天然气输气管线工程施工方案(长输管线)

2019-05-24 16:44

xx-xx天然气输气管线工程

施工方案

编制:

审核:

批准:

xx公司 20xx年8月6日

xx输气管线线路6标段 施工方案

目 录

1.工程概况................................................................................................................................................. 2 2.编制依据................................................................................................................................................. 2 3.施工工期计划 ......................................................................................................................................... 3 4.人员配备................................................................................................................................................. 4 5.施工方法................................................................................................................................................. 5

5.1一般地段管道施工方法 ............................................................................................................... 5 5.2水田段管线施工方法 ................................................................................................................. 32 5.3小型河流沟渠施工方法 ............................................................................................................. 20 5.4鱼塘穿越施工方法 ..................................................................................................................... 22 5.5人口密集地段管道施工方法 ..................................................................................................... 25 5.6陡峭地形管线施工方法 ............................................................................................................. 30 5.7高压线附近施工方法 ................................................................................................................. 33 5.8公路大开挖穿越方法 ................................................................................................................. 38 5.9公路、铁路顶管穿越方法 ......................................................................................................... 41 5.10弯管弯制方法 ........................................................................................................................... 48 5.11穿越地下管道、光(电)缆施工方法 ................................................................................... 50 5.12管道补口、补伤施工方法 ....................................................................................................... 53 5.13阴极保护施工方法 ................................................................................................................... 55 5.14石方段爆破施工方法 ............................................................................................................... 57 5.15清管、测径、试压方法 ........................................................................................................... 64 5.16阀室土建、工艺施工方法 ....................................................................................................... 76 5.17水工保护施工方法 ................................................................................................................... 88 5.18雨季施工措施 ........................................................................................................................... 90 5.19防腐管安全及防腐层保护措施 ............................................................................................... 91 5.20管线下沟施工技术措施 ........................................................................................................... 93 6.项目质量、职业健康安全与环境(QHSE)管理 ............................................................................... 95

6.1项目QHSE方针……………………………………………………………………………….93 6.2项目QHSE目标……………………………………………………………………………….93 6.3项目组织机构………………………………………………………………………………….93 6.4质量责任……………………………………………………………………………………… 94 6.8质量检测及控制程序………………………………………………………………………….97 6.7质量保证措施 ........................................................................................................................... 103 6.9保护生态环境及农田水利设施措施 ....................................................................................... 108 6.10管道焊接一次合格率保证措施 ............................................................................................. 112 6.11台风预案 ................................................................................................................................. 115 6.12水土保持措施 ......................................................................................................................... 116

xx公司

- 1 -

xx输气管线线路6标段 施工方案 1. 工程概况

工程名称:xx省天然气管网xx~xx输气管线线路第八标段

建设规模:本工程为xx~xx输气管线线路第八标段:工程内容主要包括线路工程48.1Km以及xx分输站及配套工程。工程线路共分为两段。第一段:xx~xx,第二段:xx~xx湖湖口。

第一段xx~xx起点为xx市xx首站,终点为xx分输站。管线全长48.1km,管径采用?508mm,管线途径区域基本为丘陵、低山地貌,全线村庄比较密集,与本工程交叉的的道路(铁路、高速公路、高等级公路)较多,全线主要依托国道108和xx~济南的双瑞线。

第二段xx~xx起点为xx市xx首站,截止到xxxx向钻穿越前,管线全长15.1km,管线采用?508mm,管线途径区域以平原地貌和丘陵地貌为主,在xx湖湖口的东面有2.5km的山区;全线主要依托xx高速和306省道。管线设计压力为6.3MPa,壁厚为8.0mm,主管线钢材为L415 ;本工程所用冷弯和热煨弯管采用直缝埋弧焊钢管进行制作。线路管道焊接采用手工下向焊工艺,穿越段焊接、线路连头和返修采用手工下向焊工艺。线路补口采用辐射交联聚乙烯三层结构热收缩套(带)现场补口。 2. 编制依据

1) 甲乙双方签订的施工合同及招投标文件

2) 胜利油田胜利工程设计咨询有限责任公司设计的施工图纸及文件资料 3) 《输油输气管道线路工程施工及验收规范》(SY0401-98) 4) 《钢质管道焊接及验收》SY/T4103-96

5) 《石油天然气管道穿跨越工程施工及验收规范》(SY0470-2000)

6) 《关于处理石油管道和天然气管道与公路相互关系的若干规定》(试行)((78)

交公路字698号,(78)油化管道字452号)

7) 《石油、天然气管道与铁路相互关系的若干规定》(1978.10.1) 8) 《石油天然气工业输送钢管交货技术条件第一部分:A级钢管》

(GB9711.1-1997)

9) 《管道下向焊接技术规程》(Q/CNPC78-2002)

10) 《石油天然气钢质管道对接焊缝射线照相及技术分级》(SY4056-1993)

xx公司

- 2 -

xx输气管线线路6标段 施工方案

11) 《石油天然气钢质管道对接焊缝超声波探伤及质量分级》(SY4065-1993)

12) 《油气输送钢制弯管》(SY/T5257-2004)

13) 《输油输气管道线路工程施工技术规范》(Q/CNPC59-2001) 14) 《管道干线标记设置技术规定》(SY/T6064-94)

15) 《原油和天然气输送管道穿跨越工程设计规范穿越工程》(SY/T0015.1-1998) 16) 《长输管道阴极保护工程施工及验收规范》 17) 《涂装前钢材表面处理规范》(SY/T0407-1997)

18) 《钢质管道熔结环氧粉末外防腐层技术标准》(SY/T0315-1997) 19) 《现场设备、工业管道焊接工程施工及验收规范》(GB50236-98) 20) 《钢质管道焊接及验收》(SY/T4103-1995)

21) 《工业金属管道工程施工及验收规范》(GB50235-97)

22) 《石油天然气气站内工艺管道工程施工及验收规范》(SY0402-2000) 23) 《机械设备安装工程施工及验收通用规范》(GB50231-98) 24) 《油气田地面管线和设备涂色标准》(SY0043-96) 25) 《建筑地基基础工程施工质量验收》规范(GB50202-2002) 26) 《混凝土结构工程施工质量验收规范》(GB50209-2002) 27) 《工业自动化仪表工程施工及验收规范》(GB50093-2002) 28) xx公司企业标准 3. 施工工期计划

时间2 3 4 5 6 (天) 1 工序 计划 测量放线 设备搬迁 材料运输 主体焊接 试压 防腐补口 管沟开挖 xx公司

- 3 -

xx输气管线线路6标段 施工方案

时间2 3 4 5 6 (天) 1 工序 计划 管道下沟 压载 管沟回填 地貌恢复 清理现场

4. 人员配备 序 号 1 2 3 4 5 6 7 8 9 10 11 12 工 种 项目经理 现场经理 项目副经理 项目总工 施工经理 安全员 质量员 技术员 材料员 机组长 测量员 协调员 人数 1人 1人 1人 1人 1人 1人 1人 8人 2人 4人 4人 4人 19 20 21 22 23 机械手 修理工 电 工 司 机 普 工 8人 1人 2人 4人 20人 14 15 16 17 18 管 工 电焊工 气焊工 防腐工 炊事员 4人 20人 1人 2人 1人 序号 13 工 种 起重工 人数 2人 xx公司

- 4 -


天然气输气管线工程施工方案(长输管线).doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:图解钢结构各个构件和做法(DOC)

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: