目 录
1编制依据 ...................................................................................................................... 3 2编制原则 ...................................................................................................................... 3 3工程概况 ...................................................................................................................... 3
3.1综合概述 .......................................................................................................... 3 3.2施工条件 .......................................................................................................... 5 4总体施工布置 .............................................................................................................. 6
4.1组织机构设置 .................................................................................................. 6 4.2施工场地布置 .................................................................................................. 8 5施工前期准备及进度安排 ........................................................................................... 8
5.1施工前期准备 .................................................................................................. 8 5.2总体工期及进度计划安排 ............................................................................... 9 6单位工程主要施工方案及工艺 ................................................................................. 10
6.1主要施工方案 ................................................................................................ 10 6.2主要施工工序 ................................................................................................ 23 7质量保证措施 ............................................................................................................ 27
7.1质量管理体系 ................................................................................................ 27 7.2工程质量控制组织措施 ................................................................................. 31 7.3质量控制技术措施 ......................................................................................... 34 8安全目标及保证措施 ................................................................................................. 37
8.1安全目标 ........................................................................................................ 37 8.2安全保证体系 ................................................................................................ 37 8.3安全保证措施 ................................................................................................ 37 9文明施工及环水保保证措施 ..................................................................................... 42
9.1文明施工保证体系 ......................................................................................... 42 9.2文明施工保证措施 ......................................................................................... 42 9.3环境保护的措施 ............................................................................................ 43
9.4治安 ................................................................................................................ 45 9.5保护水质 ........................................................................................................ 45 9.6防汛 ................................................................................................................ 45 10应急保证措施 .......................................................................................................... 46
10.1塌方 .............................................................................................................. 46 10.2断层 .............................................................................................................. 47 10.3溶洞 .............................................................................................................. 47 10.4涌水 .............................................................................................................. 48 10.5停电 .............................................................................................................. 49 11附图、表 .................................................................................................................. 49
11.1主要施工机械设备表 ................................................................................... 49 11.2测量检测仪器设备表 ................................................................................... 51 11.3劳动力计划表............................................................................................... 51 11.4资金流估算表表 ........................................................................................... 52 11.5施工总体计划表 ........................................................................................... 53 11.6工程进度计划网络图 ................................................................................... 54 11.7分项工程进度斜率图 ................................................................................... 55 11.8工程管理曲线............................................................................................... 56 11.9施工场地平面布置图 ................................................................................... 57 11.10主洞爆破设计图 ......................................................................................... 58 11.11 支洞爆破设计图 ........................................................................................ 60 11.12设计断面图 ................................................................................................ 62
2
1编制依据 1.1招标文件
1.2XX水电站引水隧洞设计图纸
1.3现行水利水电施工规范、验收标准、技术规范等 1.4现场施工技术调查报告,设计文件审核记录 2编制原则
2.1遵守招标文件及施工合同书各项条款的原则。严格按招标文件及施工合同书的规定,做到统一标准,规范编制。
2.2文明施工,保护环境,执行国家和当地政府的各项环保法规,制定严格的环保措施。
2.3坚持施工技术的先进性、针对性,施工管理的科学性、有效性,做到技术先进、设备齐全、科学合理、经济实用。
2.4实施项目法管理,通过对劳力、设备、材料、资金、技术、方案、时间与空间条件的优化配臵,并通过自始至终对施工现场进行全过程严密监控,实施全方位动态管理,确保实现质量、工期、安全、成本及社会信誉的预期目标。
2.5遵循企业管理标准,优质、高效、重信、守诚,完成业主要求的质量目标。 2.6坚持施工过程严格管理的原则。在施工过程中,严格执行业主及监理工程师的指令。 3工程概况 3.1综合概述 3.1.1地形地貌
本区处于昆仑-秦岭褶皱系南秦岭下古生代褶皱带的东南部,属地槽地形。工程区域无大的活断层存在,区域内地质构造稳定,区域构造对工程构造无大的影响。本区山峰高程多在700-1000m以上,为中低山区,山体陡峻,山体植被发育,进洞口坡体较陡,岩石裸露,利于进洞。 3.1.2工程地质
(1)本区处于昆仑-秦岭褶皱系南秦岭下古生代褶皱带的东南部。工程区域
3
无大的活断层存在,区域内地质构造稳定,区域构造对工程构造无大的影响。
隧洞所穿地层主要以奥陶系泥质板岩为主,局部为辉长岩和寒武~奥陶系的炭质、硅质、泥质板岩,岩层走向与洞线交角较大,有利于洞室稳定。
(2)隧洞围岩以Ⅲ-Ⅳ类为主,Ⅲ类围岩强度较高,完整性相对较好,成洞条件和稳定性均好,Ⅳ类围岩,稳定性较差,需考虑适当的支护措施。隧洞进、出口洞脸边坡岩体比较破碎属Ⅵ类围岩,断面成型差,特别是Ⅳ标XX支洞进口,成洞条件极差,需要进行技术处理。 3.1.3地震
本区域地震基本烈度为Ⅵ度。 3.1.4气象水文
当地属北亚热带边缘湿润季风气候区,气候温和,四季分明,雨量充沛,无霜期长,多年平均气温12℃,极端最低温度-15℃,极端最高温度37.8℃,雨季主要集中在4~10月份,多年平均降水量1012.2mm,主要河道:南江河,常年水位1.5m,百年最大洪水位6m。 3.1.5主要工程数量
开挖工程数量表 序号 1 2 3 4 5 隧洞名称 Ⅲ标 Ⅳ标 XX支洞 XX支洞 合计 起点里程 K3+000 K5+000 Z0+000 Z0+000 终点里程 K5+000 K7+060 Z0+211.82 Z0+154.68 长度(m) 2000 2060 211.82 154.68 开挖断 面类型 圆形 圆形 门墙式 门墙式 延米工 程量(m) 26.4208 26.4208 18.4193 18.4193 3总开挖 量(m) 52841.6 54426.85 3901.576 2849.XX7 114019 3
衬砌混凝土工程数量表
序
隧洞名称 起点里程 终点里程 4
长度(m) 开挖断 延米工 总喷砼
号 1 2 3 Ⅱ号隧洞 Ⅲ号隧洞 合计 K3+000 K5+000 K5+000 K7+060 2000 2060 4060 面类型 圆形 圆形 程量(m) 6.5345 6.5345 3量(m) 13069 13461 26530 3
喷射混凝土工程数量表
序隧洞名称 号 1 2 3 Ⅱ号隧洞 Ⅲ号隧洞 合计 K3+000 K5+000 K5+000 K7+060 2000 2060 4060 起点里程 终点里程 长度(m) 面类型 圆形 圆形 程量(m) 3开挖断 延米工 总喷砼 量(m) 1574 992 5266 3另:喷设砼数量暂按投标文件工程量清单计列。 3.2施工条件
3.2.1交通及施工场地
镇坪县XX水电站工程位于陕西省安康市镇坪县牛头店境内,距牛头店镇3公里,镇坪县30公里,平利县80公里,安康市160公里,平镇公路从工程区右边通过交通较为便利。
Ⅲ标XX施工便道业主已修通,在现有的基础上进行路面改善即可使用;Ⅳ标XX施工便道为既有乡村道路,路面宽度能满足使用需求,坡度较陡,黄粘土路面,建设指挥部协调使用,进驻施工后对路面必须进行改造。 3.2.2施工用电、通讯
施工用电由业主接到施工现场,送至距支洞口100m左右,提供低压端使用接口。每个项目队作业区各预备180kw备用电源,以保证洞内供电正常。高压线路应与低压线路分开架设,同时高压线路架设高度在3m以上。洞内管线布臵图如下:
5