目 录
第一章 编制说明 ······························································································ 5 1.1 编制内容及范围 ........................................................................................... 5 1.2 编制依据 ....................................................................................................... 5 1.2 编制原则 ....................................................................................................... 7 第二章 工程概况 ······························································································ 7 2.1 工程概况 ....................................................................................................... 7 2.2 施工条件 ..................................................................................................... 10 2.3 气象条件 ..................................................................................................... 11 2.4 工程重点、难点及施工关键 ..................................................................... 11 第三章 施工总体部署 ···················································································· 12 3.2施工区段划分 ............................................................................................. 13 3.3分包部署...................................................................................................... 13 3.4总体工期安排及关键工期控制点 ............................................................. 13 3.5施工工序计划 ............................................................................................. 14 第四章 施工准备 ···························································································· 14 4.1项目组织机构 ............................................................................................. 14 4.2项目项目经理部组成人员一览表 ............................................................. 15 4.3项目管理职责分工 ..................................................................................... 16 4.4劳动力安排及计划表 ................................................................................. 18 4.5劳务队伍分包 ............................................................................................. 19 4.5技术准备...................................................................................................... 20 4.6施工现场准备 ............................................................................................. 21
1
4.7机械设备计划 ............................................................................................. 23 4.8主要材料计划 ............................................................................................. 25 第五章 施工进度计划 ···················································································· 27 5.1进度计划表.................................................................................................. 27 5.2进度计划网络图 ......................................................................................... 28 第六章 施工总平面布置 ················································································ 28 6.2临时用水布置 ............................................................................................. 30 6.3临时用电布置 ............................................................................................. 32 6.4施工现场平面布置图 ................................................................................. 33 第七章 施工方案和项目经理部组成人员 ···················································· 34 7.1施工测量...................................................................................................... 34 7.2土方工程...................................................................................................... 39 7.3防水工程...................................................................................................... 42 7.4结构工程...................................................................................................... 45 7.5屋面工程...................................................................................................... 75 7.6 门窗工程 ..................................................................................................... 80 7.7楼地面工程.................................................................................................. 90 7.8装饰工程...................................................................................................... 97 7.9脚手架工程................................................................................................ 141 7.10安装工程.................................................................................................. 147 7.11重点、难点工程质量控制 ..................................................................... 176 第八章 保证工程质量的技术组织措施 ······················································ 182 8.1质量目标.................................................................................................... 182
2
8.2质量保证体系 ........................................................................................... 182 8.3保证质量的组织措施 ............................................................................... 183 8.4保证质量的技术措施 ............................................................................... 185 第九章 安全生产的技术组织措施 ······························································ 208 9.1 安全生产目标与保证体系 ....................................................................... 208 9.2安全施工组织措施 ................................................................................... 208 9.3安全生产技术措施 ................................................................................... 213 第十章 文明施工的技术组织措施及环境保护措施 ·································· 222 10.1文明施工、环保目标及保证体系 ......................................................... 223 10.2文明施工组织措施 ................................................................................. 223 10.3文明施工技术措施 ................................................................................. 226 10.4环境保护技术措施 ................................................................................. 232 第十一章 保证工期的技术组织措施 ·························································· 234 11.1工期目标.................................................................................................. 234 11.2施工进度计划 ......................................................................................... 234 11.3确保工期的组织措施 ............................................................................. 234 11.4确保工期的技术措施 ............................................................................. 238 第十二章 新技术、新产品、新工艺、新材料应用 ·································· 244 12.1四新技术应用项目 ................................................................................. 244 第十三章 施工总承包管理 ············································································ 247 13.1 综述 ......................................................................................................... 247 13.2 施工总承包管理目标及承诺 ................................................................. 247 13.3 总承包管理体系 ..................................................................................... 248
3
附图:
附图1主体阶段施工现场平面布置图; 附图2装修阶段施工现场平面布置图; 附图3施工进度计划横道图;
4
第一章 编制说明
1.1 编制内容及范围
本施工组织设计只供本工程使用。
内容包括招标文件及施工图范围内的土建、电气、给排水、暖卫等专业工程。
1.2 编制依据 1、招标文件
2、聚能商贸城施工图纸及答疑文件 3、现场自然条件
4、我公司质量、环境、职业健康安全管理体系文件 5、有关现行施工质量验收规范、规程及标准 (1)《工程测量规范》GB50026-93
(2)《建筑地基基础工程施工质量验收规范》GB50202-2002 (3)《建筑地基处理技术规范》GBJ79-91 (4)《地下工程防水技术规范》GB50108-2002 (5)《混凝土结构工程施工及验收规范》GB50204-2002 (6)《钢筋混凝土用热轧带肋钢筋》GB1499-98 (7)《硅酸盐水泥、普通硅酸盐水泥》GB175-1999 (8)《屋面工程质量验收规范》GB50207-2002 (9)《建筑地面工程质量验收规范》GB50209-2002 (10)《砌体工程质量验收规范》GB50203-2002 (11)《建筑工程施工质量验收统一标准》GB50300-2001
5