Waiting times per processing group have to be controlled. Input/output reports have an important function: to compare the realized output for a production unit against its planned output.每个处理组的等待时间得到控制。输入/输出报告有一个重要的功能:比较一个产品实际输出和其计划产量。
Difference between MRP-I and MRP-II
MRP-I和MRP-II的区别
MRP-I stands for materials requirements planning; aims at releasing and managing manufacturing orders and purchasing requisitions. MRP-I 代表了物料需求计划,旨在释放和管理生产订单和采购需求。
MRP-II stands for manufacturing resources planning, an integrated system that controls relevant materials flows and production capacity while also taking into account the relationship between these materials flows and the required capacity.MRP-II代表了生产资源计划,一个整合的系统,在考虑这些物料流和所需的容量的同时控制着相关的物料流和生产容量。
Characteristics of JIT management:JIT管理的特点
All materials and products become available at the very moment when they are needed in the production process, not sooner and not later but exactly on time and exactly in the right quantity. 所有的材料和产品将在生产过程中当他们被需要时的那刻提供,不早不晚,在确切时间和以正确的数量提供。
Major objective主要目标
Continuously tackle and solve manufacturing bottlenecks within, and interfaces between, consecutive steps in the manufacturing process.
连续地处理和解决生产瓶颈和在制造过程中的连续i两步骤之间的接口。
Elements of the purchasing information system采购信息系统的要素
Most important elements of a purchasing system:
Requisitioning and ordering申购和订购
Product, supplier and contract database产品,供应商和合同数据库
Order follow up 跟进的订单
Delivery 送货
Invoice handling and payment发票处理和支付
Some typical problem situations between purchasing and
logistics:采购和物流之间一些典型的问题,
Lack of well defined specifications缺乏良好定义的规范
Lack of standardization缺乏标准
Frequent changes in materials planning物料计划上频繁的改变
Unreliable planning information不可靠的计划信息
Insufficient integration of purchasing in materials management
在物料管理上不充分的采购整合
The co-operation between purchasing, materials planning and logistics should result in an efficient and uninterrupted flow of products.采购,物料计划和物流之间的合作应导致产品的