XE105-2000风电机组现场调试方案解析

2019-04-22 21:07

湖南省永州市江华县大路铺风电场(48MW)

风力发电机组调试方案

湘电风能有限公司

2013年6月

2MW风力发电机组现场调试计划书

_ __________________________________________________________________

编 写:审 核: 批 准:

湘电风能 大路铺项目部

2

2MW风力发电机组现场调试计划书

_ __________________________________________________________________

批 准:....................................................................................................................................... 2 1编制目的........................................................................................................................................ 4 2编制依据........................................................................................................................................ 4 3、调试质量目标 ............................................................................................................................. 4 4概述 ............................................................................................................................................... 5 5调试范围........................................................................................................................................ 6

5.1程序控制系统 ..................................................................................................................... 6 5.2偏航系统 ............................................................................................................................. 6 5.3变浆系统 ............................................................................................................................. 6 5.4冷却系统 ............................................................................................................................. 7 6调试前应具备的条件 .................................................................................................................... 7 7调试工作程序 ................................................................................................................................ 8 8调试步骤........................................................................................................................................ 8

8.1外观检查 ............................................................................................................................. 8 8.2 向电路供电 ...................................................................................................................... 9 8.4 检查塔基、机舱电气设备 .......................................................................................... 10 8.6 变频器检测 ...................................................................................................................... 11 9 安全注意事项 ........................................................................................................................... 11

9.1 安全要求 .......................................................................................................................... 12 9.2 个人保护装置 .................................................................................................................. 12 9.3 安全说明 ........................................................................................................................ 13 9.5 轮毂锁安全指导 .............................................................................................................. 14 9.6 设定轮毂锁 ...................................................................................................................... 14 10 人员及设备配置 ....................................................................................................................... 15

10.1 人员配置 ...................................................................................................................... 15 10.2 设备配置 ........................................................................................................................ 16 附表1 调试质量控制点 .............................................................................................................. 17 附表2 风电机组调试记录表 ........................................................................................................ 18

3

2MW风力发电机组现场调试计划书

_ __________________________________________________________________

1编制目的

1.1为了指导、规范风力发电场风电机组设备的调试工作,保证风电场风电机组设备能够安全正常投入运行,制定本措施。

1.2检查偏航、变浆系统电气、信号装置、各柜体工作状态,确认其动作可靠。

1.3检查风电场风电机组设备的运行情况,发现并消除可能存在的缺陷。

2编制依据

1、《XE-105安装手册》 2、《XE-105安全手册》 3、《XE-105操作说明书》 4、《XE-105技术说明书》

3、调试质量目标

执行风力发电场项目建设工程验收规程中有关系统及设备的各项质量标准要求,全部检验项目合格率100%,满足机组整套启动要求。

专业调试人员、专业组长应按附录1(调试质量控制点)对调试

4

2MW风力发电机组现场调试计划书

_ __________________________________________________________________

质量的关键环节进行重点检查、控制,发现问题应及时向上级领导汇报,以便协调解决,保证启动调试工作顺利进行。

4概述

4.1本细则包括XE-105风力发电机组在现场调试的所有项目。

4.2在进行任何工作中,必须时刻考虑最新的标准、规范和规则以及 风力发电发展水平。如果存在若干标准、规范和规则适用于同一条款,则工作中必须遵循最严格的标准执行。

4.3如果有几何图,则认可的图纸优先于尺寸说明。 主要设备技术参数: 风电机组型号:XE-105

发电机型号:TFYD2000-3NT 2180KW 690V 容量:2MW 频率:8.5Hz

转速:17r/min(额定) 切入风速:3m/s 切出风速:22m/s 生产厂家:湘潭电机厂 偏航系统:湘电风能 执行机构:电动 变浆系统:湘电风能 控制系统:湘电风能

5


XE105-2000风电机组现场调试方案解析.doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:练习题

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: