1、编制依据 ....................................................................................................................................... 1 2、工程概况 ....................................................................................................................................... 1 2.1、工点段落 ................................................................................................................................... 1 2.2、地质情况 ................................................................................................................................... 1 2.3、土石方数量 ............................................................................................................................... 2 2.4、边坡防护形式 ........................................................................................................................... 3 3、施工准备、部署 ........................................................................................................................... 3 3.1、施工准备 ................................................................................................................................... 3 3.2、施工人员、设备 ....................................................................................................................... 3 3.3、进度计划 ................................................................................................................................... 4 4、施工技术方案 ............................................................................................................................... 4 4.1、土石方工程施工 ....................................................................................................................... 4 4.2、石方爆破施工 ........................................................................................................................... 5 4.2.1、爆破方案 ............................................................................................................................... 5 4.2.2、爆破控制方案 ....................................................................................................................... 6 4.2.3、爆破安全 ............................................................................................................................... 8 4.3、浆砌工程施工 ........................................................................................................................... 9 4.3.1、材料要求 ............................................................................................................................... 9 4.3.2、施工方法 ............................................................................................................................... 9 4.4、片石混凝土挡墙施工 ............................................................................................................. 11 4.4.1、材料要求 ............................................................................................................................. 11 4.4.2、施工方法 ............................................................................................................................. 11 4.4、锚固工程施工 ......................................................................................................................... 13 4.4.1、系统锚杆框架梁施工 ......................................................................................................... 13 4.4.1.1、施工准备 ......................................................................................................................... 13 4.4.1.2、施工方法 ......................................................................................................................... 13 4.4.2、预应力锚杆框架梁施工 ..................................................................................................... 16 4.4.2.1、施工准备 ......................................................................................................................... 16 4.4.1.2、施工方法 ......................................................................................................................... 16 4.5、排水工程施工 ......................................................................................................................... 21 5、监控量测 ..................................................................................................................................... 21 5.1、监测目的 ................................................................................................................................. 21

5.2、监测内容 ................................................................................................................................. 21 5.3、监测项目 ................................................................................................................................. 21 5.4、监测时间及频度 ..................................................................................................................... 22 6、质量保证措施 ............................................................................................................................. 22 6.1、质量保证体系 ......................................................................................................................... 22 6.2、质量保证措施 ......................................................................................................................... 23 7、施工安全 ..................................................................................................................................... 24 7.1、人身安全 ................................................................................................................................. 24 7.2、设备安全 ................................................................................................................................. 24 7.3、材料安全 ................................................................................................................................. 25 7.4、环境安全 ................................................................................................................................. 25 7.5、工艺安全 ................................................................................................................................. 25

1

路堑高边坡施工方案

1、编制依据 2、工程概况

XXX合同段起讫桩号:K140+620~K146+400,全长5.78km,该区岩层主要为下古生界-元古界变质岩类组成,岩性以石英片岩、泥质板岩、砂质板岩、砂质千枚岩、碳质千枚岩等为主,构造侵蚀剥蚀作用较强烈。该段主要为老地层,断裂十分发育,对线路有一定影响。

2.1、工点段落

其工点段落见下表。

表1 深路堑高边坡一览表

长度起讫桩号 (m) K140+855 K141+860 K142+703 K142+703 ~ ~ ~ ~ K140+903 K141+963.5 K142+880 K142+840 YK143+320 ZK144+906 48 103.5 177 137 73 141 左 左 右 右 右 右 边坡位臵 (m) 7.4 18.9 26.6 26.6 21.9 5 (m) 30.3 34.3 44.44 31.2 47.4 38 最大挖深最大坡高YK143+247 ~ ZK144+765 ~ 2.2、地质情况

1)周家沟深路堑(K140+855~K140+903)

本路堑位于文峰乡长坪村,路堑区属构造侵蚀剥蚀中低山地貌,路堑区域及周边断层、褶皱构造发育,剥蚀严重。岩性为强风化~弱风化石英片岩。路堑右侧边坡为挖方路基,挖方路基开挖深度小,坡向和岩层倾向组合关系为逆向坡。

设计边坡坡率采用1:0.75、1:1、1:1、1:1.25,最大坡高31.3m。 2)文峰1号深路堑(K141+860~K141+963.5)

