地下室防水等级一级,且需有防海水腐蚀功能,我们采用3mm厚SAR耐盐碱型高聚物改性沥青防水卷材+4mm厚SBS改性沥青防水卷材;
隧道防水等级一级,且需有防海水腐蚀功能,我们采用3mm厚SAR耐盐碱型高聚物改性沥青防水卷材+4mm厚SBS改性沥青防水卷材;
屋顶花园部分防水要求有耐根穿刺:我们采用3mm厚SBS改性沥青+4mm厚SBS改性沥青聚酯胎化学阻根耐根穿刺防水卷材,达到防水一级;
其它屋面采用防水等级二级,我们采用3mm厚SBS改性沥青+3mm厚SBS改性沥青防水卷材。
3、施工准备 Preparations for Commencement
3.1现场准备 Site Preparation
a.按施工现场平面位置图搭建生产和生活临时设施,做好施工用水电的布置,现场安全防护设施的搭建等工作。
Set up the temporary facilities for site production and life as per the site layout. Prepare the water and power, the safety protection facilities for the commencement.
b.组织施工人员进场,并做好各项教育工作,
Organize the work force, move into the site and do well educational work and others. 3.2技术准备 Preparations for execution techniques
及时组织技术人员,预算员认真熟悉施工图纸,参与图纸会审和技术交底。 Timely organize the technicians and quantity surveyors to get familiar with the drawings. They shall participate in the drawings studying and examining, and explain all the technical details.
编制施工图预算和月旬作业计划,提供材料的需求量计划。
Work out the project budget and the schedules for monthly ,and also the materials supply plan.
根据施工图纸,配备与本工程相关的规程,规范及有关图集,并分发给项目经理部相关人员,相关人员根据规范,图集和企业标准,做好各相应的技术交底记录。
The drawing,regulations,code will be delivered to key personnel for keeping a record of technical clarification.
做好各种进场材料的质量检验,合格证等准备工作。
Do a good job in checking all those materials to be brought into the site, certificate and
4
other preparatory work
4、主要施工机具及劳动力资源配置Preparations for Major Construction
equipment and work forces
根据本工程的施工规模及结构形式,为了顺利快速地完成本工程,拟投入的施工机具及劳动力计划表详见附表。
As per the project scale and structural formation, in order to smoothly complete the execution, it is proposed to allocate of the following equipments and labor forces as the form listed below.
4.1劳动力资源配备 Labor Forces
(1)集结精干的施工队伍,组织好劳动力进场,根据机构特点,建设单位工期要求及我公司项目部承诺条件,结合本工程的施工情况,合理组织一支强有力的施工队伍进场。
The most capable construction units shall be selected for mobilization.The selection shall consider the local condition,the construction program and the promises we have made.
(2)落实各级人员的岗位责任制
Hold all-level personnel responsible to their own jobs.
(3)做好劳动力的入场教育培训,搞好全员的各项交底工作。
Make sure the site workers shall receive appropriate trainings and various clarifications be made in due time.
5、项目组织管理机构 The Project Administration Organization
5.1项目管理组织机构的组建The set-up of the Project AdministrationOrganization
为了提高工程质量,加速施工进度及加强施工现场的管理,并能科学地安排施工进度,组织和保证各类物资及时供应,做好各种协调工作,我公司高度重视本工程,委派具有丰富现场管理经验的负责人组建成项目经理部,项目经理部建立岗位责任制,明确分工职责,落实施工责任,各岗位各行其职。
In order to improve the project quality, speed up the project progress, strengthen the site management, scientifically arrange the site production, organize and guarantee timely supple of the various materials and do a good job in coordination work, this company extremely stresses the Project and accredits the company staff with rich site management and
construction experiences to set up the Project Management; establishes the post-responsibility
5
system in the project management so as to enable everyone to do his job well. 5.2项目管理网络 The Network of the Project Management
(1)施工现场项目组织机构网络图The Network of the Project Management and the Site Organization
项目经理Project manager 生产经理Product manager 项目副经理Assistant project manager 施工员Builder质检员Quality inspection技术员Technical leader材料员 安全员Security Material clerkclerk预算员Accounting clerk 资料员File keeper 6、施工工艺流程方案Technical Flow Chart
6.1地下室、隧道施工工艺
本工程地下室、隧道底板、地下室外墙防水为3mm厚SAR耐盐碱型高聚物改性沥青防水卷材+4mm厚SBS改性沥青防水卷材。
地下室底板防水施工 (1)工艺流程
基层清理——验收——涂刷冷底子油——铺贴附加层——平铺卷材(第一层)——热熔封边——验收——交叉平铺卷材(第二层)——热熔封边——验收.
(2) 基层清理
涂刷冷底子油前,前仔细将基层表面的垃圾、尘土等清除干净,必要时可采用喷灯局部喷烤,但喷烤时间不宜过长,防止爆裂、起砂。报监理验收合格后,进行下一道工序。
(3)涂刷基层处理剂
基层含水率不超过9%,(检验含水率简便方法:剪一块200×200 见方的卷材平铺于基层表面,压紧,保持2h,然后揭开卷材观察其下方基层面,如有明显的水珠,则表
6
明含水率过大,不宜施工,如仅有潮气则可满足施工条件)在基层表面满刷一道冷底子油,涂刷要均匀、不透底、遮盖率100%。
(4)铺贴附加层
外墙管根、阴阳角部位加铺一层同质卷材附加层,将卷材裁成相应的形状进行热熔满贴,宽度50cm。附加层施工必须粘贴牢固,施工要细心。项目质检员对此部位专门做隐蔽工程检查。
(5)确定铺贴方向、弹基准线冷底子油涂刷完毕6h 后,手摸感觉不黏即可根据卷材的宽度和搭接的规定,在冷底子油上进行弹线。
按照卷材铺贴的一般原则:弹线由排水较集中的部位开始,遵照由低到高、先平面后立面的顺序弹基准线。针对现场实际,弹线由电梯基坑、集水坑开始;弹线方向为南北方向,同时,根据选用卷材幅宽及长边搭接长度要求,确定弹线间距。
(6)做样板
在大面积铺贴施工前,施工队要按照技术要求及细部做法做100m2 样板,经项目验收合格后,进行大面积施工。
(7)大面积铺贴卷材铺贴方向:南北方向。铺贴顺序:由电梯基坑、集水坑开始,向各方向顺序铺贴。卷材铺帖时要减少阴阳角和大面积的接头,卷材根据墙面尺寸配制,从边沿开始,弹出标准线。
将改性沥青防水卷材按铺贴长度和弹线尺寸裁剪并卷好备用,操作时将已卷好的卷材,用1500mm 长φ30 的管穿入卷心,卷材端头比齐开始铺的起点,按照弹好的线,手扶管心两端向前缓缓滚动向前铺设,使卷材平铺于基层上,要求用力均匀、不窝气,掌握好铺设压边宽度。
然后点燃汽油喷灯,掀开卷材,加热基层与卷材交接处,喷灯与加热面保持300mm 左右的距离,往返喷烤,观察当卷材的沥青刚刚熔化时,压合至边缘挤出沥青粘牢。
对平面与立面相连的卷材,先铺贴平面,然后由下向上满粘,并使卷材紧贴阴、阳角。在永久保护墙上满贴卷材,粘贴牢固,防水卷材甩头上砌两皮砖临时保护。
(8)四周甩槎的卷材贴于保护墙上,保护墙600mm 高度以上不刷基层处理剂,刷脱模剂,卷材上部临时收头用低强度等级砂浆压住,以免坠落,同时起保护作用。
7
(9)卷材施工完毕后,报监理验收,合格后方可进行下道工序。
(10)立面防水卷材施工
地下室结构施工完毕并经验收合格后,开始进行地下室外墙防水施工。外墙防水层施工时,先从外墙0.4m 高度起铺贴第一层卷材,再往上错开500mm 开始铺贴第二层防水。待立面防水施工完,再按照搭接长度、搭接错开要求等铺贴底板甩出卷材至墙面高0.4m 范围的防水卷材。地下室结构施工完毕后,将墙面凹凸不平、错台部位打磨平整,局部平整度较差采取刮水泥腻子找平,阳角犬牙状突起打磨光滑,把墙面浮浆、灰尘等清理干净。
基层处理及检查:将外墙上气泡用水泥腻子刮平,同时将墙面粘连的砂浆、突出物用小铲铲除,使外墙面达到规范规定的防水基层要求(基层要求同底板部分)。
拆除临时保护墙,并将卷材甩槎整理好,对于受损的部位必须先行修理。将冷底子油搅拌均匀后,均匀涂布在干净的基层上,不得漏涂和出现透底现象,干燥6h,手感不黏时方可进行下道工序。
管根、阴阳角等薄弱部位、异形部位加附加层施工。附加层要求同底板部分,管道与卷材连接。然后铺贴外墙立面防水卷材。防水卷材亦采用热熔法施工,其搭接位置、搭接长度及卷材收头等要求同底板卷材防水施工要求。
地下车库顶板外防水,接缝处在平面,距离转角不得小于60cm。
(11)卷材末端收头
接缝处用喷灯热熔卷材缝边缘,待表面熔化后随即用小铁抹子将边缝封好,再用喷灯均匀细致地将边缝烤一遍保证接头密封,以免翘边。收口位置在室外散水下,详见图1。
8