内江市西林大道北延线道路工程
管 道 吊 装 专 项 方 案
四川省建筑机械化工程公司 二0一二年九月十日
四川省建筑机械化工程公司 1
目 录
1 工程概况 .........................................................................................................................................................3
1.1 工程概述 ..............................................................................................................................................3 1.2 工程特点 ..............................................................................................................................................3 1.3 主要工程量 ..........................................................................................................................................4 2 施工依据及编制依据 .....................................................................................................................................5
2.1 施工依据 ..............................................................................................................................................5 2.2 编制依据 ..............................................................................................................................................5 3 施工部署 .........................................................................................................................................................6
3.1 项目管理机构 ......................................................................................................................................6 3.2 具体人员安排 ........................................................................................................................................6 3.3 吊装进度计划 ........................................................................................................................................7 3.4 劳动力配置 ............................................................................................................................................7 4 施工准备 .........................................................................................................................................................8
4.1 施工工艺 ..............................................................................................................................................8 4.2 施工技术准备 ......................................................................................................................................8 4.3 施工场地安排及施工机具准备 ..........................................................................................................8 4.4 施工前进行教育培训 ..........................................................................................................................9 5 受力分析 .......................................................................................................................................................10
5.1 排水管规格及参数 ............................................................................................................................10 5.2 吊车受力分析 ....................................................................................................................................10 5.3 钢丝绳的受力 ....................................................................................................................................13 6 施工方法 .......................................................................................................................................................14
6.1 吊装前准备工作 ................................................................................................................................14 6.2 吊装注意事项 ....................................................................................................................................14 6.3 吊装方法 ............................................................................................................................................15 7 雨季施工措施 ...............................................................................................................................................16 8 安全保证措施 ...............................................................................................................................................17
8.1 安全技术的基本要求 ........................................................................................................................17 8.2 吊车吊装安全技术要求 ....................................................................................................................17 8.3 发现问题的应急措施 ........................................................................................................................18 9 应急预案 .......................................................................................................................................................19 重大风险及危险源的评价、确定及防护措施 .................................................................................................19
四川省建筑机械化工程公司 2
1 工程概况 1.1 工程概述
本工程位于内江市东兴区胜利镇,起自321国道(K0+000),止于北环路(K1+583.91),道路横断面采用“一块板”型式,设计红线宽度为50m,其中:车行道24m,人行道7m×2,绿化带6m×2。该道路属内江市城市II级主干道。设计行车速度:40公里/小时,设计标准荷载:BZZ100KN,设计年限:15年,道路桩号K0+220~K0+320和K0+680~K0+740路段设计采用CFG桩复合地基对路堤进行处理。 1.2 工程特点 1.2.1 涵洞工程
全工程段涵洞2道,双排DN1500钢筋砼排水管。分别位于桩号K0+300、K0+710,涵长分别为76.06m、89.48m。两道涵洞均位于回填区内,设计涵底高程分别为334.293、327.555,涵管采用每节2米长钢筋砼平口管,每节管道重3.956T,管顶覆土深度分别为7.761m、11.087m。 1.2.2 排水工程
排水工程设计双污、双雨。雨水管道分别位于道路两侧绿化带内,设计雨水中线距道路中线距14.5m,每条雨水管长度为1448.5m,总长2897m,其中:DN600II级钢筋砼承插管1350m,每节管道长2.5m,每节管道重0.791T,埋深2.03m;DN800II级钢筋砼承插管1547m,每节管道长2.5m,每节管道重1.407T,埋深2.28m;污水管道分别位于道路两侧人行道内,设计污水中线距
四川省建筑机械化工程公司 3
道路中线距20m,每条污水管道长度为1471.5m,总长2943m,全线为DN600II级钢筋砼承插管,每节管道长2.5m,每节管道重0.791T,埋深3.03m。 1.3 主要工程量
1.3.1 III级DN1500钢筋砼平口管331.08m; 1.3.2 II级DN600承插式钢筋砼雨水管1350m; 1.3.3 II级DN800承插式钢筋砼雨水管1547m; 1.3.4 I级DN300承插式钢筋砼雨水支管515m; 1.3.5 II级DN600承插式钢筋砼污水管2943m; 1.3.6 II级DN400承插式钢筋砼过街预埋管150m;
四川省建筑机械化工程公司 4
2 施工依据及编制依据 2.1 施工依据
1、根据施工图纸资料及施工组织设计和我公司与甲方签订的工程承包合同;
2、根据《给水排水管道工程施工及验收规范》GB50268—2008; 3、《给水排水标准图集》(2005年合订本)。 2.2 编制依据
1、根据内江市西林大道北延线道路工程设计图纸、资料及业主要求; 2、根据《工程建设安装工程起重施工规范》HG 20201-2000; 3、根据《实用给水排水工程施工手册》中国建筑工业出版社。 4、根据施工现场实际情况。
四川省建筑机械化工程公司 5