目 录
1 编制依据 .................................................................................................................................................. 2 2 工程概况 .................................................................................................................................................. 2 3 材料的选择及配置 .................................................................................................................................. 3 4 模板及支撑体系设计 .............................................................................................................................. 4
4.1墙模板 .............................................................................................................................................. 4 4.2柱模板 .............................................................................................................................................. 5 4.3梁模板 .............................................................................................................................................. 6 4.4板模板 .............................................................................................................................................. 9 4.5楼梯模板 ........................................................................................................................................10 4.6车道弧形墙模板 ............................................................................................................................12 5 模板工程施工工艺及施工方法 ............................................................................................................ 12 5.1模板工程施工工艺 ........................................................................................................................12 5.2模板工程施工方法 ........................................................................................................................13 6 施工总体部署 ........................................................................................................................................ 15 7 模板施工技术措施 ................................................................................................................................ 17
7.1进场模板质量标准 ........................................................................................................................ 17 7.2 质量保证程序及质量信息反馈体系 ............................................................................................ 17 7.3模板安装质量要求 ........................................................................................................................18 7.4脱模剂及模板堆放、修补 ............................................................................................................ 20 8 模板的拆除 ............................................................................................................................................ 21 9 安全文明施工措施 ................................................................................................................................ 22
9.1 管理制度 .......................................................................................................................................22 9.2 施工措施 .......................................................................................................................................22 10 模板工程质量通病及防治方案 .......................................................................................................... 23 11 模板设计计算书 .................................................................................................................................. 27
