混凝土工程施工方案京东方 - 图文

2019-03-10 14:09

目 录

一、编制依据····················································································································································· 1 1.1工程设计图纸及施工组织设计············································································· 1 1.2规范、规程、标准及图集····················································································· 1 1.3其它························································································································· 1 二、工程概况····················································································································································· 2 2.1总体概况·················································································································· 2 2.2混凝土分项工程概况······························································································ 2 三、施工总体部署·········································································································································· 3 3.1混凝土浇筑方案的选择·························································································· 3 3.2施工流水段的划分·································································································· 3 四、施工准备····················································································································································· 4 4.1材料准备·················································································································· 4 4.2人员、机具设备准备······························································································ 5 4.3作业条件·················································································································· 5 五、混凝土的运输·········································································································································· 6 六、混凝土的泵送·········································································································································· 6 6.1砼泵的布置·············································································································· 6 6.2管道敷设注意事项·································································································· 7 6.3砼的泵送·················································································································· 7 七、混凝土的浇筑·········································································································································· 8 7.1工艺流程·················································································································· 8 7.2浇筑过程·················································································································· 8 7.3柱砼的浇筑柱·········································································································· 9 7.4剪力墙砼浇筑········································································································ 10 7.5梁、板混凝土浇筑································································································ 11

1

7.6楼梯砼的浇筑········································································································ 11 7.7构造柱、圈梁砼浇筑···························································································· 11 7.8后浇带砼浇筑········································································································ 12 八、混凝土的养护········································································································································14 九、混凝土试块留置 ··································································································································14 十、质量保证措施········································································································································15 10.1质量控制程序······································································································ 15 10.2质量标准·············································································································· 16 10.3质量保证措施······································································································ 20 十一、安全保证措施 ··································································································································21 8.1塔吊使用主要安全措施························································································ 21 8.2砼泵送设备的主要安全措施················································································ 22 8.3墙、柱、梁砼浇筑安全要求················································································ 22 8.4洞口安全防护措施································································································ 22 十二、成品保护保证措施························································································································23 十三、环保保证措施 ··································································································································24

2

中国建筑一局(集团)有限公司 合肥京东方光电科技有限公司综合配套区项目 混凝土工程施工方案

一、编制依据

1.1工程设计图纸及施工组织设计

1、《合肥京东方光电科技有限公司综合配套区项目施工组织设计》

2、合肥京东方光电科技有限公司综合配套区项目设计施工图纸、设计修改通知单及工程洽商记录

1.2规范、规程、标准及图集

1、《建筑工程施工质量验收统一标准》(GB50300-2001) 2、《混凝土结构施工质量验收规范》(GBJ50204-2002) 3、《混凝土结构设计规范》(GB50010-2002) 4、《混凝土结构设计规范》(GB50010-2002)

5、《普通混凝土力学性能试验方法》(GB/T50081-2002) 6、《混凝土强度检验评定标准》(GBJ 107-87) 7、《混凝土外加剂应用技术规范》(GB50119-2003) 8、《混凝土质量控制标准》(GB 50164-92)

9、《混凝土结构工程施工质量验收规范》(GB 50204-2002) 10、《混凝土泵送施工技术规程》(JGJ/T10-95)

11、《普通混凝土用砂、石质量及检验方法标准》(JGJ52-2006) 12、《普通混凝土配合比设计规程》(JGJ55-2000) 13、《混凝土用水标准》(JGJ63-2006)

14、《混凝土异形柱结构技术规程》(JGJ149-2006) 15、《建筑工程冬期施工规程》(JGJ 104-97)

16、《混凝土结构施工图平面整体表示方法制图规则和构造详图(框架、剪力墙)》(03G101-1修正版)

17、《混凝土结构施工图平面表示方法制图规则和构造详图(现浇混凝土板式楼梯)》(03G101-2)

18、《现浇混凝土楼面与屋面板》(04G101-4)

19、《独立基础、条形基础、桩基承台平法》(06G101-6) 1.3其它

1

中国建筑一局(集团)有限公司 合肥京东方光电科技有限公司综合配套区项目 混凝土工程施工方案

1、《建筑施工手册》(第四版)

2、《建筑工程施工工艺标准汇编》(中国建筑工程总公司)

二、工程概况

2.1总体概况

合肥京东方光电科技有限公司综合配套区工程位于合肥新站综合开发试验区,铜陵北路与礼河路交汇处,本工程共13栋建筑单体,1#-8#楼为8栋职工宿舍,均为11层;9#-10#楼为2栋职工公寓,均为6层;另有活动中心2层(地下1层)、食堂2层(局部3层)及锅炉房1层各一栋。所有建筑单体均为钢筋混凝土框架结构,1#-10#楼、食堂及锅炉房均无地下室,活动中心有一层地下室。总建筑面积约84340m2。

本工程结构形式均为现浇混凝土框架结构,其中9#、10#建筑为异形柱现浇混凝土框架结构。基础形式为:1#-10#楼均为桩承台基础,食堂、活动中心为现浇混凝土独立基础。 2.2混凝土分项工程概况

本工程工期较紧,混凝土浇筑用量大,施工现场场地有限,同时为了减少污染,确定采用商品混凝土,利用地泵和汽车泵配合进行混凝土的浇筑。 混凝土强度等级详见下表:

1#-8#楼混凝土强度等级 构件 基础顶~标高5.7 5.7标高~标高17.1 17.1标高~屋顶 标高 框架柱 C40 C35 C30 框架梁板 C30 C30 C25 混凝土墙 C40 C35 C30 过梁、构造柱、圈梁 C20 承台 C35 垫层 C15 注:用于固定幕墙的梁、柱(构造柱)、压顶不低于C25。 9#-10#楼混凝土强度等级 构件 基础顶~标高11.600 11.600标高~屋顶 标高 框架柱 C35 C30 框架梁板 C30 C25 混凝土墙 C35 C30 过梁、构造柱、圈梁 C20 2

中国建筑一局(集团)有限公司 合肥京东方光电科技有限公司综合配套区项目 混凝土工程施工方案

承台 C30 垫层 C15 注:用于固定幕墙的梁、柱(构造柱)、压顶不低于C25。 食堂混凝土强度等级 构件 基础顶~屋顶 标高 墙、柱 C30 梁、板 C30 过梁、构造柱、圈梁 C20 基础 C30 垫层 C15 注:用于固定幕墙的梁、柱(构造柱)C30。 活动中心混凝土强度等级 构件 基础顶~屋顶 标高 墙、柱 C30 梁、板 C30 过梁、构造柱、圈梁 C20 基础 C30 垫层 C15 注:1.用于固定幕墙的梁、柱(构造柱)C30。 2.地下室底板和地下室外墙均为抗渗混凝土,抗渗等级为P6。 锅炉房混凝土强度等级 构件 基础顶~屋顶 标高 墙、柱 C25 梁、板 C25 过梁、构造柱、圈梁 C20 基础 C25 垫层 C15 注:1.用于固定幕墙的梁、柱(构造柱)C30。 三、施工总体部署

3.1混凝土浇筑方案的选择

本工程混凝土采用商品混凝土,采用地泵、汽车泵与塔吊配合进行混凝土浇筑。

3.2施工流水段的划分

本工程共分为两个施工区域:一、 1#-4#楼、食堂及活动中心部分;二、5#-10#楼部分。这两部分分别由两个施工队伍同时进行施工。由于本工程工期较紧,结

3


混凝土工程施工方案京东方 - 图文.doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:XP-1A SF6定性检漏仪检漏操作

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: