**场地回填及地基处理工程
施工组织方案
编制单位: 编 制: 审 核: 审 批:
日 期 年 月 日
目 录
第1章 概述 ········································································································································· 1 1.1编制依据 ····················································································································· 1 1.2工程概述 ····················································································································· 2 1.2.1地理位置及地质特征 ································································································ 2 1.2.2工作范围和施工内容 ································································································ 2 1.2.3质量要求 ·················································································································· 3 1.2.4 主要工程数量表 ······································································································ 3 1.2.5 设计要求 ················································································································· 4 第2章 施工概要 ·································································································································· 5 2.2计划投入的主要机械设备 ··························································································· 5 第3章 项目组织机构 ·········································································································· 5 3.2主要职责 ····················································································································· 8 第5章 施工顺序与施工工艺············································································································ 12 5.2施工工艺流程 ············································································································ 12 5.3 主要项目施工方法 ·································································································· 14 第6章 施工监测 ································································································································ 35 6.1监测目的和监测项目 ································································································· 35 6.2表面沉降监测 ············································································································ 35 6.3孔隙水压力监测 ········································································································ 36 6.4分层沉降监测 ············································································································ 38 6.5深层位移监测 ············································································································ 40 6.6施工后钻孔取土 ········································································································ 41 6.7加固后现场十字板剪切试验 ······················································································ 42 6.8质量保证措施 ············································································································ 43 6.9加固效果的评价依据 ································································································· 44 6.10监测及试验工程量 ·································································································· 47 6.11测量仪器设备表 ······································································································ 48 6.12试验及监测人员使用计划 ······················································································· 48 第7章 施工进度计划 ······················································································································ 49 7.1 工期计划 ·················································································································· 49 7.2 施工船机效率分析 ···································································································· 49 7.3 施工进度计划网络图、横道图 ················································································· 49 7.4 施工进度保证措施 ···································································································· 50 第8章 质量计划与保证措施············································································································ 53 8.1 质量目标 ·················································································································· 53
8.2 质量管理保证体系 ···································································································· 54 8.3 项目主要人员质量管理职责 ····················································································· 57 8.4 质量保证措施 ··········································································································· 59 第9章 安全计划和措施 ···················································································································· 66 9.1 安全生产的原则和目标 ···························································································· 66 9.2 安全生产管理组织机构、保证体系和安全生产责任 ················································ 66 9.3 安全工作程序 ··········································································································· 69 9.4 奖励及处罚 ·············································································································· 70 9.5 员工安全教育及培训 ································································································ 71 9.6 事故的损害报告,调查及分析 ················································································· 72 9.7 安全检查及核查 ······································································································· 73 9.8 本工程的安全风险评估 ···························································································· 73 9.9 施工区、生活区的安全及卫生控制 ·········································································· 74 9.10 施工现场强制性安全要求 ······················································································· 74 9.11 医疗服务和紧急响应 ······························································································ 77 9.12 应急计划和措施 ····································································································· 78 第10章 环保计划和措施 ················································································································ 79 10.1 对环保和文明施工承诺 ·························································································· 79 10.2 施工作业区环保和文明施工措施 ············································································ 80 10.3 环境、环保、卫生管理 ·························································································· 81 10.4 生活区后勤场区管理措施 ······················································································· 82 10.5 配合环境保护的施工措施 ······················································································· 83
第1章 概述
1.目的
1.1 保证为甲方提供《**工程施工合同》规定的各项施工任务。 1.2 保证**工程施工阶段的施工作业按规定的方法和程序在控制下进行。
2.适用范围
本施工组织设计适用于**工程的施工准备,软地基处理,土方回填及平整,站场内外道路,房屋建筑,设备管道基础,室外环境,给排水、电气、通讯、消防、空调通风安装等全过程施工作业。
3.职责
3.13.2 技术负责人负责本施工组织设计在各专业、工序内有效运行,并在本施工组织设计指导下制定施工作业程序,具体指导施工实务作业。
3.3 质检员、检安员、施工员及其他项目管理人员将依据本施工组织设计、施工作业程序进行施工实务作业。
1.1编制依据
1、**公司的设计图纸
2.现行有关的技术标准与施工规范
(1)、《建筑地基基础设计规范》GB5007-2002 (2)、《建筑地基处理技术规范》JGJ79-2002
(3)、《建筑地基基础工程施工质量验收规范》GB50202-2002
************************* 第 1 页 共85页
(4)、《建筑结构荷载规范》GB50009-2001 (5)、《土工试验方法标准》GB/T50123-99 (6)、《岩土工程勘察规范》GB5001-2001 (7)、《塑料排水板施工规程》JTJ/256-96
(8)、《建筑工程施工质量验收统一标准》GB50300-2001 (9)、《工程测量规范》GB50026-93
(10)、《真空预压法加固软土地基施工技术规程》HG/T20578-95 (11)、《土工合成材料聚氯乙烯土工膜》GB/T17688-1999
1.2工程概述
1.2.1地理位置及地质特征
本工程位于**
1.2.2工作范围和施工内容
a、工作范围:主要包括**M2的地基处理的施工。工作内容包括但不限于以下内容:
b、施工内容: (1)、回填素土 (2)、铺设中粗砂垫层 (3)、插塑料排水板 (4)、挖密封沟、铺密封膜
************************* 第 2 页 共85页