UFGS 02 66 10 Test Fill
**************************************************************************USACE / NAVFAC / AFCESA / NASA UFGS-02 66 10 (February 2010) -----------------------------Preparing Activity: USACE Superseding UGGS-02 66 10 (April 2006)UNIFIED FACILITIES GUIDE SPECIFICATIONSReferences are in agreement with UMRL dated January 2012**************************************************************************SECTION TABLE OF CONTENTSDIVISION 02 - EXISTING CONDITIONS
SECTION 02 66 10
TEST FILL
02/10PART 1 GENERAL 1.1 REFERENCES
1.2 SYSTEM DESCRIPTION
1.3 SUBMITTALS
1.4 QUALITY ASSURANCE
PART 2 PRODUCTS 2.1 RANDOM FILL 2.2 CLAY BARRIER LAYER
2.3 GEOMEMBRANE
2.4 GEOSYNTHETIC CLAY LINER
2.5 GEOSYNTHETIC DRAINAGE LAYER
2.6 GEOTEXTILE
2.7 GRANULAR DRAINAGE LAYER
2.8 SELECT FILL
2.9 EQUIPMENT
PART 3 EXECUTION 3.1 GENERAL 3.1.1 Location
3.1.2 Size
3.1.3 Slope
3.2 PLACEMENT
3.2.1 Clearing and Grubbing
3.2.2 Subgrade Compaction
3.2.3 Drainage Controls
3.2.4 Anchor Trench
3.2.5 Test Fill Placement
3.2.6 Survey Control Points
3.2.7 Permanent Bench Mark
3.3 TESTS
3.3.1 Random Fill Tests
3.3.2 Clay Barrier Layer Tests