中国第一冶金建设有限责任 公司 THE CHINA FIRST METALLURGICAL CONSTRUCTION COMPANY LTD.
邯钢7#高炉主体设备08年大修工程 邯钢7#高炉主体设备08年大修工程施工组织设计
目 录
第一章 综合说明 ......................................................................................................................................... 1 1.1编制依据 .............................................................................................................................................. 1 1.2目标 ...................................................................................................................................................... 1 1.3工程概况 .............................................................................................................................................. 2 第二章 施工进度计划及平面布置 ............................................................................................................. 5 2.1施工总进度计划 .................................................................................................................................. 5 2.2施工平面布置 ...................................................................................................................................... 5 2.3现场管理规定 ...................................................................................................................................... 5 第三章 主要施工方法 ................................................................................................................................. 6 3.1施工部署 .............................................................................................................................................. 6
3.1.2施工准备阶段 ...................................................................................................................... 6 3.1.3加固阶段 .............................................................................................................................. 7 3.1.4拆除阶段 .............................................................................................................................. 7 3.1.5炉壳及冷却壁安装阶段 ...................................................................................................... 8 3.1.6耐材砌筑阶段 ...................................................................................................................... 8 3.1.7交工、服务阶段 .................................................................................................................. 9 3.2拆除施工 ............................................................................................................................................ 10
3.2.1高炉本体拆除施工 ............................................................................................................ 10 3.3高炉炉壳制作、预装、检验、运输 ................................................................................................ 11
3.3.1材料的检验 ........................................................................................................................ 11 3.3.2钢结构图纸深化设计 ........................................................................................................ 11 3.3.3高炉炉壳制作 .................................................................................................................... 12 3.3.4高炉炉壳预装 .................................................................................................................... 13 3.3.5高炉炉壳的验收要求 ........................................................................................................ 14 3.3.6零件加工的工艺要求 ........................................................................................................ 15 3.3.7焊接检验 ............................................................................................................................ 16 3.3.8涂装和运输加固措施 ........................................................................................................ 17 3.4高炉系统结构安装 ............................................................................................................................ 17
3.4.1高炉炉壳的预拼装 ............................................................................................................ 17 3.4.2高炉炉壳及冷却壁安的安装 ............................................................................................ 18 3.4.3冷却壁安装要点 ................................................................................................................ 19 3.4.4钢结构的涂装 .................................................................................................................... 24 3.5工艺管道施工 .................................................................................................................................... 26
3.5.1工序流程 ............................................................................................................................ 26 3.5.2管道安装要求及方法 ........................................................................................................ 27 3.5.3阀门安装 ............................................................................................................................ 27 3.5.4补偿器安装 ........................................................................................................................ 27 3.5.5支、吊架安装 .................................................................................................................... 28 3.5.6管道焊接 ............................................................................................................................ 28
---------------------------------------------------------------------------施工组织设计 - 1 -
中国第一冶金建设有限责任 公司 THE CHINA FIRST METALLURGICAL CONSTRUCTION COMPANY LTD.
邯钢7#高炉主体设备08年大修工程 3.5.7管道试验 ............................................................................................................................ 28 3.5.8管道冲洗、吹扫 ................................................................................................................ 29 3.5.9防腐 .................................................................................................................................... 29 3.5.10绝热 .................................................................................................................................. 30 3.6高炉炉顶主要设备安装方案 ............................................................................................................ 30
3.6.1炉顶设备安装 .................................................................................................................... 30 3.6.2炉顶设备调试 .................................................................................................................... 31 3.6.3安全及施工技术措施 ........................................................................................................ 32 3.7高炉系统耐材砌筑方案 .................................................................................................................... 32 第四章 工程投入的主要物资和施工机械设备情况 ............................................................................... 33 4.1高炉结构安装施工方案用料计划 .................................................................................................... 33 4.2拟投入的主要施工机械设备 ............................................................................................................ 36 第五章 劳动力安排计划及劳务分包情况表 ........................................................................................... 37 5.1施工人员安排计划原则 .................................................................................................................... 37 5.2劳动力计划表 .................................................................................................................................... 37
---------------------------------------------------------------------------施工组织设计 - 2 -
中国第一冶金建设有限责任 公司 THE CHINA FIRST METALLURGICAL CONSTRUCTION COMPANY LTD.
邯钢7#高炉主体设备08年大修工程
第一章 综合说明
1.1编制依据
1)《邯钢7#高炉主体设备08年大修工程》招标文件及图纸;
2)按GB/T19001-2000idtISO9001:2000、GB/T24001-1996idtISO14001:1996、GB/T28001-1996idtOHSAS18001:2001标准制定的《质量、环境、职业健康安全管理手册》和《质量、环境、职业健康安全程序文件》,以及公司颁布实施的有关企业标准和操作规程;
3)业主对质量、安全、文明施工的有关规定; 4)建设部颁布的《建设工程施工现场管理规定》; 5)国家现行安全生产法规;
6)国家及行业颁发的现行施工质量验收规范、工程质量检验评定标准; 1.2目标
质量:达到国家建设工程合格标准
工期:含业主烘炉及开炉准备时间80天,我公司施工工期70天。 文明:文明施工工地。 安全:
——人员伤亡事故为0; ——重大机械设备事故为0; ——重大火灾交通事故为0; ——创无事故工程。
---------------------------------------------------------------------------
施工组织设计 - 1 -
中国第一冶金建设有限责任 公司 THE CHINA FIRST METALLURGICAL CONSTRUCTION COMPANY LTD.
邯钢7#高炉主体设备08年大修工程 1.3工程概况
邯钢7#高炉炉缸侵蚀严重,冷却壁水管多数损坏,炉壳多处变形,使用寿命已到极限,定于2008年2月中旬停产大修。
工程主要内容和范围:邯钢7#高炉炉壳制安、炉体炉顶设备拆除安装施工、耐材砌筑、调试等。
(1)炉前部分:
1)炉前鹅颈管拆除、更换、安装10套、法兰更换28套; 2)炉前进风联接管拆除、更换、安装28套; 3)炉前进风吹管拆除、更换 、安装28套; 4)风口大套拆除、更换、安装28套; 5)风口二套拆除、更换、安装28套;
6)两铁口上部冷却水箱、托梁及两侧梁拆除、制作、更换; 7)风口平台加固,混凝土拆除、重新浇注(约200m2); (2)炉体部分:
1)1层至14层冷却壁拆除、更换(5层、6层、7层为铜冷却壁); 2)炉喉钢砖、内侧混凝土拆除、浇注、更换; 3)炉喉钢砖托圈拆除、更换; 4)炉内耐材全部砌筑; 5)炉顶钢圈拆除、更换;
6)炉身炉壳拆除、更换标高3.100至标高31.700; 7)铁口框拆除、更换、安装;
8)炉体梯子、平台面板部分更换; (3)软水系统:
1)炉底软水冷却进水总管拆除、安装、更换;
2)炉底软水冷却水冷管、连接管、阀门拆除、安装、更换; 3)软水炉基供水环管拆除、更换;
4)1-12层冷却壁冷却软水连接管道、阀门拆除、安装、更换; 5)软水回水集管拆除、更换;
6)软水回水集管与回水总管间连接管拆除、更换; (4)工业水系统:
1)炉前高压分水器及阀门拆除、制作、更换四件; 2)风口小套水管拆除、更换;
3)高压分水器与环管间连接管道更换; 4)炉体高压工业水进水阀门、过滤器更换; 5)炉体中压工业水进水阀门、过滤器更换; 6)喷淋支管、围管拆除、更换; 7)炉顶洒水管拆除、更换; 8)风口二套水管拆除、更换;
9)中压分水器与环管间连接管道更换;
10)中压分水器及阀门拆除、制作、更换四件; 11)风口平台排水箱及下部回水管拆除、更换;
---------------------------------------------------------------------------
施工组织设计 - 2 -
中国第一冶金建设有限责任 公司 THE CHINA FIRST METALLURGICAL CONSTRUCTION COMPANY LTD.
邯钢7#高炉主体设备08年大修工程 12)炉基工业水回水围管拆除、更换; 13)喷淋水回水总管拆除、更换; 14)炉体防溅板拆除、制作、安装; 15)炉体排水槽拆除、制作、安装;
16)炉体排水槽间回水管拆除、制作、安装;
16)13层、14层冷却壁给水包及阀门拆除、更换; 17)冷却壁排水箱及排水管拆除、更换;
18)高中压供水管间连接管及阀门拆除、更换; (5)热风炉部分:
1)热风总管波纹补偿器拆除、安装、更换6台;(包括拆除一台热风阀) 2)热风总管、围管上3台放散阀拆除、更换、安装; 3)热风总管内耐火材料拆除、重砌; 4)热风围管内耐火材料拆除、重砌; (6)粗煤气部分:
1)φ1000放散阀拆除、安装、更换一套; 2)φ750放散阀拆除、安装、更换两套;
3)煤气上升管、下降管、煤气导出管上波纹补偿器更换。 (7)炉顶部分:
1)移动受料斗拆除、安装、更换,受料斗内篦子制作、安装、更换,道轨更换; 2)两分岔漏斗拆除、制作、安装、更换; 3)左、右上密阀阀座拆除、安装、更换
4)左、右上密阀操作机构拆除、安装、更换两套; 5)左、右料罐锥部衬板及锥型斗衬板拆除、安装、更换; 6)左、右料罐下部八角溜槽拆除、安装、更换2套; 7)下部漏斗导料板拆除、安装、更换; 8)左、右一均阀拆除、安装、更换; 9)左、右二均阀拆除、安装、更换;
10)左、右均压放散阀拆除、安装、更换; 11)φ500眼睛阀检修;
12)左、右下密阀阀座拆除、安装、更换;
13)左、右下密阀操作机构拆除、安装、更换两套;
14)左、右料流调节阀拆除、安装、更换两套,阀板拆除、安装2套; 15)左、右料流调节阀膨胀节拆除、安装、更换两套; 16)阀箱修理;
17)探尺拆除、安装、一套;新装探尺 一套; 18)气密箱上部膨胀节更换;
19)气密箱上部膨胀节内托斗、抗磨环更换;
20)气密箱拆除、安装、更换;(包括布料流槽、中心喉管、差动减速机 ) 21)布料流槽检修孔整体更换;
22)供气密箱软水进、回水管道拆除、更换,循环泵站检修; 23)十字测温拆除、安装4套; 24)炉喉打水枪更换10套;
25)放散消音器增加一套,放散管路增加一套,制作相应平台支架。现用消音器拆---------------------------------------------------------------------------
施工组织设计 - 3 -