目 录 第一章 对招标文件的响应性 ................................................................................................................ 4 一、编制依据 ...................................................................................................................................... 4 二、对招标文件的响应性 .................................................................................................................. 4 第二章 工程概况及项目特点 ................................................................................................................ 4 一、工程概况 ...................................................................................................................................... 4 二、工程改造施工范围 ...................................................................................................................... 5 三、本工程施工的特点、重点及难点分析 ...................................................................................... 5 第三章 施工部署 .................................................................................................................................... 6 一、深化设计阶段 .............................................................................................................................. 6 二、材料的供应阶段 .......................................................................................................................... 6 三、生产加工阶段 .............................................................................................................................. 6 四、现场安装阶段 .............................................................................................................................. 6 五、工程清理验收及撤场阶段 .......................................................................................................... 7 第四章 施工现场总平面布置 ................................................................................................................ 7 一、施工总平面布置说明 .................................................................................................................. 7 二、临时用水、电容量的要求 .......................................................................................................... 8 三、施工总平面布置图(详见后附图) .............................................................................................. 9 第五章 各分部分项工程主要施工方案 ................................................................................................ 9 一、总体施工工艺概述 ...................................................................................................................... 9 二、预埋件、构件加工 .................................................................................................................... 11 三、施工测量放线 ............................................................................................................................ 11 四.龙骨型材安装 ............................................................................................................................ 14 五、转接件施工 ................................................................................................................................ 15 六、埋件复核、补埋 ........................................................................................................................ 16 七、铝板幕墙施工工艺 .................................................................................................................... 17 八、幕墙注胶及清洗措施 ................................................................................................................ 22 九、施工现场成品保护措施 ............................................................................................................ 23 十、铝合金门窗安装工艺 ................................................................................................................ 24

1

十一、铝合金百叶窗安装工艺 ........................................................................................................ 27 十二、脚手架使用与技术要求 ........................................................................................................ 29 十三、材料、构件专项测试方案 .................................................................................................... 30 十四、玻璃雨蓬施工工艺 ................................................................................................................ 31 十五、金属扶手栏板施工工艺 ........................................................................................................ 32 十六、安全施工技术方案 ................................................................................................................ 33 第六章 冬雨季、防台风及防雷施工保证措施 .................................................................................. 34 一、冬季施工措施 ............................................................................................................................ 35 二、雨季施工措施 ............................................................................................................................ 35 三、防台风措施 ................................................................................................................................ 36 四、防雷措施 .................................................................................................................................... 36 第七章 施工质量控制及材料、设备质量保证措施 .......................................................................... 36 一、质量目标 .................................................................................................................................... 36 二、质量控制、质量检验计划 ........................................................................................................ 37 三、质量保证体系 ............................................................................................................................ 37 四、施工质量保证措施 .................................................................................................................... 39 五、材料、设备质量保证措施 ........................................................................................................ 39 第八章 施工难点、质量通病防治及相应对策 .................................................................................. 42 一、测量放线定位 ............................................................................................................................ 42 二、预(后)置埋件施工 ................................................................................................................ 42 三、支座节点紧固 ............................................................................................................................ 43 四、横梁与立柱连接节点 ................................................................................................................ 43 五、横梁与立柱连接间隙 ................................................................................................................ 44 六、横梁、窗框排水、泄水 ............................................................................................................ 44 七、铝板及铝框 ................................................................................................................................ 44 八、装饰面板板块组件 .................................................................................................................... 45 九、胶缝质量 .................................................................................................................................... 45 十、封边处理 .................................................................................................................................... 45 第九章 施工进度计划和保证措施、施工进度网络图 ...................................................................... 46 一、施工总工期 ................................................................................................................................ 46

2

二、进度保证措施 ............................................................................................................................ 46 三、施工进度网络图(详见后附图) ................................................................................................ 49 第十章 拟投入的主要施工机械设备及材料供应计划 ...................................................................... 49 一、拟投入本工程的主要施工机械设备配备计划 ........................................................................ 49 二、拟投入本工程的主要质量检验和测试仪器配备计划 ............................................................ 49 三、机具操作管理条例 .................................................................................................................... 49 四、主要物资进场计划 .................................................................................................................... 49 第十一章 劳动力安排计划 .................................................................................................................. 50 一、劳动力安排计划 ........................................................................................................................ 50 二、劳动力计划表 ............................................................................................................................ 51 第十二章 安全文明施工、环境保护保证措施 .................................................................................. 51 一、安全文明施工目标 .................................................................................................................... 51 二、安全生产保证措施 .................................................................................................................... 51 三、文明施工保证措施 .................................................................................................................... 57 四、环境保护保证措施 .................................................................................................................... 57 第十三章 项目管理班子配备情况及技术力量 .................................................................................. 58 第十四章 售后服务措施及四性检测相应承诺 .................................................................................. 61 一、售后服务措施 ............................................................................................................................ 62 二、幕墙四性检测及相应承诺 ........................................................................................................ 63 附件一:拟投入本工程的主要施工机械设备配备计划 .................................... 错误!未定义书签。 附件二:拟投入本招标项目的试验和检验仪器设备表 .................................... 错误!未定义书签。 附件三:劳动力计划表 ........................................................................................ 错误!未定义书签。 附件四:临时用地表 ............................................................................................ 错误!未定义书签。 附件五:施工进度计划(网络)图 .................................................................... 错误!未定义书签。 附件六:施工现场平面布置图 ............................................................................ 错误!未定义书签。

3

第一章 对招标文件的响应性

一、编制依据

1、****工程施工招标文件及工程量清单; 2、****工程设计施工图及补充答疑文件;

3、有关国家、浙江省、宁波市有关的施工技术规范、标准规程等技术性文件; 4、浙江省及宁波市建设工程现场文明施工管理实施细则;

5、公司ISO9002企业质量标准文件及标准化现场施工管理有关细则; 6、施工现场踏勘情况; 7、工程本身的特点、环境等;

二、对招标文件的响应性

我公司积极响应招标文件规定的技术及商务条款内容,为表示我公司的决心和实力,如果达不到招标文件技术及商务条款的要求,我公司愿按相关承诺及商务报价文件的说明之条款予以罚款,如质量达不到要求,愿无条件予以返工,直至达到招标文件的质量要求为止。 1、工期承诺:

150日历天,且必须满足总承包施工工期的整体要求,延误合同工期愿按合同金额限额的2%处罚。 2、质量目标

达到按国家施工验收规范一次性验收合格,并与主体工程质量同步。未达到按国家验收规范一次性验收合格,愿按合同金额限额的1.0%处罚。 3、安全、文明施工承诺

同施工总承包单位安全要求(总承包单位安全要求为在合格标准前提下,并达到市安全文明施工标化工地),力争省文明标化工地。未按照承诺标准实施的,愿按合同金额限额的15%处罚。

4、项目负责人及主要管理人员到位承诺:

确保项目负责人及主要管理人员到位率100%,如未达到承诺要求,愿按投标文件规定的合同金额限额的7.5%处罚。

五、同意本次招标文件中的所有商务合同及技术条款。

第二章 工程概况及项目特点

一、工程概况

1、招标人:**** 2、招标代理人:*** 3、项目名称:*** 4、建设地点:****

4

5、建设规模:幕墙面积约9288㎡,门窗面积约11000㎡

6、招标范围:幕墙专业施工图纸范围内的所有门窗幕墙工程,包括幕墙、门窗、雨棚等(详见施工图纸)

7、工程质量:达到国家幕墙专业施工验收规范要求并达到一次性验收合格,达到幕墙专项测试、节能专项验收和各项试验标准,并配合总承包单位达到甬江杯幕墙相关评审标准。

8、工期要求:必须满足总承包施工进度要求,其中预埋工作须跟进土建结构施工进度,确保各单体中间结构验收合格后开始至幕墙分部分项工程验收合格工期为A楼135日历天、B楼105日历天、C楼115日历天、D楼135日历天、E楼165日历天

9、安全要求:同施工总承包单位安全要求(总承包单位安全要求为在合格标准前提下,并达到市级安全文明标化工地),力争省文明标化工地

二、工程改造施工范围

****工程施工图及工程量清单范围内工程施工。

具体内容包括:幕墙专业施工图纸范围内的所有门窗幕墙工程,包括幕墙、门窗、雨棚等工程。

三、本工程施工的特点、重点及难点分析

(一)工程特点

1、本工程幕墙体量较大,总体施工面积达到幕墙约9288㎡,门窗约11000㎡。 2、立面效果丰富,主楼大面通过铝合金凸窗和凹窗与铝板幕墙的进出关系,营造出立面的堆砌感和强烈的视觉效果。

3、本次工程施工范围及工艺较多,涵盖金属扶手带栏杆、铝板幕墙、铝合金百叶、金属固定窗、钢化玻璃雨棚、金属推拉窗等,施工中必须狠抓每项分部分项工程工艺及质量。

4、本工程场内运输方便,施工面较多,便于开展大面积施工和流水作业。 5、本工程工期较紧。 (二)工程重点、难点

1、本工程幕墙体量较大,施工工期要求较短,必须合理安排协调各种材料的进场时间、施工班组人员的调配,精心组织现场施工安装进度计划。

2、针对本工程幕墙体系众多,应充分协调管理各种不同的幕墙材料现场堆放,避免现场长距离二次搬运。

3、建筑结构体型的复杂性和立面形式的丰富性对幕墙安装较常规建筑要求更高,同时要求土建结构的施工偏差在允许范围内。

4、考虑到本工程幕墙设计多采用开模铝型材,现场的深化设计尤为重要。

5