xx制梁场10t-24m龙门吊安装及拆除方案

目 录

1 概述 ............................................................................................................................................................. 1 1.1 编制依据 ................................................................................................................................................. 1 1.2 编制目的 ................................................................................................................................................. 1 1.3工程概况 .................................................................................................................................................. 1 2 施工总体部署 ............................................................................................................................................. 2 2.1施工组织机构 .......................................................................................................................................... 2 2.2施工机械安排 .......................................................................................................................................... 3 2.3工期安排 .................................................................................................................................................. 4 2.4安全目标 .................................................................................................................................................. 4 2.5龙门吊布置平面图 .................................................................................................................................. 4 3 龙门吊安装施工方案 ................................................................................................................................. 5 3.1 龙门吊基础施工 ..................................................................................................................................... 5 3.2 地锚的布置及缆绳检算 ......................................................................................................................... 6 3.3 龙门吊运行轨道安装 ............................................................................................................................. 7 3.4龙门吊安装 .............................................................................................................................................. 8 4龙门吊拆除 ................................................................................................................................................ 12 4.1拆除前的准备工作 ................................................................................................................................ 12 4.2龙门吊拆除 ............................................................................................................................................ 12 5 质量保证措施 ........................................................................................................................................... 12 5.1龙门吊工程检验、验收标准 ................................................................................................................ 12 5.2质量保证措施 ........................................................................................................................................ 13 6 安全保证措施 ........................................................................................................................................... 14 7应急救援预案 ............................................................................................................................................ 17 7.1触电事故应急预案 ................................................................................................................................ 18 7.2高处坠落事故应急预案 ........................................................................................................................ 20 7.3大型机械设备倒塌应急预案 ................................................................................................................ 22 8环境保护措施 ............................................................................................................................................ 24 9结构计算书 ................................................................................................................................................ 24

中铁七局集团宁西铁路项目部

xx制梁场10t-24m龙门吊安装及拆除方案

潢川制梁场10t-24m龙门吊安装及拆除方案

1 概述 1.1 编制依据

(1)、《起重机设计规范》GB3811-2008

(2)、《起重设备安装工程施工及验收规范》GB50278-2010 (3)、《通用桥式起重机可靠性评定试验规范》JB/T50103-1998 (4)、《桥式和门式起重机制造及轨道公差》GB10183-2005 (5)、《起重机安全规程》GB6067-2010

(6)、《铁路桥涵工程施工安全技术规程》TB10303.2-2009 (7)、《铁路桥涵设计通用规范》TB 10002.1-2005 1.2 编制目的

xx梁场后张法预应力T梁生产区为四条生产线,为了方便拆装模板和吊运钢筋网片及混凝土浇筑的使用,需配备起重设备10T-24m门吊两台。为了保证施工期间龙门吊施工的安全、质量,合理的安排施工工期,编制龙门吊安装及拆除方案。 1.3工程概况

根据承建合同,本梁场需预制后张法简支砼T梁1396片,共690孔(单线)和4孔(双线),梁型为通桥(2005)2101型T梁,其中32mT梁496孔(单线)和1孔(双线),24mT梁130孔(单线)和3孔(双线), 16mT梁64孔。本梁场预制的各种类型桥梁数量见下表:

表1:工程量清单

序号 1 2 3 4 桥梁类型 32m后张梁 24m后张梁 16m后张梁 总 计 工程数量 单位砼数量 合计砼数量 图号 (单线孔/(m3) (m3) 双线孔) 通桥(2005)2101-I 496/1 106.68/206.7 53120.02 通桥(2005)2101-II 通桥(2005)2101-IV 130/3 75.34/145.78 10231.54 64/0 47.66 3050.24 690/4 66402 1

xx制梁场10t-24m龙门吊安装及拆除方案

根据梁场规划,制梁场需配置两台10t-24m龙门吊机,采用郑州华中路桥设备有限公司两台MH10-24m A3型门式起重机,龙门吊主要参数如下:

(1)额定起重量:10t (2)跨度:24m (3)起升高度:9m

(4)大车运行速度:0~19m/min (5)起升速度:7m/min (6)电动葫芦速度:20m/min (7)大车基距:7100mm (8)行走轨踏面直径:370mm (9)大车最大轮压50KN (10)工作级别:M3

表2:龙门吊主要构件总重一览表

序号 1 2 3 4 5 6 7 8 9 10 部件名称 数量 主纵梁 3 托架横梁 2 托架支撑 4 支腿 4 支腿拉杆 2 控制室撑杆 2 转向平台 1 行走轮箱 4 10t电动葫芦 1 电缆卷筒 1 合计 单件重(Kg) 2266.67 310 120 1570 250 70 292 590 800 320 总重量(Kg) 6800 620 480 6280 500 140 292 2360 800 320 18592 备注 2 施工总体部署 2.1施工组织机构

为了保证施工期间的安全、质量、进度,成立了xx制梁场龙门吊安装及拆除领导小组

2

xx制梁场10t-24m龙门吊安装及拆除方案

(1)项目部成立特种设备安装及拆除领导小组: 组长:xxx; 副组长:xxx 组员:

安质部长:xxx;工程部长:xxx;物质设备部部长:xxx;质检员:xxx;技术员:xxx;现场管理人员:xxx。

(2)施工人员配置

为了能够保证拼装在工期内,安全、高效优质的完成,现场管理及施工人员配备如下:

表3:施工人员责任分工一览表

职务 施工总指挥 安全负责人 技术负责人 测量员 电工 起重工 辅助人员 人数 1名 1名 1名 1名 1名 3名 3名 责任分工 指导全面工作 指导监督施工安全 设备拼装的技术指导 对关键尺寸的测量复核 电气机构的安装调试 起重的指挥及操作 除辅助人员外,以上其余人员应持证上岗,严禁无证人员随意操作。 2.2施工机械安排

表4:主要施工设备和检测仪器

序号 1 2 3 4 5 机具名称 汽车吊 钢丝绳 标准绳夹 麻绳 卸扣(卡环) 规格型号 YQ25E φ36.5 26 φ22 许用载荷20t 单位 辆 m 个 m 个 数量 2 20 20 60 4 备注 用于抬吊门吊 吊装 钢丝绳卡接 溜绳 3

xx制梁场10t-24m龙门吊安装及拆除方案

6 7 8 9 10 11 12 13 14 卸扣(卡环) 卷尺 卷尺 钢直尺 塞尺 水准仪 电工套件 指挥旗 安全带 许用载荷5t 5m 50m 1m 100mm DS3 个 把 把 把 把 台 套 个 副 4 2 1 1 1 1 2 1 4 或口哨 2.3工期安排

龙门吊计划安装时间3天,调试时间2天,2012年11月18日前完成龙门吊的安装及调试,夜间严禁施工,所有安装拆除作业均安排在白天。 2.4安全目标

坚持“安全第一,预防为主”的方针。职工伤亡事故:死亡率控制在0,重伤率控制在0,安全生产达国标。 2.5龙门吊布置平面图 图1:10t-24m龙门吊布置平面图 龙门吊龙门吊 4