5708#外架施工方案(悬挑架经专家论证)

2019-04-01 16:31

目录

一、工程概况 .................................................................................................................................................................. 2 1.1、项目概况: ......................................................................................................................................................... 2 1.2、外架搭设概况 ..................................................................................................................................................... 2 1.3、技术保证条件 ..................................................................................................................................................... 4 1.4、施工要求 ............................................................................................................................................................. 4 1.5、施工场地条件 ..................................................................................................................................................... 4 二、编制依据 .................................................................................................................................................................. 4 三、施工计划 .................................................................................................................................................................. 5 3.1、施工进度计划 ..................................................................................................................................................... 5 3.2、周转材料计划 ..................................................................................................................................................... 5 3.3、机械设备计划表 ................................................................................................................................................. 6 四、施工工艺技术 .......................................................................................................................................................... 7 4.1、工艺流程 ............................................................................................................................................................. 7 4.2、外架搭设施工方法 ............................................................................................................................................. 7 4.3、特殊部位处理 ................................................................................................................................................... 11 4.4、检查验收 ........................................................................................................................................................... 14 4.5、脚手架的拆除 ................................................................................................................................................... 15 五、施工安全保证措施 ................................................................................................................................................ 15 5.1、组织保证措施 ................................................................................................................................................... 15 5.2、安全保证措施 ................................................................................................................................................... 16 5.3、应急预案 ........................................................................................................................................................... 18 5.4、检测监控 ........................................................................................................................................................... 22 六、外架劳动力计划 .................................................................................................................................................... 23 6.1、专职安全员安排计划 ....................................................................................................................................... 23 6.2、外脚手架劳动力计划 ....................................................................................................................................... 24 七、相关计算书及图纸 ................................................................................................................................................ 24 7.1.脚手架参数 .......................................................................................................................................................... 24 7.2.活荷载参数 .......................................................................................................................................................... 24 7.3.风荷载参数 .......................................................................................................................................................... 24 7.4.静荷载参数 .......................................................................................................................................................... 25 7.5.水平悬挑支撑梁 .................................................................................................................................................. 25 7.6.拉绳参数 .............................................................................................................................................................. 25 7.7、小横杆的计算 ................................................................................................................................................... 26

0

7.8.大横杆的计算 ...................................................................................................................................................... 27 7.9.扣件抗滑力的计算 .............................................................................................................................................. 29 7.10.脚手架立杆荷载的计算 .................................................................................................................................... 29 7.11、连墙件的计算 ................................................................................................................................................. 30 7.12、①型3米悬挑梁的受力计算(16#2.2米长工字钢1.2米悬挑长度) .................................................... 31 7.13、②型阳角处16#工字钢3米悬臂梁组合斜撑的受力计算 ........................................................................... 35 7.14、③型阳台处16#工字钢4.5米悬臂梁组合斜撑的受力计算 ........................................................................ 39 7.15、④型阳台处20A#工字钢4.5米悬臂梁受力计算 ......................................................................................... 44 7.16、⑤型采光井处20A#工字钢6米简支梁受力计算 ........................................................................................ 47 7.17、阳台处卡口梁承载力验算 ............................................................................................................................. 51 附图一:1#、2#、3#楼结构平面图 附图二:悬挑架挑梁布置平面图 附图三:悬挑架各立面示意图 附图四:施工平面布置图

附图五:悬挑架挑梁监测点平面示意图

1

一、工程概况

1.1、项目概况:

本工程于贵阳市花溪区洛平村,由贵阳市公共住宅投资建设(集团)有限公司投资建设,上海沪闵建筑设计院有限公司设计,贵州黔水工程监理有限公司监理,中铁五局建筑工程有限责任公司承建。 本工程为地下室两层、塔楼1层公建配套加28层住宅,标准层层高3米,屋面顶标高为90.00m,总建筑面积为52786㎡。属于一类高层居住建筑,建筑使用年限为50年。结构形式:框架剪力墙结构,结构类别为二类抗震设防烈度为六度。 悬挑层结构情况:

梁截面尺寸为200*500mm,配筋分别2C18+3C18 、2C16+2C16 、2C18+3C16 、2C16+3C16四种(承载力验算选2C16+2C16)。

