,争创国家优质工程的总体建设目标。
5