监理实施细则
(石材幕墙工程)
编制人: 审核人:
编制单位:奉化市凯远工程咨询有限公司 编制时间:2010年5月20日
目 录
一、工程概况 ················································································································ 2 二、监理细则依据 ········································································································ 2 三、幕墙工程施工质量保证条件 ················································································ 2 四、幕墙工程监理程序 ································································································ 3 五、幕墙材料 ················································································································ 4
1. 2. 3. 4.
钢材 ·············································································································· 4 石材 ·············································································································· 4 建筑密封材料 ······························································································ 5 其他材料 ······································································································ 7
六、幕墙设计和施工阶段监理要点 ············································································ 7 七、幕墙工程的制作与安装 ························································································ 8
1. 2. 3. 4. 5.
“施工组织设计”的审查要点 ·································································· 8 审查、确认进场材料 ·················································································· 8 幕墙材料制作加工 ······················································································ 9 幕墙工程的安装施工 ················································································ 11 幕墙的性能试验 ························································································ 12
八、幕墙工程验收 ······································································································ 13
1. 2.
工程现场验收 ···························································································· 13 工程提交资料验收 ···················································································· 15
一、工程概况
本工程位于 。总建筑面积172324.64m2,由 组成。其中 。均为钢筋混凝土剪力墙结构。外墙装饰大部分采用外挂石材幕墙。根据本工程特点外立面设计装饰效果要求较复杂,施工有一定难度,所以幕墙子分部工程由 幕墙有限公司分包。计划工期 天。
二、监理细则依据
本细则根据以下有关规范、标准制定:
1、 建筑装饰装修工程质量验收规范 (GB50210—2001) 2、 金属与石材幕墙工程技术规范 (JGJ133—2001) 3、 建筑用硅酮结构密封胶 (GB16776) 4、 建筑幕墙物理性能分级 (GB/T15225) 5、 建筑幕墙风压变形检测方法 (GB/T15227) 6、 建筑幕墙雨水渗漏性能检测方法 (GB/T15228) 7、 建筑幕墙空气渗透性能检测方法 (GB/T15226) 8、 铝合金建筑型钢 (GB/T 5237.2—5237.5) 9、 天然石材产品放射性防护分类标准 10、 其他有关国家标准。
三、幕墙工程施工质量保证条件
1、幕墙设计必须由相应资质的设计单位承担。设计应严格执行国家相关规范。 2、幕墙工程所用材料:钢材及不锈钢、石材、粘结密封胶等均须有出厂合格证,并符合国家和行业标准。
3、加工制作所使用的材料和配件、加工质量等均应符合国家和行业标准、技术规程。
4、幕墙施工必须由相应资质的施工单位进行施工安装,安装工艺及质量应符合国家现行标准。幕墙工程的设计、材料、制作和安装施工及验收应符合《金属与石材幕墙工程技术规范》合同签订;图纸会审;质量保证体系和控制体系落实;审阅施工进度计划和施工方案;新工艺、新材料、新技术进行格;第一次工地会议召开 试验合格;工地环境、开工条件检查合JGJ133—2001、《建筑装饰装修工程质量验收规范》GB50210—2001的要求。四、幕墙 工程监理程序
开工前准备工作 施工单位填报 《开工报告》 整改 监理处审核 不同意 工序返工整改处、理原材料限期退场前期开工条件 同意 材料报验、 下道工序 工序施工、工序报验 施工单位填报《材料报验单》《工 不合格 序报验单》附,材料出厂合格证、铝型材、石材、金属材料试验报告、结构胶与接触材料相容性、粘结力试验报告、夹胶玻璃的试验报告等,工序自检记录,检查 合格 试验结果等 监理工程师签认 《材料报验单》 《工序报验单》 施工单位提交 《竣工报告》 竣工图、 技术管理等资料
工程质量初验
工程交工验收 五、幕墙材料
1. 钢材
①幕墙工程所使用的不锈钢宜采用奥氏体不锈钢材,型材材质应符合相应的现行国家标准:不锈钢棒(GB1200)、不锈钢冷轧钢板(GB3280)、不锈钢热轧钢板(GB4237)。
②普通钢筋HPB235是应用最多的钢材,使用时应对其试验报告中的化学成份, 力学性能等重点审查。
③幕墙工程中使用的钢材、五金件应有出厂合格证、试验报告,热镀锌涂层必须合格。
④钢结构幕墙高度超过40M时,钢构件宜采用高耐候结构钢,并应在其表面涂刷防腐涂料。
⑤钢构件采用冷弯薄壁型钢时,其壁厚不得小于3.5mm,强度应符合设计计算要求,表面应进行处理。 2. 石材
① 幕墙石材宜选用火成岩。
② 石材的弯曲强度不应小于8.0MPa,吸水率应小于0.8%。
③ 石材幕墙的铝合金挂件厚度不应小于4.0mm,不锈钢挂件厚度不应小于3.0mm。
④ 火烧石板与抛光石板若要求同强度时,火烧石板的厚度应比抛光石板厚3mm。
⑤ 石材的强度,弯曲强度、耐磨性、耐酸性、体积密度、吸水率等主要性能试