本路堑位于文峰乡长坪村,路堑区属构造侵蚀剥蚀中低山地貌,位于山体斜坡较陡部位,坡顶高程约为652m,坡底高程约为594m,相对高差58m,坡向约为71°~243°,坡脚14°~35°。岩性为碎石土、强风化~弱风化石英片岩。边坡切坡较高,表层碎石

1

土层属松散结构,强风化地层遇水易软化,抗剪强度降低,坡向和岩层倾向组合为顺向坡,不利于边坡稳定。

设计边坡坡率采用1:1、1:1、1:1、1:1.25、1:1.25。 3)文峰2号深路堑(K142+703~K142+840)

本路堑位于文峰乡长坪村,路堑区属构造侵蚀剥蚀中低山地貌,位于山体斜坡地带,坡顶高程约为664m,坡底高程约为599m,相对高差约为65m。岩性为强风化~弱风化石英片岩。边坡切坡较高,表层风化地层遇水易软化,抗剪强度降低,坡向和岩层倾向组合为顺向坡,不利于边坡稳定。

左侧设计边坡坡率采用1:1、1:1.75、1:1.75、1:1.75、1:1.75、1:1.75。 右侧设计边坡坡率采用1:1、1:1、1:1、1:1.25。 4)纸纺沟1号深路堑(YK143+247~YK143+320)

本路堑位于文峰乡长坪村五组,路堑区属构造侵蚀剥蚀中低山地貌,位于山体斜坡地带,坡顶高程约为654m,坡底高程约为544m,相对高差约为110m,为单斜坡地貌。性为碎石土、强风化~弱风化石英片岩。边坡切坡较高,表层碎石土层属松散结构,强风化地层遇水易软化,抗剪强度降低。主要发育为2组节理:J1与坡向组合为逆向坡;J2与坡向组合为顺向坡,不利于边坡稳定。

设计边坡坡率采用1:0.75、1:1、1:1、1:1.25、1:1.25。 5)纸纺沟2号深路堑(ZK144+765~ZK144+906)

本路堑位于文峰乡长坪村五组,属构造侵蚀剥蚀中低山地貌,位于山体坡脚,坡顶高程约为655m,坡底高程约为564m,相对高差约为91m,为单斜坡地貌。岩性为强风化~弱风化石英片岩,坡向和岩层倾向为顺向坡。

设计边坡坡率采用1:0.75、1:1.25、1:1.25、1:1.25~1.75、1:1.25。

2.3、土石方数量

表2 路堑土石方数量表

挖方 序号 1 2 3 K140+855 K141+860 K142+703 起讫桩号 (m) ~ ~ ~ K140+903 K141+963.5 K142+880 2

3填方 土石方调配 (m) 1.2 431 到弃土坑K140+800 到弃土坑K140+800 到弃土坑K142+450 310233 87649.6 123557.1 4 5 YK143+247 ZK144+765 ~ ~ YK143+320 ZK144+906 61643.6 20932.9 154 4324.8 到弃土坑K143+350 挖方部分调至路基 2.4、边坡防护形式

本合同段高边坡防护工程主要有以下形式(具体工程量见图纸):

1)浆砌防护工程:浆砌片石路堑矮墙护坡、挂网喷播混生植被护坡基础、浆砌拱形骨架护坡;

2)片石混凝土工程:片石混凝土路堑挡土墙; 3)锚固工程:系统锚杆框架梁、预应力锚杆框架梁; 4)排水工程:路堑边沟、平台截水沟、坡顶截水沟、急流槽。

3、施工准备、部署

3.1、施工准备

1)对设计文件进行现场调查与核对,做好截排水设施,永临结合设计排水系统。开工前,调查山体在自然状态下的稳定状况,分析施工期间边坡的稳定性,发现问题及时加固处理;

2)复测已经完成、水准点及导线网的布设满足施工需要;

3)项目部根据相关技术规范,完成对施工班组下发技术交底工作;

3.2、施工人员、设备

本合同段安排两个路基作业队伍,负责路基土石方工程、防护工程及便道维护整修。

表3 施工人员计划表

路基作业队 路基作业一队 路基作业二队 管理人员 8 5 测量人员 3 3 机械人员 14 10 施工人员 40 30 它他人员 10 8 合计 75 56 表4 施工机械计划表

序号 1 2 机械名称 推土机 挖掘机 型号、规格 TY220、162Kw ACT320 3

单位 台 台 数量 2 4