地铁车站施工组织设计

2019-04-14 11:18

前 言 .................................................................................................................................................................. 1 1 编制依据和工程概况 ..................................................................................................................................... 1 1.1 编制依据 ................................................................................................................................................. 1 1.2 编制原则 ................................................................................................................................................. 1 1.3编制目的 ................................................................................................................................................... 1 1.4 工程简介 ................................................................................................................................................. 2 1.5 工程地质 ................................................................................................................................................. 2 1.6 工程环境 .................................................................................................................................................. 2 1.6.1气候条件 ........................................................................................................................................... 2 1.6.2交通条件 ........................................................................................................................................... 2 1.6.3施工用水、用电、通讯条件 ........................................................................................................... 2 2 专项工作实施方案 ......................................................................................................................................... 3 2.1建(构)筑物保护 ................................................................................................................................... 3 2.2、管线保护制度 ........................................................................................................................................ 3 3 主要施工方案 .................................................................................................................................................. 4 3.1 施工安排 .................................................................................................................................................. 4 3.2 主要施工方法 .......................................................................................................................................... 4 3.2.1、钻孔桩施工 .................................................................................................................................... 4 3.2.2、土方开挖及钢支撑安装 ................................................................................................................ 4 3.2.3、结构施工 ........................................................................................................................................ 4 3.2.4、防水施工 ........................................................................................................................................ 4 3.2.5、基坑回填 ........................................................................................................................................ 5 3.3 主要施工技术 .......................................................................................................................................... 5 3.3.1 围护结构施工 .................................................................................................................................. 5 3.3.2土石方开挖及钢支撑施工 ............................................................................................................... 8 3.3.3车站结构施工 ..................................................................................................................................11 3.3.4混凝土施工工艺流程 ..................................................................................................................... 16 3.3.5混凝土质量控制 ............................................................................................................................. 16 3.3.6浇筑顺序和施工缝留设位置 ......................................................................................................... 17 3.3.7模板支架注意事项 ......................................................................................................................... 17 3.3.8车站防水施工 ................................................................................................................................. 17 3.3.9土石方回填 ..................................................................................................................................... 20 4 施工监控量测 ............................................................................................................................................... 20 4.1、监测项目 .............................................................................................................................................. 21 4.2、监测频率和监测预警控制值 .............................................................................................................. 21 4.3、监测预警值 .......................................................................................................................................... 21 5 工程与试验 .................................................................................................................................................... 22 5.1工程试验 ................................................................................................................................................. 22 5.2、试验资源配备 ...................................................................................................................................... 22 5.3、工地常规试验项目 .............................................................................................................................. 22

5.4、试验质量保证措施 .............................................................................................................................. 23 6 进度计划 ........................................................................................................................................................ 23 6.1 工期目标 ................................................................................................................................................ 23 6.2 进度计划编制原则 ................................................................................................................................ 23 参考文献 ............................................................................................................................................................ 24 致 谢 ................................................................................................................................................................ 25

中国地质大学长城学院2015届毕业论文(设计)

前 言

近年随着城市化进程的加快, 城市人口急剧增多, 国内各大城市的地面交通均面临着巨大的压力,城市轨道交通成为一种有效疏导地面人流和缓解交通堵塞的重要手段, 目前已在国内多个城市中建成并投入运营, 且大多以地下铁道为主。地铁车站投资大、建设时间长,所以在设计时,应仔细论证,选用最经济实用、安全的结构及施工方法。本设计的主要内容从工程地质入手,对地质进行了分析,本工程工程地质条件良好,所以合理规划布局起来也比较容易。本设计基坑围护方法选用永久地下连续墙防护,墙体作为施工后车站结构的一部分,安全性高且经济效益高。对主体结构进行设计、验算,主体结构采用双层双跨岛式站台结构,在经济效益最大化的情况下,能够满足设计的出行量及机构安全性要求。设计最后,摘选了一篇外文文献并作出翻译,内容是有限元分析在结构内力中实际应用的例子。由于本人能力有限,知识上还有一定局限性,望读者批评指正。

1 编制依据和工程概况

1.1 编制依据

(1)青岛市地铁一期工程(3号线)招标文件组成及内容。 (2)与青岛地铁公司签订的施工合同。 (3)《青岛市地铁一期工程(3号线)招标设计》 (4)《青岛市地铁一期工程(3号线)施工图设计》

(5)国家现行的有关工程的设计、施工及验收规范,工程质量检验评定标准合质量管理体系GB/T19001-2000标准 。

(6)国家、青岛市现行的有关施工安全、环境保护、文明施工方面的法规和政策以及GB/T24001-2004标准和GB/T28001-2001标准。

1.2 编制原则

以满足业主要求为目标,在深刻理解本工程特点、重点与难点的基础上,按照“技术领先、资源可靠、施工科学、组织合理、措施得力”的指导思想,遵循人本安全、质量保证、工期保障、技术可靠、经济合理、环保、合规、履约的原则编制本施工组织设计。

1.3编制目的

在满足业主要求的前提下,不断发展完善施工技术,确保工程施工质量达到全优;力争工程施工工

1

中国地质大学长城学院2015届毕业论文(设计)

期超前;对周边环境的影响和扰动控制在最小程度,确保施工影响范围内地面建筑物和地下管线的安全,确保施工过程中无任何安全事故。

1.4 工程简介

车站位于太平角公园内,为地下2层10m岛式车站,采用明挖顺做工法施工,总长为182.7m,车站主体结构基坑标准段宽度17.4m,基坑深度15.2m。围护结构采用φ800@1600(局部@1200、1300、1500)的钻孔桩,φ609(t=14)钢管(第一道)、预应力锚索(第二道、第三道)作为临时支撑。

1.5 工程地质

本站址基坑开挖深度最深约16m,上部覆盖层主要为强风化花岗岩,开挖基坑时,应注意地面沉降及基坑位移变形。基岩为燕山期花岗岩及后期侵入岩脉,局部裂隙发育,需进行爆破开挖。

工程地质评价:冲洪积粉质粘土分布不均匀,砂层零星分布,粉质粘土呈可塑状为主,为弱~微透水层,有一定的承载能力和自稳能力,对站址基坑施工影响较小。砂层中地下水赋水程度中等,对站址基坑施工有较大影响,基坑开挖时,排水可导致基坑周围地面沉降,引起建筑物、道路开裂变形等。本站址主要位于强风化花岗岩中,强风化花岗岩具遇水软化特点,基坑开挖施工时,应做好止水和排水措施,防止受水浸泡。

1.6 工程环境

1.6.1气候条件

青岛属华北暖温带沿海季风区,大陆性气候。受海洋影响,空气湿润、气候温和,雨量较多,四季分明,具有春迟、夏凉、秋爽、冬长的气候特征。年平均风速5.5m/s,瞬时风速大于17m/s的天数为42.83d。年平均受台风侵袭或受台风外围影响达13次;年平均降水量为714mm;年平均气温12.3℃,年各月平均气温8月最高,1月最低,青岛寒潮一般发生在11月~次年2月,平均每年发生4.9次,年均结冰日82天。

1.6.2交通条件

本工程地处青岛市城区内,各施工场地沿香港西路0两侧布置,交通四通八达,较为便利。但由于本合同段工程地理位置特殊,处于青岛市闹市区白天交通流量较大,施工运输车辆尽量安排在夜间运行。

1.6.3施工用水、用电、通讯条件

2

中国地质大学长城学院2015届毕业论文(设计)

施工用水:从每一施工场地位置接DN100主供水管,分别接到施工现场各处及生活办公区,以满足生产及生活的需要。

施工用电:进场前期租用发电机自发电,满足施工围挡和钢筋笼加工等急需用电项目的施工。各施工场地分别配置独立的供电变压器。

通讯条件:本工程位于青岛市城区,通讯条件良好。

2 专项工作实施方案

2.1建(构)筑物保护

本工程主要沿香港西路方向,地面为商业、商务办公、居住和商住用地,原有建筑物调查资料并未进行结构的评估并给出控制要求,建议业主委托具备建(构)筑物评估资质的单位对结构进行详细的评估,提出建(构)筑物的控制要求及采取的措施。

在此基础之上,施工前进一步采用如下措施进行障碍物排查保护。

(1)在工程施工前,成立专门调查小组,在调查前制订详细的调查计划和调查图表,用实地观测、测绘等方法来完成在工程影响范围内既有建(构)筑物的调查工作。

(2)对调查资料进行整理分析,明确各类保护项目的允许变形量,同时妥善保存,以指导工程施工,在需要时可随时查找。

(3)主要调查内容

隧道开挖影响范围内的建(构)筑物的名称、位置、结构类型、建造时间、所属业主,建筑物的用途等,其中构筑物的基础是调查重点。清楚地列出建(构)筑物当前状况,并与已有资料核对。

2.2、管线保护制度

为确保施工区域及周边地下管线安全,必须建立完善的管线保护制度。

(1)详细阅读、掌握设计、建设单位提供的地下管线图纸资料,通过建设单位在工程施工前组织召开各管线单位技术交底会议,收集管线资料。

(2)建立管线安全管理领导小组,定期召开管线安全会议,通报管线的状况,调整管线的保护或通过措施。

(3)针对关键管线建立以地铁风险施工为核心的技术工作会议,讨论总体管线保护措施下的各项管线专项保护措施,包括:燃气、上水、雨水、污水、电信、电力、通信、热力等管线的专项保护措施。

(4)结合施工设计管线图纸,施工前做好管线技术交底工作,并保证其内容传达到每一个人。

(5)管线监测情况定期通报,并随工程进展情况上报监理、业主等单位。 (6)实行“三级预警”制,一旦出现预警情况及时上报。

(7)对受施工影响的地下管线设置若干沉降测点,工程实施中,定期观测管线的沉

3


地铁车站施工组织设计.doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:关于宁波市出口企业品牌建设问题的研究

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: