110kV立塔架线施工方案 - 图文

2019-04-21 16:07

鼎美-芸伟110kVⅠⅡ回线路工程 立塔架线施工方案

鼎美-芸伟110kVⅠⅡ回线路工程

立 塔 架

线

施 工 方 案

福建省亿力电力建设有限公司

二O一六年四月

- 1 -

鼎美-芸伟110kVⅠⅡ回线路工程 立塔架线施工方案

批准: 审核: 编写:

年 年 年 - 2 -

月 日

月 日

月 日

鼎美-芸伟110kVⅠⅡ回线路工程 立塔架线施工方案

目 录

一、工程概况: ········································································- 1 - (一)线路有关情况说明 ····························································- 1 - (二)主要交叉跨越 ··································································- 2 - (三)、杆塔明细 ······································································- 4 - (四)、本工程异动 ···································································- 5 - 二、现场人员布置安排如下表: ···················································- 8 - 三、施工工艺流程: ································································ - 10 - (一)、工作准备 ···································································· - 10 - (二)、50t吊车组立钢管杆方案 ················································ - 11 - (三)、导线架设及附件安装 ····················································· - 19 - (四)附件安装 ······································································ - 22 - (五)OPGW光缆架设 ······························································· - 23 - (六)、施工危险点分析及控制措施: ········································· - 25 - (七)、安全事故事件应急预案: ··············································· - 31 - 附表一、杆塔分节重量表 ·························································· - 35 -

- 3 -

鼎美-芸伟110kVⅠⅡ回线路工程 立塔架线施工方案

新垵变T接110kV鼎美~正东ⅠⅡ回线路工程

(立塔架线施工方案)

一、工程概况:

(一)线路有关情况说明

本工程线路起自110kV芸伟变构架,止于已建110kV鼎康Ⅰ回#9塔、110kV鼎康Ⅱ回#9塔。架空线路全长1.919km,其中双回架空线路长1.84km,单回路架空线路长97m。

新建线路110kV芸伟变构架至新建#14塔采用同塔双回架设,鼎芸Ⅱ回从#14塔引下,改为电缆敷设至已建的鼎康Ⅱ回#9塔,鼎芸Ⅰ回从新建#14塔架空接至已建的鼎康Ⅰ回#9塔。本工程新建铁塔共14基,其中直线塔2基,耐张塔12基,均为钢管杆。

本工程全线导线采用JLHA3-335中强度全铝合金导线,全线安全系数不低于7.0。本工程芸伟变构架~新建#14塔段地线为双OPGW复合光纤地线,两根地线均直接接地;新建#14塔~已建鼎康Ⅰ回#9塔段地线一根为OPGW复合光纤地线另一根为JLB40-80良导体地线,两根地线均直接接地。本工程以芸伟变往已建鼎康Ⅰ回#9塔为线路前进方向,OPGW挂在塔头右侧地线架上,良导体挂在塔头左侧地线架上。

本工程OPGW光缆接至鼎美变构架,因此需将鼎康Ⅰ回、鼎康Ⅱ回原良导体地线更换为OPGW光缆。

- 1 -

鼎美-芸伟110kVⅠⅡ回线路工程 立塔架线施工方案

2、新建部分

本工程新立钢管杆14基、新架设2km导线。 3、主要交叉跨越

(二)主要交叉跨越

跨10kV线路 2处 跨通讯线 2处 跨公路 村道 6处

跨树林 40处(60m为一处)

- 2 -


110kV立塔架线施工方案 - 图文.doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:vxWorks设备驱动开发指南(2)

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: