安全施工技术方案(新)(6)

2019-03-28 08:02

Mmax=FL1

=0.96*0.4 =0.384KN.m Vmax=F

=0.96KN

σ=M/W=0.384*106/5.08*103 =75.6N/mm2<205N/mm2=f wmax=FL1(3L2-4L12)/24EI

=0.96*1000*400*(3*12002-4*4002)/(24*2.06*105*12.19*104) =2.4mm<1200/150=8mm(满足要求) C、横向水平杆验算

F=0.96KN

1200 1200 A′ A B

(b)

Mmax=0.188FL

=0.188*0.96*1.2 =0.22KN.m Vmax=0.688F =0.688*0.96

=0.66KN

25

σ=M/W=0.22*106/5.08*103

=43.3N/mm2<205N/mm2=f wmax=0.911FL3/100EI

=0.911*0.86*1000*12003/(100*2.06*105*12.19*104) =0.54mm<1200/150=8mm d、支座处扣件抗滑移 Vmax=0.66KN<8KN 均满足要求. 均布荷载+集中荷载

在集中力和均布力共同作用下,弯距取分别作用时弯距和的最大值 a、内楞强度验算 Mmax=0.188FL+0.125qL2

=0.188*2.98*0.6+0.125*1.532*0.6*0.6 =0.41KN.m Vmax=0.688F+0.625qL

=0.688*2.98+0.625*1.532*0.6 =2.62KN

σ=M/W=0.41*106/(50*1002/6)

=4.9N/mm2<13N/mm2 b、纵向水平杆强度验算 Mmax=FL1

=2.5*0.4

26

=1KN.m Vmax=F

=2.5KN

σ=M/W=1*106/5.08*103 =196.9N/mm2<205N/mm2=f wmax=FL1(3L2-4L12)/24EI

=2.5*1000*400*(3*12002-4*4002)/(24*2.06*105*12.19*104) =6mm<1200/150=8mm(满足要求) C、横向水平杆验算

F=2.5KN

1200 1200 A′ A B

(b)

Mmax=0.188FL

=0.188*2.5*1.2 =0.9KN.m Vmax=0.688F =0.688F =1.72KN

σ=M/W=0.9*106/5.08*103

=177.2N/mm2<205N/mm2=f wmax=0.911FL3/100EI

=0.911*2.5*1000*12003/(100*2.06*105*12.19*104) =1.6mm<1200/150=8mm

27

d、支座处扣件抗滑移 Vmax=1.72KN<8KN 均满足要求. ⑶立柱验算

立柱用υ48×3.5钢管,A=489㎜2。立柱承受外楞传递荷载,F=6.4×1.2×1.2=9.2 KN。各立柱间布置双向水平撑上下两道步距1800㎜,并适当布置垂直剪刀撑。 a.强度计算 支柱的受压应力为

σ=F/A=9200/489=18.8/ N/mm2<〔f〕=215N/mm2(可) b.稳定验算

长细比λ=L/i=kμh/I=1.155×1.5×1.8×103/15.8=197 查的ψ=0.186

σ= F /ψA=9200/(0.186×4.89×102)=101

28

第4节 脚手架施工方案 1.脚手架搭设工艺 ⑴、安全通道:由于工程外墙搭设双排脚手架,施工人员进入楼层时,都必须从安全通道,安全通道采用Φ48×3.5钢管,上面用3000×200×50的木跳板进行双层防护,具体搭设如图下图所示: A栏杆 45°≤α≤60°排水沟AA-A剖面图双排脚手架搭设图悬挑脚手架节点构造见下图:

29


安全施工技术方案(新)(6).doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:新东方赵丽老师考研词汇总结

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: