高支模方案内容 - 图文

2019-04-15 14:20

目 录

1、工程概况 .................................................................................................................................................. 3 2、编制依据 .................................................................................................................................................. 3 3、施工准备 .................................................................................................................................................. 4

3.1技术准备 ......................................................................................................................................... 4 3.2物资准备 ......................................................................................................................................... 4 3.3劳动力准备 ..................................................................................................................................... 4 4、支撑方案 .................................................................................................................................................. 4

4.1模板及支撑架的材料选择 ............................................................................................................. 4 4.2支撑系统的设计 ............................................................................................................................. 5 4.3通用布置 ......................................................................................................................................... 7 5、高支模的安装 .......................................................................................................................................... 8

5.1施工顺序 ......................................................................................................................................... 8 5.2支撑架搭设 ..................................................................................................................................... 8 5.3模板安装 ......................................................................................................................................... 9 5.4验收及拆除的批准程序 ............................................................................................................... 10 5.5模板工程质量保证措施 ............................................................................................................... 10 6、高支模的拆除 ........................................................................................................................................ 11

6.1支顶、模板的拆除 ....................................................................................................................... 11 6.2模板的清理维修、存放 ............................................................................................................... 12 7、高支模施工的安全管理 ........................................................................................................................ 12

7.1高支模系统施工管理机构 ........................................................................................................... 12 7.2支模管理机构的职责与分工 ....................................................................................................... 13 7.3高支模的安全管理措施 ............................................................................................................... 13 8、监测措施 ................................................................................................................................................ 14 9、针对浇捣砼输送制定的安全措施 ........................................................................................................ 15

9.1施工部署 ....................................................................................................................................... 15 9.2施工方法 ....................................................................................................................................... 15 10、安全文明施工措施 .............................................................................................................................. 16

10.1预防坍塌事故的安全技术措施 ................................................................................................. 16 10.2预防高空坠落事故的安全技术措施 ......................................................................................... 17 10.3预防触电措施 ............................................................................................................................. 18 10.4预防火灾措施 ............................................................................................................................. 18 10.5文明施工措施 ............................................................................................................................. 19 11、应急救援预案 ...................................................................................................................................... 19

11.1应急救援机构 ............................................................................................................................. 19 11.2应急救援机构职责 ..................................................................................................................... 19 11.3应急救援工作程序 ..................................................................................................................... 20 11.4应急救援装备 ............................................................................................................................. 20 11.5应急救缓药品 ............................................................................................................................. 20 11.6应急救援措施 ............................................................................................................................. 20 12、高支模验算书 ...................................................................................................................................... 24

12.1支模方案的计算说明 ................................................................................................................. 24 12.2 250*600mm梁模板(后浇带位置),高度5.92m钢管支撑计算书 ....................................... 24

1

12.3 300*900mm(边梁)模板,高度5.92m钢管支撑计算书 ........................................................ 31 12.4 350*1100mm梁模板,高度5.92m钢管支撑计算书 ............................................................. 40 12.5 120mm厚楼板(后浇带位置),高度5.92m支撑计算书 ..................................................... 49 13、附图...................................................................................................................................................... 55

13.1四层梁板高支模支撑系统平面布置图 ..................................................................................... 55 13.2四层梁板高支模支撑系统剪力撑布置图 ................................................................................. 57 13.3四层梁板高支模支撑系统A-A剖面示意图 ............................................................................. 58 13.4四层梁板高支模支撑系统B-B剖面示意图 ............................................................................. 59 13.5支撑体系纵横水平拉杆与结构柱抱箍扣接节点大样图 ......................................................... 60

2

1、工程概况

1.工程名称:中国科学院广州生物医药与健康研究院研究生公寓 2.工程地点:广州市科学城开源大道190号

3.工程规模:本工程为1栋地下1层,地上11层,总建筑面积约25032平方米,混凝土框架结构,建筑总高为37.5米的公寓。

4.结构类型:钢筋混凝土框架剪力墙结构

5.建设单位:中国科学院广州生物医药与健康研究院 6.设计单位:广东工业大学建筑设计研究院 7.勘测单位:广州中科地化环保工程有限公司 8.监理单位:广州市城市建设工程监理公司 9.施工单位:广东省第一建筑工程有限公司

公寓楼地下1层,地上11层,负一层层高3.95m;群楼中的1层层高4.3m, 2层阶梯教室及多功能厅层高5.7~5.92m;塔楼中2层至11层标准层层高2.85m.

本高支模专项施工方案编制对象部位如下: 序号 1 2 3 4 部位 5~14轴×L~M轴裙楼 (相对标高:4.3m~10.22) 5~14轴×L~M轴裙楼 (相对标高:4.3m~10.22) 5~14轴×L~M轴裙楼 (相对标高:4.3m~10.22) 5~14轴×L~M轴裙楼 (相对标高:4.3m~10.22) 支模高度(m) 5.7~5.92 5.7~5.92 5.7~5.92 5.7~5.92 梁截面(mm) 350×1100 300×900 250×600 250×500 板厚(mm) 120 120 120 120 2层梁板 (板厚100mm)

梁最大跨度(m) 支撑基础 14.6 2、编制依据

为了保证本工程超重支模施工安全,根据《广东省建设工程高支撑模板系统施工安全管理办法》以及建设部关于《危险性较大工程安全专项施工方案编制及专家论证审查办法》的要求,加强施工安全的管理,按相关规定特编制本专项施工方案。方案编制计算依据如下:

(1)建设部建质[2004]213号文件。 (2)广州市建委有关高支模的规定。

(3) 广东工业大学建筑设计研究院的施工图纸;

(4)《建筑施工计算手册》(ISBN-7-11-04626-2江正荣编著); (5)《混凝土结构工程施工质量验收规范》(GB50204-2002); (6)《建筑施工模板安全技术规范》(JGJ162-2008) (7)《建筑结构荷载规范》(GB50009-2012);

3

(8)《建筑施工安全检查标准》(JGJ59-2011); (9)《建筑施工高处作业安全技术规范》(JGJ80-91)

(10)《建筑施工扣件式钢管脚手架安全技术规范》(JGJ130-2011) (11) 本方案脚手架采用一洲计算软件进行验算。

3、施工准备 3.1技术准备

在施工前进行图纸会审及完善施工组织设计方案这两项工作,并组织施工人员认真学习施工图纸、会审记录、施工方案和施工规范等技术文件,做好三级安全技术交底工作,减少和避免施工误差。

3.2物资准备

(1)材料准备:确保材料质量合格,材料供应满足使端面等的偏差应符合规范的规定;钢管宜涂有防不锈漆;旧扣件使用前应进行质量检查,有裂缝、变形的严禁使用,出现滑丝大螺栓必须更换;新、旧扣件均应进行防锈处理,并对多次使用的受力材料作必要的强度测试。

(2)机具准备:根据施工机具需用量计划,做好机械的租赁和购买计划,并做好进场使用前的检验、保养工作,确保运转正常。

(3)周转材料准备:做好模板、钢管支顶等周转料的备料工作,分批分期进场。

3.3劳动力准备

(1)根据开工日期和劳动力需要量计划,组织工人进场,并安排好工人生活。水、电管线架设和安装已完成,能够满足工程施工及工程管理、施工人员生活的用水、用电需要。

(2)做好施工人员进场的安全、质量、防火、文明施工等教育工作,进行岗前培训,对关键技术工种必须持证上岗,按规定进行三级安全技术交底,交底内容包括:施工进度计划;各项安全、技术、质量保证措施;质量标准和验收规范要求;设计变更和技术核定等。必要时进行现场示范,同时健全各项规章制度,加强遵纪守法教育。

4、支撑方案

4.1模板及支撑架的材料选择

支顶系统主要材料如下:

(1)模板均采用915mm×1830mm×18mm(厚)胶合板; (2)木枋:统一采用50×100mm木枋(材质为松木); (3)支撑系统:Φ48×3.2mm钢管及配件;

(4)纵横水平拉杆、纵横向剪刀撑:选用Φ48×3.2mm钢管及其配件; (5)垫板:采用钢管配套底托,垫板采用50mm×100mm双木方。

4

4.2支撑系统的设计

高支模模板、支架系统设计一览表1: 支撑系统 计算梁截面尺序施工部位 号 层高 类型 (mm) (m) (mm) 构件 寸或板厚高度 板厚支撑系统组合 间距(m) 1 裙楼 四层梁 裙楼 四层梁 裙楼 四层梁 裙楼 四层梁 裙楼 四层板 裙楼 四层板 5.92 框架梁 250×600 5.32 120 梁底2立杆@900 @0.9 跨度方向@1100 梁底2立杆@900 @0.9 跨度方向@900 梁底2立杆@600 @0.6 跨度方向@900 梁底2立杆@900 @0.9 跨度方向@900 钢管间距900, @0.9 纵距900 钢管间距1100, 纵距900 @1.1 间距(m) @1.1 1.5 次龙骨木枋@300 主龙骨双钢管 次龙骨木枋@300 主龙骨双钢管 梁截面≤0.15m2 (m) 设(mm) 搭设 梁侧 横向纵向步距梁(板)底龙骨布适用范围 备注 (mm) (后浇带位置) 梁截面≤0.15m22 通过调整可调2 2 5.92 框架梁 250×600 5.32 120 @0.9 1.5 3 5.92 框架梁 300×900 5.02 120 @0.9 1.5 次龙骨木枋@300 0.15 m<梁截面≤0.27m主龙骨双钢管 (边梁) 次龙骨木枋@200 主龙骨双钢管 板底龙骨木枋@400, 主龙骨双钢管 2托座来满足支模高4 5.92 框架梁 350×1100 4.82 120 @0.9 1.5 梁截面=0.385m 5 5.92 板 120 5.8 120 @0.9 1.5 120mm板 度要求。 6 5.92 板 120 5.8 120 @0.9 板底龙骨木枋@400, 1.5 120mm板(后浇带位置) 主龙骨双钢管 注:1)梁底、梁侧模板均采用18mm厚胶合板;木枋均采用50×100mm;钢管均采用υ48×3.2mm;现场均采用Φ12对拉螺杆。 2)各类型梁支撑验算时,均考虑梁两侧楼板荷载的影响;模板均采用18mm厚胶合板;木枋均采用50×100mm。

3)各楼层的梁板支模支撑系统参照以上梁布置施工。

广东省第一建筑工程有限公司 5 - -


高支模方案内容 - 图文.doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:今天我是升旗手阅读测试题(附答案)

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: