QGDW248— 2008 5、第5部分:变电站电气工程施工 - 图文

2019-04-22 22:40

ICS 29.240

备案号:CEC 130?2009

Q/GDW

国家电网公司企业标准

Q / GDW 248.5 — 2008

输变电工程建设标准 强制性条文实施管理规程

第5部分:变电站电气工程施工

Management regulation for enforcing the compulsory provisions of standards of transformer substation engineering construction

Part 5: Electrical construction of the substation

2009-06-30发布

2009-06-30实施

国家电网公司

发 布

305

Q / GDW 248.5 — 2008

306

Q / GDW 248.5 — 2008

目 次

前言 ···························································································································· 309 1 范围 ······················································································································· 310 2 规范性引用文件 ········································································································ 310 3 强制性条文执行计划表 ······························································································· 310 4 高压电气设备 ··········································································································· 316 4.1 断路器 ················································································································· 316 4.2 变压器 ················································································································· 317 4.3 母线 ··················································································································· 318 5 电缆线路施工 ··········································································································· 318 6 接地装置施工 ··········································································································· 318 6.1 变电站设备接地 ······································································································· 318 6.2 室内外接地网施工 ···································································································· 319 6.3 接地线连接 ············································································································ 320 6.4 重要设备和设备架构接地 ···························································································· 321 6.5 电缆接地 ·············································································································· 321 6.6 电气装置本体接地 ···································································································· 321 6.7 变电站附属及二次设备接地 ·························································································· 322 6.8 接地体焊接 ············································································································ 322 6.9 GIS接地 ··············································································································· 323 6.10 避雷针(带、网施工)······························································································ 324 6.11 携带式和移动式电气设备接地 ······················································································ 325 6.12 输电线路杆塔接地线 ································································································ 325 6.13 通讯及微波站二次系统接地 ························································································ 326 6.14 配电装置接地 ········································································································ 326 7 旋转电机施工 ··········································································································· 327 8 盘、柜安装 ·············································································································· 327 9 架空线路施工 ··········································································································· 327 10 低压电器设备安装 ···································································································· 327 11 起重机电气设备安装 ································································································· 328 11.1 起重机接地··········································································································· 328 11.2 起重机电气设备安装 ································································································ 329 11.3 起重机试运··········································································································· 330 12 危险环境电气装置施工······························································································ 331 12.1 危险环境电气装置安装······························································································ 331 12.2 危险环境的接地 ····································································································· 333 12.3 危险环境通风 ········································································································ 334 13 交接试验 ················································································································ 334 13.1 交流电动机 ·········································································································· 334

307

Q / GDW 248.5 — 2008

13.2 变压器 ················································································································ 335 13.3 电抗器及消弧线圈 ··································································································· 335 13.4 互感器 ················································································································ 335 13.5 真空断路器 ·········································································································· 336 13.6 SF6断路器 ··········································································································· 336 13.7 SF6封闭式组合电器 ································································································· 336 13.8 电力电缆 ············································································································· 337 13.9 避雷器 ················································································································ 337 13.10 架空线路 ············································································································ 337 13.11 接地 ················································································································· 337

附录A(规范性附录) 低压电气设备安装强制性条文引用表 ················································ 339 附录B(规范性附录) 危险环境电气装置施工强制性条文引用表 ·········································· 340

308

Q / GDW 248.5 — 2008

前 言

根据国家电网公司国家电网科[2008]928号《关于下达国家电网公司2008年度标准制修订计划(第一批)的通知》,制定本规程。

本标准贯彻“强制性条文、强制性执行”的指导思想。

《输变电工程建设标准强制性条文实施管理规程》是一套系列标准,用于输变电工程建设中强制性条文的执行、检查及记录。

该规程由如下8部分组成: ——第1部分:通则

——第2部分:变电站建筑工程设计 ——第3部分:变电站建筑工程施工 ——第4部分:变电站电气工程设计 ——第5部分:变电站电气工程施工 ——第6部分:输电线路工程设计 ——第7部分:输电线路工程施工 ——第8部分:输变电工程施工安全

本部分是该规程中的第5部分:变电站电气工程施工。对变电站电气工程施工质量强制性条文参建各责任主体单位的执行、检查及记录做了统一规定,尽可能地避免在执行中发生偏差、遗漏和违反强制性条文的情况,有利于变电站电气工程施工水平及工程实体质量的提高。

本规程由国家电网公司基建部提出。 本规程由国家电网公司科技部归口。 本规程由国家电网公司基建部负责解释。

本部分主编单位:山西省电力建设工程质量监督中心站 本部分参编单位:山西锦通工程项目管理咨询有限公司

山西省电力公司忻州供电分公司

本部分主要起草人:高士法、丁瑞明、郝志刚、王巳英、毛志文、李源、浮习新、石志伟、李灵川、张雷、白彦杰、王锐锋、陈强、薛茜、李怀斌、周利柱、范国平陈建光

309


QGDW248— 2008 5、第5部分:变电站电气工程施工 - 图文.doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:测试试题(1)-AIX

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: