UFGS 02 66 10 Test Fill(8)

2020-12-16 09:44

UFGS 02 66 10 Test Fill

The random fill layer shall extend a minimum of [1.5] [_____] meters [5]

[_____] feet beyond the edge of the upper surface of the test fill.

3.1.3 Slope**************************************************************************

NOTE: In situations where compaction of soil on side slopes is a concern, the specified slope for the test fill should represent the steepest designed

slope.

**************************************************************************The completed slope of each layer in the test fill shall be [_____] horizontal on 1 vertical.

3.2 PLACEMENT**************************************************************************NOTE: Benches and haul roads are other potential

components of a landfill cover that can be modeled

by a test fill. A good deal of construction

activity is required to construct benches. This

increased construction activity may result in damage

to the underlying cover system. The movement of

large vehicles on haul roads may also cause damage to the cover system.**************************************************************************

3.2.1 Clearing and Grubbing

Clear and grub the area beneath the test fill and [3] [_____] meters [10]

[_____] feet beyond the edges of the test fill in accordance with Section 31 11 00 CLEARING AND GRUBBING.3.2.2 Subgrade CompactionAfter clearing and grubbing, the existing landfill surface beneath the test fill and [3] [_____] meters [10] [_____] feet beyond the edges of the test fill shall be compacted as described in Section [31 00 00 EARTHWORK]

[_____].

3.2.3 Drainage Controls

Before beginning construction, construct drainage controls around the test fill to protect it from erosion damage. The drainage control shall be maintained until completion of the post-construction monitoring period.3.2.4 Anchor Trench**************************************************************************

NOTE: Anchor trenches are often not required for

the construction of a test fill. An anchor trench

allows specific interfaces to be tested for

interface stability. Delete this paragraph when an

anchor trench will not be a component of the test

fill.

**************************************************************************Construct an anchor trench along the full width of the top edge of the test


UFGS 02 66 10 Test Fill(8).doc 将本文的Word文档下载到电脑 下载失败或者文档不完整,请联系客服人员解决!

下一篇:2012年最全的职称英语历年真题及答案1

相关阅读
本类排行
× 注册会员免费下载(下载后可以自由复制和排版)

马上注册会员

注:下载文档有可能“只有目录或者内容不全”等情况,请下载之前注意辨别,如果您已付费且无法下载或内容有问题,请联系我们协助你处理。
微信: QQ: