湖北中南路桥有限责任公司
项目经理部 湖北省保宜高速公路一期土建工程BYYCTJ-03合同段
系统锚杆加固施工
方案
编制: 审核: 审批:
二零一一年
— I —
湖北省保宜高速公路一期土建工程BYYCTJ-03合同段
湖北保宜高速公路宜昌段BYYCTJ-3合同段 系统锚杆框架施工方案 目 录
一、编制依据与原则 ·························································································································· 3 1、相关标准、规范和施工图 ····································································································3 2、编制原则 ································································································································3 二、工程概况 ······································································································································ 3 1、概况 ········································································································································3 2、地质和气侯条件 ····················································································································4 3、工程特点 ································································································································4 4、施工要求和技术保证条件 ····································································································4 三、施工组织机构与施工计划 ········································································································· 5 1、施工组织机构 ························································································································5 2、进度计划 ································································································································5 3、劳动力计划 ····························································································································6 4、机械配置计划 ························································································································6 四、系统锚杆防护施工工艺 ············································································································· 7 1、施工顺序 ································································································································7 2、施工场地布置 ························································································································7 3、材料准备 ································································································································7 4、施工方法 ································································································································8 (1) 锚杆框格梁施工 ············································································································8 (2)浆砌片石施工 ····················································································································8 5、工艺流程和工艺控制 ············································································································9 (1)锚杆框格梁施工工艺流程 ································································································9 (2)锚杆框格梁施工工艺 ········································································································9 (3)系统锚杆注意事项 ··········································································································17 (4)浆砌片石护坡砌筑注意事项 ··························································································17 6、工序检查和验收 ··················································································································17 (1)工序检查 ··························································································································17 (2)锚杆框格梁验收 ··············································································································18 (3)锚杆抗拔力试验 ··············································································································19 (4)浆砌片石拱型护坡验收 ··································································································19 (5)高边坡监测 ······················································································································19 五、安全保证措施及应急预案 ······································································································· 22 1、组织保障 ······························································································································22 2、安全保证管理措施 ··············································································································22 3、安全生产技术措施 ··············································································································23 (1)在施工中存在的危险源 ··································································································23 (2)施工现场设置 ··················································································································23 (3)地质情况复查 ··················································································································24 (4)机械电器的使用 ··············································································································24 (5)清理边坡 ··························································································································24
— I —
湖北保宜高速公路宜昌段BYYCTJ-3合同段 系统锚杆框架施工方案 (6)锚杆钻孔作业 ··················································································································25 (7)锚杆施工 ··························································································································25 (8)注浆施工 ··························································································································25 (9)框格梁施工 ······················································································································26 (10)拱型浆砌片石护坡 ········································································································26 (11)坠落落物防护措施 ········································································································26 (12)锚杆施工平台搭设安全措施 ························································································27 4、施工安全检查和监测 ··········································································································27 (1)严格执行安全检查制度 ··································································································27 (2)安全监测 ··························································································································27 (3)边坡外部变形监测 ··········································································································28 (4)表面裂缝监测 ··················································································································28 (5)支护效应监测 ··················································································································28 (6)边坡渗流监测 ··················································································································28 (7)安全监测成果的整理、反馈 ··························································································28 (8)坡体截排水 ······················································································································28 5、安全应急预案 ······················································································································29 (1)现场应急自救组组织机构 ······························································································29 (2) 应急自救领导小组人员分工 ························································································29 (3)应急管理原则 ··················································································································31 (4)事故特征及现场应急处置措施 ······················································································31 1)机械伤害事故应急处置方案 ·························································································31 2)高处坠落事故特征及应急处置措施 ·············································································32 3)坍塌滑坡事故特征及应急处置方案 ·············································································34 4)触电伤害事故特征及应急处置方案 ·············································································35 5)落物伤害事故及应急处置方案 ·····················································································38 6)应急处理物资 ·················································································································39 7)应急救治外援机构 ·········································································································39 6、安全培训和安全交底 ··········································································································39 (1)特殊技术工人技术培训 ··································································································39 (2)岗前安全教育 ··················································································································39 (3)安全和技术交底 ··············································································································39 六、环保水保措施 ···························································································································· 40 1、环保水保机构和保证体系 ··································································································40 2、环保水保管理措施 ··············································································································40 3、环保水保技术措施 ··············································································································40 (1)生态环境保护 ··················································································································40 (2)防止噪音污染和光污染 ··································································································41 (3)固体废物处理 ··················································································································41 (4)水保措施 ··························································································································42 七、文明施工 ···································································································································· 43 1、文明施工管理措施 ··············································································································43 2、文明施工技术措施 ··············································································································44
— II —
系统锚杆加固施工方案
一、编制依据与原则 1、相关标准、规范和施工图
(1)招标文件、两阶段施工图设计、实施性施工组织设计; (2)施工调查及现场勘察资料;
(3)《公路工程质量检验评定标准》(JTG F80/1-2004); (4)施工现场临时用电安全规范(JGJ462005); (5)《公路工程施工安全技术规程》(JTJ076—95);
(6)《湖北省高速公路建设标准化指导意见(安全生产管理)》 ; (7)《建筑施工高处作业安全技术规范》 ;
(8)法律、法规对质量、水土保持、环境保护、安全管理的规定; (9)我单位从事类似工程的施工经验及资源情况。 2、编制原则
(1)严格遵守招标文件明确的设计规范,施工规范和质量评定验收标准。 (2)坚持技术先进性,科学合理性,经济适用性,安全可靠性与实事求是相结合。 (3)对施工现场坚持全员、全方位、全过程严密监控,动态控制,科学管理的原则。
二、工程概况 1、概况
本标段为湖北保宜高速公路宜昌段BYYCTJ-3合同段,本合同段路线起点(K95+800)位于远安镇金家冲,与第2合同段的终点相接。终点设在花林寺镇高楼村,桩号为K109+281.698,路线全长13.481Km。
本标段高边坡共有系统锚杆框架6处。 具体如下表:
系统锚杆加固一览表 序号 1 2 3 4 5 6 名称 庙心冲深路堑 龙家冲1号深路堑 起讫桩号 K101+601~K101+637 K105+213~K105+240 K105+213~K105+231 K105+837~K105+909 K105+882~K105+909 K107+693~K107+765 长度(m) 27 27 18 72 27 72 坡率 1:1 1:1 1:1 1:1 1:1 1:1 坡高 8 8 8 8 8 8 单根锚杆长度(m) 8 8 8 8 8 8 位置 右侧三级 右侧二级 右侧三级 右侧二级 右侧三级 右侧四级 — 3 —
龙家冲2号深路堑 肖家塘深路堑