.结构板厚100mm 板底配筋C8@200。 混凝土最低强度等级为C30。

外墙饰面采用米色涂料和黄色涂料。

1.2、外架搭设概况

因地下室裙楼图纸未出、3#楼范围内有军用电缆(待甲方定出具体方案)暂不施工,故现在仅施工1、2#楼主体塔楼部分。1、2#楼正南面及1#楼正西面为高边坡(见附图四:施工平面布置图),待地下室施工完成后全部回填至正负零标高,本工程地下室底板至标准层一层顶搭设落地式双排脚手架,从标准层2层板开始搭设悬挑式脚手架。分三段搭设,第一段从标准层2层底(标高9.00m)开始搭设,第二段从标准层11层底(标高36.00m)开始搭设,第三段从标准层20层底(标高63.00m)开始搭设,63.00至屋面顶90.00加1.5m防护,悬挑高度为28.5m,固最大悬挑高度为28.5米。部分斜屋面架体在87.00处再次悬挑至屋檐标高加1.5m防护。本方案主要是针对悬挑式脚手架部分编制,计算的脚手架为双排脚手架最不利搭设高度为28.5米.

立杆的纵距为 1.5米,立杆的横距为0.8米,立杆的步距为1.8米,每一步架设置两根水平拦腰杆,立杆采用单立管,内立杆距离墙长度为0.3米,小横杆在大横杆之上,采用的钢管类型为 Φ48×3.0(按照Φ48×2.8计算),横杆与立杆连接方式为单扣件,连墙件层层设置,即竖向间距3米,水平间距4.5米,采用扣件与预埋钢管连接,脚手架外侧自上而下满搭剪刀撑。悬挑水平钢梁采用[16号、20a号工字钢]。 在4、10、19层设置挑棚,挑棚采用6m钢管悬挑,不与架体连接。(挑棚方案另见专项方案)

外架搭设方案表 栋号 1# 2# 3# 第一次悬挑高度(m) 27 27 27 第二次悬挑高度(m) 27 27 27 第三次悬挑高度(m) 28.5 28.5 28.5 架体总高度(m) 82.5 82.5 82.5 2

附图一、1#、2#、3#楼结构平面图(3栋楼主体结构完全相同)

3

1.3、技术保证条件

(1)脚手架搭设人员必须是经过按现行国家标准《特种作业人员安全技术考核管理规则》(GB 5036)考核合格的专业架子工,上岗人员要定期体检,合格者方可持证上岗。 (2)作业人员经培训上岗,操作前进行技术交底。

(3)本方案仅针对1#、2#、3#楼悬挑式脚手架,根据建质87号文件要求,本工程悬挑式脚手架高度已超20米,需编制专项方案,并请专家进行论证。

1.4、施工要求

(1)作业层上的施工荷载要符合设计要求,不得超载,不得将模板支架、泵送混凝土和砂浆的输送管等固定在脚手架上,严禁悬挂起重设备。

(2)连墙件设置符合方案要求,并禁止私自拆除。

(3)每一颗悬挑水平钢梁必须采用14#钢丝绳作为保险绳反拉。

(4)所使用材料必须符合方案要求,并经检验合格后方可使用,如钢管壁厚不小于2.8mm,无严重锈蚀、开裂等现象,扣件无滑丝。

1.5、施工场地条件

本工程交通较方便;1、2#楼正南和正北面及1#楼正西面属高边坡回填区域,此区域落地架体(-10.20m~9.00m)在裙楼施工完成后拆除,待回填后重新搭设装修脚手架(拆除及二次搭设高度按图纸计量);周围场内有高压线通过,离外架最小水平间距为30m,虽高压线离外架满足安全距离但仍在塔吊覆盖范围内,特此加强塔吊班组技术交底,避免在此高压线区域吊运。具体现场防护棚及通道设置图见施工平面布置图(附图四)。

二、编制依据

1、《建筑结构荷载规范》(GB 50009-2012); 2、《钢结构设计规范》(GB 50017-2003); 3、《混凝土结构设计规范》(GB 50010-2010); 4、《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2011); 5、建筑施工安全检查标准(JGJ59-2011)

6、施工现场临时用电安全技术规范(JGJ46-2005) 7、《特种作业人员安全技术考核管理规则》(GB 5306-85) 8、《建筑施工高处作业安全技术规范》(JGJ80-91); 9、《危险性较大的分部分项工程安全管理办法》(建质〈2009〉87号文);

10、贵州黔鹰5708铝箔厂国有工矿棚户区改造工程实施性施工组织设计及施工图纸等; 11、我公司的相关安全、质量管理办法。

4


5708#外架施工方案(悬挑架经专家论证).doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!