UFGS 02 66 10 Test Fill(11)

2020-12-16 09:44

UFGS 02 66 10 Test Fill

each lift of the granular drainage layer, in accordance with ASTM D422.

3.3.5 Select Fill Tests**************************************************************************

NOTE: The select fill layer placed above

geosynthetic layers can be constructed using both

method and performance specifications. Modify this

paragraph if a method specification will be used.

The first lift of soil placed immediately above a

geosynthetic layer is generally placed with low

ground pressure equipment. No density testing

requirements are generally specified for this first

lift.**************************************************************************A minimum of [2] [_____] sets of classification tests shall be performed on each lift of select fill placed. Classification tests shall be performed in accordance with ASTM D422 and ASTM D4318. A minimum of [5] [_____] density and [5] [_____] moisture content tests shall be performed per lift. Density testing is not required on the first lift of soil placed above a geosynthetic layer.3.3.6 SurveysThe following surveys shall be performed to monitor horizontal and vertical movement of the test fill. The horizontal and vertical accuracy of the surveys shall be to the nearest [0.003] [_____] meter [0.01] [_____] foot.

a. During construction, all installed control points shall be surveyed immediately after each layer is placed.

b. During the post-construction monitoring period, all control points shall be surveyed once every [7] [_____] days.3.3.7 Post-Construction Monitoring

**************************************************************************

NOTE: The duration of post-construction monitoring

depends on the site specific testing which will be

performed. If the only purpose of the test fill is to demonstrate construction methods and monitor for

damage to geosynthetics, no post-construction monitoring period is necessary. A 14 to 60 day

monitoring period is typical if surveys to monitor

for horizontal movement will be performed.**************************************************************************The test fill shall be monitored for [_____] days following construction. The QC Inspector shall inspect the test fill daily and report its condition in the Construction Quality Control Daily Reports. After every

precipitation event, the QC inspector shall inspect the condition of the test fill.

3.3.8 Weekly Reports

Weekly reports shall include test results and survey data related to test fill construction and post-construction monitoring during the previous 7 days. The QC inspector shall certify that the weekly reports are


UFGS 02 66 10 Test Fill(11).doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:2012年最全的职称英语历年真题及答案1

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: