编号:×××
4. 10kV××线电缆线路停电作业指导书
编写:__________ __________年_______月_______日 审核:__________ __________年_______月_______日 __________ __________年_______月_______日 批准:__________ __________年_______月_______日
作业负责人:__________
作业时间: 年 月 日 时 分至 年 月 日 时 分
××供电公司××供电分公司
目 录
一、准备阶段 ····························································· 第×页
1.1 准备工作安排 ············································· 第×页 1.2 作业现场示意图 ········································· 第×页 1.3 危险点分析及安全控制措施 ····················· 第×页 二、作业阶段 ····························································· 第×页
2.1 作业开工 ····················································· 第×页
2.2 作业内容、步骤及工艺标准 ······················ 第×页2.3 作业结束 ······················································ 第×页三、总结阶段 ······························································ 第×页召开班后会 ··························································· 第×页附件1 主要工器具指导卡 附件2 主要设备材料指导卡
37
一、准备阶段 1.1 准备工作安排
√ 序号 内 容 标 准 责任人 备 注 1 现场勘察 写明现场实际情况:现场勘察应查看现场施工(检修)作业需要停电的范围、保留的带电部分和作业现场的条件、环境及其他危险点等。 ××× 2 明确作业任务 10kV××线停电××#开闭站、环网柜清扫检查。 ××× 3 确定作业方法 清扫检查 ××× 4 签发工作票 (1)填写、审核工作票的正确性; (2)交工作票签发人进行签发。 ××× 5 召开班前会 (1)组织作业人员认真学习作业指导书; (2)做好危险点分析; (3)交待安全注意事项; (4)作业人员学习质量技术标准; (5)交待人员分工; (6)工器具及材料准备。 ××× 见附件1 、2
38
1.2 作业现场示意图
10kV××线电缆线路停电作业现场示意图
39
1.3 危险点分析及安全控制措施
√ 序号 危险点 安全控制措施 (1)挂接地线前,应将该电缆逐相放电; (2)环网柜停电、验电、挂接地线后,应在所停开关或拔下的插拔头处悬挂“禁止合闸,有人工作!”警告牌。 (1)高处人员应防止掉东西,使用工具材料应用传递绳传递; (2)电缆井内有人作业,井口应设专人监护。 备 注 1 2 触电伤害 高处坠落、坠物伤人 二、作业阶段 2.1 作业开工
√ 序号 内 容 办理工作许可手续 标 准 备 注 1 工作负责人得到全部工作许可人许可后,并在工作票上签名或记录。 工作负责人宣读工作票,交待有电部位及安全措施。经危险点告知提问无误后,作业人员在工作票上签名确认。 (1)断开有可能反送电的10—20kV用户分支开关,挂“禁止合闸,有人工作!”标示牌; (2)断开危及该线路停电作业,且不能采取相应安全措施的交叉跨越、平行和同杆架设线路的开关、刀闸和熔丝保险; (3)断开作业地段有可能返回低压电源的开关和熔断器,挂“禁止合闸,有人工作!”标示牌或将熔断器熔丝管摘下; (4)线路停电作业时,工作班在工作地段两端装设接地线,装设地点如和配电调度掌握的地线重合时可以借用,作业人员必须始终处在接地线的保护范围内;必须将临近保留的带电线路和带电设备的名称和地点详细填写在工作票中,并在有误登可能的地点设专人监护; (5)工作班现场应挂的高、低压接地线; 2 宣读工作票 3 辅助安全措施 40