11.1墙模板 .......................................................................................................................................... 27 11.2柱模板 ..........................................................................................................................................34
11.2.1中小截面柱模板验算 .......................................................................................................34 11.2.1大截面柱模板验算 ...........................................................................................................41 11.3 梁模板 .........................................................................................................................................42 11.4满堂架楼板模板验算 .................................................................................................................. 53
1 编制依据
1、南宁**中心项目一期购物中心工程相关施工图纸; 2、南宁**中心项目一期购物中心施工组织设计; 3、南宁市政府有关文件和规定; 4、建筑工程施工质量验收统一标准;
5、混凝土结构工程施工质量验收规范(GB50204-2002); 6、建筑施工扣件式钢管脚手架安全技术规程(JGJ130-2001); 7、建筑施工模板安全技术规范(JGJ 162-2008); 8、建筑工程模板施工手册 中国建筑工业出版社(第二版); 9、《建筑施工手册》(第四版); 10、广西建筑工程施工质量验收系统; 11、本方案计算采用品茗施工安全计算软件。
2 工程概况
南宁**中心项目一期购物中心位于南宁市******商务区核心区内,**大道、**路、**路交汇处。本工程为超大型商业购物中心,总建筑面积为288341.36㎡,其中地下3层,建筑面积118031.23㎡,地上6层,建筑面积170310.13㎡,净用地面积34824㎡,总建筑高度为47.30m。结构安全等级为二级,设计使用年限50年。
本工程设计标高±0.000m相当于黄海高程95.50m。地下部分各层层高为:B3层4.15m、B2层3.90m、B1层3.35m、B1M(地下一层夹层)3.4m,地上部分各层层高为L1层3.35m、L1M(一层夹层)3.4m、L2层6.0m、L3层6.0m、L4层6.5m、L5层6.0m、L6层6.0m、屋顶层6.0~10.0m。
本工程需使用模板的部分有:桩承台基础、基础梁、地下室挡土墙、主体结构柱、剪力墙、梁、板等。其中承台基础及基础梁采用砖胎模施工,具体详见我司已编制的砖胎模施工方案,另本工程地下部分消防水池、泵房、冷冻机房处层高超过8.0m,地上三层(la-E)轴/(1/la-14)~(2-1)轴处存在跨度大于18m的梁,以及部分框架梁截面尺寸较大如1500×1500、1200×2200等,总荷载超过20 KN/㎡,针对此部分梁、板模板的支设,我司将单独编制高大模板安全专项施工方案并组织专家论证。本方案仅针对普通模板工程编制。
主要构件的尺寸详见下表:
底板 承台厚度 楼板 700、500 1200、1400、1800、1900、2000 100、120、150、180、200 1500×1500、1000×1100、1000×1000、750×900、700×1600、600×2200、500×900、500×800、400×700、300×700、1800×500、1300×400、850×400、800×500等 墙 外墙 内墙 人防墙 600、500、400 300 300 混凝土构件尺寸(mm) 梁 柱 1600×1100、1400×1400、1300×1300、1500×1000、1000×1000、900×900、800×800、600×600等 3 材料的选择及配置 根据我公司对本工程创优目标的要求,模板体系的选型是关系到本工程施工进度和质量目标实现的关键。
本工程根据施工工期、质量和安全要求,在选择方案时,充分考虑以下几点: (1)模板及其支架的结构设计,力求做到安全可靠,不变形、不破坏、不倒塌。 (2) 在规定的条件下和规定的使用期限内,能够充分满足预期的安全性和耐久性。 (3)从经济性方面考虑,选用材料时,因地制宜,增加周转,减少支拆用工,便于保养维修,造价经济合理。
(4)实用性方面保证砼结构的质量: ①接缝严密,不漏浆;
②保证构件的形状和相互位置的正确; ③模板构造相对简单,支拆方便。
(5)按模板承受荷载的最不利组合对模板进行验算。
综合以上几点,本工程将选用1830 mm×915 mm×18mm的9层胶合板模板。模板及模板支架的搭设,还必须符合《建筑施工安全检查标准》(JGJ59-99)检查标准要求,并符合南宁市文明标准化工地的有关要求。
竖向次背楞采用50×100木枋,脚手架、模板支撑体系均采用Φ48×3.0的无缝钢管进行搭设,回转扣件、直角扣件、对接扣件等必须配套齐全,扣件活动部位应灵活转动,与钢管的贴合面必须严格整齐,保证与钢管扣紧时接触良好,同时,所有构配件必须经过防锈处理,确保力学性能达到规范要求。地下室部含有部分弧形墙,考虑钢管的不易弯折性,弧形墙水平模板水平支撑横楞采用φ20钢筋加固。周转材料配备时考虑
以下几方面因素:
(1)施工顺序依次为AⅣ-1→AⅢ-1→AⅡ-1→AⅠ-1、AⅠ-2→AⅡ-2→AⅢ-2→AⅣ-2两条流水并行施工。
(2)柱距大部分为1.1m,按《混凝土结构工程施工质量验收规范》(GB50204-2002)要求梁板混凝土强度应满足100%强度后才能拆模。
(3)地下室存在大量后浇带,后浇带所在区域内模板应在后浇带浇筑(至少结构施工完后60天)后且混凝土达到一定强度后才能拆除。
综合以上情况,地下室按以下方式进行周转材料配备:地下室水平结构按三层满配,竖向结构满配一层,地上结构考虑在周转使用地下室配备材料的基础上,根据工程实际增进材料。
4 模板及支撑体系设计
4.1墙模板
本工程墙厚度有600mm、500 mm、400 mm、300mm、250mm、200mm等。模板采用18厚木模,竖向次背楞采用50×100木枋,间距不大于300mm,水平方向主背楞采用Φ48×3.0钢管@450mm。外墙、人防墙、水池墙均采用Φ14一次性止水对拉螺杆,墙体一次浇注高度以层高为准,因负一层及一层部分区域含夹层,故此相应区域考虑分两次浇筑 ,基本考虑分层高度自地下三层依次为4.15m、3.9m、3.35m、3.4m、3.35m、3.4m、6.0m、6.0m、6.5m、6.0m、6.0m。支撑体系如下图所示:
4.2柱模板
本工程混凝土柱均多为矩形柱,模板采用18mm厚木模板,现场拼装定型,普通钢