编号:Q/52SPP—2009—07—002
10kV双山干改造工程停电架设导线作业指导书
26
编写:__________ __________年_______月_______日 审核:__________ __________年_______月_______日 批准:__________ __________年_______月_______日
作业负责人:__________
作业时间: 2009 年 07月 29 日 07 时 30 分至 2009 年 07 月 29 日 17 时 30 分
鞍山市申普电力安装有限公司送配电公司
目 录
一、准备阶段 ····························································· 第1页
1.1 准备工作安排 ············································· 第1页 1.2 作业现场示意图 ········································· 第2页 1.3 危险点分析及安全控制措施 ····················· 第3页 二、作业阶段 ····························································· 第4页
2.1 作业开工 ····················································· 第4页
2.2 作业内容、步骤及工艺标准 ······················ 第4页2.3 作业结束 ······················································ 第5页三、总结阶段 ······························································ 第5页召开班后会 ··························································· 第5页附件1 主要工器具指导卡 附件2 主要设备材料指导卡
27
一、准备阶段 1.1 准备工作安排
√ 序号 内 容 标 准 责任人 备 注 1 现场勘察 经现场勘察本次作业需要停电的范围:与立山供电分公司调度核对10KV双山干24#、25#柱上开关在切位;10KV双通分2#柱上开关在切位(2台);10KV环山支17#柱上开关在切位(2台),拉开10KV朝阳分1#柱上开关(2台),拉开双山变配出10KV双山干双山线、双余线盘开关;将10KV双山干1#—23#、10KV朝阳分2#—10KV环山支16#高压线路停电。双山干12#—朝阳分5#架设导线作业时跨越公路,设专人监护并持旗看守。 2 明确工作任务 10KV双山干12#—10KV朝阳分5# 1、架设导线JKLYJ—240×6条×1档 3 确定作业方法 采用人工撤放线,电动绞磨紧线。 4 签发工作票 (1)填写、审核工作票填写的正确性; (2)交工作票签发人进行签发。 5 (1)组织学习本次作业的作业指导书; (2)做好危险点分析; (3)交待安全注意事项; 召开班前会 (4)学习检修质量技术标准; (5)交待人员分工; (6)主要工器具及材料准备。 见附件1、2
28
29
1.2 作业现场示意图
30
10kV××线1#~24#更换导线作业现场示意图