X+方向,高度 H= 600

Fl = pj*Al = 238.35* 0.60= 143.01

0.7*βhp*ft*(at+ab)*ho/2 = 0.7*1.00*1270.94*(0.60+1.70)*0.55/2 = 562.71KN

本方向冲切验算满足 X-方向,高度 H= 600

Fl = pj*Al = 152.59* 0.60= 91.55

0.7*βhp*ft*(at+ab)*ho/2 = 0.7*1.00*1270.94*(0.60+1.70)*0.55/2 = 562.71KN

本方向冲切验算满足 Y+方向,高度 H= 600

Fl = pj*Al = 152.59* 0.60= 91.55

0.7*βhp*ft*(at+ab)*ho/2 = 0.7*1.00*1270.94*(0.60+1.70)*0.55/2 = 562.71KN

本方向冲切验算满足 Y-方向,高度 H= 600

Fl = pj*Al = 238.35* 0.60= 143.01

0.7*βhp*ft*(at+ab)*ho/2 = 0.7*1.00*1270.94*(0.60+1.70)*0.55/2 = 562.71KN

本方向冲切验算满足

四边冲切验算 H = 600.

Fl = N-pk*(bc+2*h0)*(hc+2*h0)

= 1000.00- 189.0*(600.0+2* 550.0)*(600.0+2* 550.0)*1e-6 = 453.7Kn Fr = 0.7*Bhp*ft*am*h0

= 0.7*1.00* 1270.9*(600.0+ 600.0+2* 550.0)* 550.0*1e-6 = 2250.8Kn

34 哈尔滨工程大学继续教育学院

毕 业 设 计 用 纸

四边冲切验算满足

X+方向,高度 H= 600mm

Fl = pj*Al = 238.35* 0.60= 143.01

0.7*βhp*ft*(at+ab)*ho/2 = 0.7*1.00*1270.94*(0.60+1.70)*0.55/2 = 562.71KN

本方向冲切验算满足 X-方向,高度 H = 600mm

Fl = pj*Al = 152.59* 0.60= 91.55

0.7*βhp*ft*(at+ab)*ho/2 = 0.7*1.00*1270.94*(0.60+1.70)*0.55/2 = 562.71KN

本方向冲切验算满足 Y+方向,高度 H= 600mm

Fl = pj*Al = 152.59* 0.60= 91.55

0.7*βhp*ft*(at+ab)*ho/2 = 0.7*1.00*1270.94*(0.60+1.70)*0.55/2 = 562.71KN

本方向冲切验算满足 Y-方向,高度 H= 600mm

Fl = pj*Al = 238.35* 0.60= 143.01

0.7*βhp*ft*(at+ab)*ho/2 = 0.7*1.00*1270.94*(0.60+1.70)*0.55/2 = 562.71KN

本方向冲切验算满足

独基尺寸 长 宽 高 2500 2500 300 600 600 300 2、剪切验算

b+2*h0 = 1700mm < BB = 2300 Y方向不需要进行抗剪计算: h+2*h0 = 1700mm < HH = 2300

35 哈尔滨工程大学继续教育学院

毕 业 设 计 用 纸

X方向不需要进行抗剪计算: 3、配筋验算

采用GB5007-2002建筑地基基础设计规范,计算公式如下:

12?1(2l?a')(pjmax?pj)?(pjmax?pj)l12

弯矩计算:

MⅠ??? x方向,h0 = 540mm

M = 1/12*a1*a1*[(2l+a`)*1(Pjmax+Pj)+(Pjmax-Pj)*l]

= 0.85*0.85[(2*2.30+0.60)*( 238.3+ 201.9)+( 238.3- 201.9)*2.30]/12 = 142.88KNm

M = 1/12*a1*a1*[(2l+a`)*1(Pjmax+Pj)+(Pjmax-Pj)*l]

= 0.85*0.85[(2*2.30+0.60)*( 139.7+ 176.2)+( 139.7- 176.2)*2.30]/12 = 93.85KNm

y方向,h0 = 540mm

M = 1/12*a1*a1*[(2l+a`)*1(Pjmax+Pj)+(Pjmax-Pj)*l]

= 0.85*0.85[(2*2.30+0.60)*( 139.7+ 176.2)+( 139.7- 176.2)*2.30]/12 = 93.85KNm

M = 1/12*a1*a1*[(2l+a`)*1(Pjmax+Pj)+(Pjmax-Pj)*l]

= 0.85*0.85[(2*2.30+0.60)*( 238.3+ 201.9)+( 238.3- 201.9)*2.30]/12 = 142.88KNm

x方向,h0 = 540mm

M = 1/12*a1*a1*[(2l+a`)*1(Pjmax+Pj)+(Pjmax-Pj)*l]

= 0.85*0.85[(2*2.30+0.60)*( 238.3+ 201.9)+( 238.3- 201.9)*2.30]/12 = 142.88KNm

M = 1/12*a1*a1*[(2l+a`)*1(Pjmax+Pj)+(Pjmax-Pj)*l]

= 0.85*0.85[(2*2.30+0.60)*( 139.7+ 176.2)+( 139.7- 176.2)*2.30]/12 = 93.85KNm

36 哈尔滨工程大学继续教育学院

毕 业 设 计 用 纸

y方向,h0 = 540mm

M = 1/12*a1*a1*[(2l+a`)*1(Pjmax+Pj)+(Pjmax-Pj)*l]

= 0.85*0.85[(2*2.30+0.60)*( 139.7+ 176.2)+( 139.7- 176.2)*2.30]/12 = 93.85KNm

M = 1/12*a1*a1*[(2l+a`)*1(Pjmax+Pj)+(Pjmax-Pj)*l]

= 0.85*0.85[(2*2.30+0.60)*( 238.3+ 201.9)+( 238.3- 201.9)*2.30]/12 = 142.88KNm

配筋计算: M1 = 142.882

AGx = M1/(0.9*h0*fy) = 142882.406/(0.9*0.540*360.) = 816.658mm*mm

M2 = 142.882

AGy = M2/(0.9*h0*fy) = 142882.406/(0.9*0.540*360.) = 816.658mm*mm

M1 = 142.882

AGx = M1/(0.9*h0*fy) = 142882.406/(0.9*0.540*360.) = 816.658mm*mm

M2 = 142.882

AGy = M2/(0.9*h0*fy) = 142882.406/(0.9*0.540*360.) = 816.658mm*mm

X方向配筋 Y方向配筋 816.658 816.658

原钢筋X方向配筋量满足 原钢筋Y方向配筋量满足

37 哈尔滨工程大学继续教育学院

毕 业 设 计 用 纸

计算的配筋方案为: AGx: HRB400 10 @200 AGy: HRB400 10 @200

38 哈尔滨工程大学继续教育学院


实验楼毕业设计计算书(8).doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:张家港华兴电力有限公司二期扩建两台F级(400MW)燃机热...

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: